In my control plan, I've included two process steps: one for the dimensions checked at set-up and another step for the (same) dimensions during the actual production run.
In my FMEA, since the same failure modes are going to be associated with the same dimensional characteristics and since these are two distinct processes in the control plan, can avoid duplicating all this information? Or am I not approaching this correctly?
In my FMEA, since the same failure modes are going to be associated with the same dimensional characteristics and since these are two distinct processes in the control plan, can avoid duplicating all this information? Or am I not approaching this correctly?