Mumus
14th September 2007, 11:55 AM
Hi All,
I would appreciate some help from you guys...:)
I have recently interviewed for a QM position and I was informed that I will be invited for a test which includes: gauge R&R, capability studies, PPAP's.
Regarding gauge R&R's: I was told that %R&R is most of the time over 30% which is bad. I do not have a lot of experinece doing R&R's so can somebody give me some advice on how to improve this (some plastic -- injection moulding experience would be beneficial) ? I know that without data is hard to make assumptions but maybe there is somebody who's working/worked in the plastic industry and can share some experience.
Some info for capability studies in the plastic industry would also be greatly appreciated.
Thanks. :agree1:
David DeLong
14th September 2007, 12:03 PM
If one has a rather high R & R, the gauge needs to be reviewed.
If one is using a dial indicator, it must be read perpendicular to the gauge otherwise one can be 1 digit out - either + or - depending upon the angle that it is being read.
Hand held gauges such as micrometer, verniers etc. can be replaced with a variable checking fixture with a setting block. We will eliminate the "feel" and different locations in which we measure.
We could also go 1 digit smaller in resolution.
These are just some thoughts for gauge improvement.
Jim Wynne
14th September 2007, 12:09 PM
Hi All,
I would appreciate some help from you guys...:)
I have recently interviewed for a QM position and I was informed that I will be invited for a test which includes: gauge R&R, capability studies, PPAP's.
Regarding gauge R&R's: I was told that %R&R is most of the time over 30% which is bad. I do not have a lot of experinece doing R&R's so can somebody give me some advice on how to improve this (some plastic -- injection moulding experience would be beneficial) ? I know that without data is hard to make assumptions but maybe there is somebody who's working/worked in the plastic industry and can share some experience.
Some info for capability studies in the plastic industry would also be greatly appreciated.
Thanks. :agree1:
Specific advice is hard to give; the subjects you're dealing with don't lend themselves to quick studies. Insofar as R&R and capability studies, there's nothing in particular about molding that differs significantly from other industries. If you're not already familiar with MSA and capability studies you're probably going to have problems. If you are familiar with those things, you should be OK because the application (molding) doesn't have much effect on application of the tools.
ScottK
14th September 2007, 12:41 PM
Hi All,
I would appreciate some help from you guys...:)
I have recently interviewed for a QM position and I was informed that I will be invited for a test which includes: gauge R&R, capability studies, PPAP's.
Regarding gauge R&R's: I was told that %R&R is most of the time over 30% which is bad. I do not have a lot of experinece doing R&R's so can somebody give me some advice on how to improve this (some plastic -- injection moulding experience would be beneficial) ? I know that without data is hard to make assumptions but maybe there is somebody who's working/worked in the plastic industry and can share some experience.
Some info for capability studies in the plastic industry would also be greatly appreciated.
Thanks. :agree1:
I'm not a gauge R&R expert but I have worked in injection and blow molding and did a lot of capability studies as part of my job. Not PPAP, but we did often do three step mold qualification following and IQ/OQ/PQ process.
Trying to keep it brief:
Pre qualification - review the design and determine critical characteristics (with customer involvement if it was a custom part), determine quality plan.
IQ - check mold, install in press, heat up, shoot some plastic to check flows and such, take a sample when production was satisfied that the process was stable. Check one part from each cavity for all characteristics called out on the drawing. Run various statistics on these figures. it it passes go on to OQ. If it fails, report to production on what needs to be fixed, or change the spec if necessary.
OQ - bring mold to stability (passes first article on quality plan), lock setpoints in on the machine, take samples according to a sample plan during a run (we would typically take a one sample from each cavity every hour for 8 hours). Analyze all variables on the quality plan for the first/middle/last sampels. Analyze all attributes on the quality plan for a sample between first/middle and middle/last. Crunch numbers and generate a report. Report results during design review. Make adjustments as needed, re-do run if necessary. If OK then mold is approved for production.
PQ - this took place over the course of several prodcution runs and we used the inspection data gathered during regular QC functions. We used characteristics required by the quality plan over the course of 3 production runs. If capabilities were consistent then the tool was fully qualified.
honestly, though - we rarely did the PQ part. Only when customers asked for it (and paid for it).
I'm probably leaving some stuff out but this is the bare bones of what we did.
gszekely
17th September 2007, 05:49 AM
Hello Mumus
Inspection criteria, and Gage R&R, in injection molding usually is performed for dimensional and visual characteristics, but for destructive measurements can be performed as well.
In my opinion the molding process, having good molds, machines, set up, and stable process, is fairly capable, with small variation.
If all the above is in place, usually the following mistakes are made during gage R&R:
- samples are not collected correctly. Assuming that the process variation is small, let say 30% of tolerance, assuming a tolerance for a part of 100mm +/- 0,2mm, then the stable process variation itself will be 0,12 mm(usually less, in order of hundrets of mm.) The samples then are collected from this range, while during set up, or mass production , you will produce parts out of tolerance or at least close to upper or lower tolerance, which in my opinion are part of the process, or at least you have to measure them and give indications, in which direction the settings should go. If the process under controll, does not produce parts to cover the whole tolerance range, usually I will take parts from start ups, and try to select them in such a way, to have at least covered the tolerance range, and have at least one or two samples out of tolerance, close to upper or lower limit.
As far as I know the R&R study results are reported to tolerance range and process variation range. If you chose samples from a process with a very small variation compared to your tolerance, then you will have poor results, while your measurement system in real life is capable.
Shortly:
- collect samples for study from set up parts as well
- chose samples in such a way that there is a significant part to part variation, for example having the sample above:99.75, 99.8, 99.85, 99.9, 99.95, 100.00, 100.05 and so on
If all the above are in place then we can go to measuring device, and fixtures.
First of all, your measuring device for the sample above should have a resolution capability of at least 10% of the tolerance range, ex. 0.04mm, to be able to indetify the part to part variation.
Fixture should be accurate enough to correct, eliminate, minimize the placement erors made by operators.
Everybody should be trained, and use correctly the measuring instrument.
If you have a measuring program that should be build up correctly, datumes or reference points corrected in each routine.
That's all what comes in my mind by first, attribute and destructive gage R&R, is an other story.
For process validation, adding to the good advice alrady given:
- mold qualifications or prequalifications should be run at mold manufacturer, and at least a half capability run done there, before takin it to your shop
- Injection molding machine technical specs and it's capability of meeting these, adequate screw for some resins, and raw material drying are some of the kes issues
- proper set up, and processing window, I have posted good sites and a set up sheet in several threads, see some:
http://elsmar.com/Forums/showthread.php?p=204687#post204687
http://elsmar.com/Forums/showthread.php?p=198126#post198126
http://elsmar.com/Forums/attachment.php?attachmentid=7063&d=1184139212
http://elsmar.com/Forums/attachment.php?attachmentid=6491&d=1172333050
There is a good guidance on the the ghtf.org site, document posted in other threds, you can find here:
http://elsmar.com/Forums/fileslist.php?mode=allfiles&sortby=filename&pageamt=2&criteria=ghtf
http://elsmar.com/Forums/showthread.php?p=204687#post204687
Most probably I may have made mistakes in my advice, compared to the theorethical R&R study rules, but this works in real life, and the gurus in the cove will correct me. :)
Good luck and let us know the results of your interview.
BR
György