16th December 2007, 12:56 AM
Hi,
Does Anybody have information/example on how to do the IQ, OQ, PQ for Laboratory equipment? (eg. incubator)
Marc
16th December 2007, 12:59 AM
Please define IQ, OQ, and PQ.
badtzcroc
16th December 2007, 01:32 AM
Installation Qualification, Operation Qualification, Performance Qualification
harry
16th December 2007, 01:51 AM
Installation Qualification, Operation Qualification, Performance Qualification
Are they collectively referred to as Validation? Attached is an article on validation of autoclave.
badtzcroc
16th December 2007, 02:12 AM
Thank you Harry.
Do you have example on how it is done (documents that related and forms that need to filled up)?
Stijloor
16th December 2007, 02:28 AM
Thank you Harry.
Do you have example on how it is done (documents that related and forms that need to filled up)?
Here (http://www.tovatech.com/iq_oq_pq_home.html) is a company that sells a software "kit" to do it yourself.
Here (http://www.yvqm.com/free_sample/VAL-025%20sample.pdf) is a "free sample" of an SOP.
Attached are 3 articles about validating ( IQ, OQ and PQ) autoclaves.
This may not exactly what you are looking for but perhaps a start.
Stijloor.
yodon
17th December 2007, 04:50 PM
Thank you Harry.
Do you have example on how it is done (documents that related and forms that need to filled up)?
At the most basic level, you'll want (approved) protocols and some kind of a test report. How you achieve this is up to you. Typically, I think, most companies have a master validation plan that provides the guidance.