Inputs please...
" We are into design of pressure vessels, shop
fabricated tanks, steel structures for our fabrication unit".
Could anyone explain how we can comply with Design and Development V& V
Current System here is:
Design Verification
The DE shall hand over the calculations (original and check print) to the SDE to ensure that the engineering procedure is fulfilled and client requirements are met.
Design Validation
Design validation will be done through the following:
Through software whose results have earlier been validated.
Through performing manual calculations and comparing the results with
software’s output or Code examples.
Are we complying or not? please advice
" We are into design of pressure vessels, shop
fabricated tanks, steel structures for our fabrication unit".
Could anyone explain how we can comply with Design and Development V& V
Current System here is:
Design Verification
The DE shall hand over the calculations (original and check print) to the SDE to ensure that the engineering procedure is fulfilled and client requirements are met.
Design Validation
Design validation will be done through the following:
Through software whose results have earlier been validated.
Through performing manual calculations and comparing the results with
software’s output or Code examples.
Are we complying or not? please advice