View Full Version : Deming PDCA Cycle Automotive Mfg Sector Example


Ganesh
19th July 2008, 07:09 AM
Dear Sirs,

I am searching for an elaborate example of PDCA (Deming cycle) in Automitve Manufacturing Sector.

Could any one revert with an example of PDCA Cycle (MS ppt format)

Thanks & Regards

Ganesh

Umang Vidyarthi
19th July 2008, 10:36 AM
Dear Sirs,

I am searching for an elaborate example of PDCA (Deming cycle) in Automitve Manufacturing Sector.

Could any one revert with an example of PDCA Cycle (MS ppt format)

Thanks & Regards

Ganesh

Welcome to the cove Ganesh, :bigwave:

Dr. Deming always referred to PDCA, as 'Shewhart cycle'. Later Dr.Deming modified it as PDSA (Plan-Do-Study-Act).

There is loads of information here on the subject. Just click on the 'Search' button on the right hand of the bar at the top, and type your querry to reach the pandora box of information.

Umang :D

Patricia Ravanello
19th July 2008, 02:29 PM
Dear Sirs,

I am searching for an elaborate example of PDCA (Deming cycle) in Automitve Manufacturing Sector.

Could any one revert with an example of PDCA Cycle (MS ppt format)

Thanks & Regards

Ganesh

Hi Ganesh,
I've attached a model that I've created to demonstrate the sequence of the organization's 12 Key Processes relative to the Plan-Do-Check-Act cycle. This was originally created for an automotive manufacturer.

Your procedural level documents should be fairly similar...it could be adapted.

Hope this helps.
Patricia

Umang Vidyarthi
19th July 2008, 11:41 PM
Hi Ganesh,
I've attached a model that I've created to demonstrate the sequence of the organization's 12 Key Processes relative to the Plan-Do-Check-Act cycle. This was originally created for an automotive manufacturer.

Your procedural level documents should be fairly similar...it could be adapted.

Hope this helps.
Patricia

Nice job Patricia. A very neat presentation. :applause:

Umang

Patricia Ravanello
30th July 2008, 02:23 PM
Dear Sirs,

I am searching for an elaborate example of PDCA (Deming cycle) in Automitve Manufacturing Sector.

Could any one revert with an example of PDCA Cycle (MS ppt format)

Thanks & Regards

Ganesh

Did my attachment help you at all? Is it what you were looking for?

Patricia

Ganesh
2nd August 2008, 04:57 AM
Thanks a lot for the presentation slide.

regards