View Full Version : Defining the RPN cut off number - Working on the top 3- 5 high RPNs?


rak
5th July 2002, 04:17 PM
Perhaps this has been debated to death earlier, if so pls. excuse me for raking it up again.

I would like to know what is the better way of doing FMEAs - identifying a RPN cut off number or working on the top 3- 5 high RPNs? As i understand, both have their pros and cons.

Pls. advise.

Al Dyer
5th July 2002, 05:45 PM
Maybe think of the RPN's as a driver for a part of your continuous improvement projects???

Howard Atkins
6th July 2002, 05:41 AM
Some customers define a cut off RPN for treatment. This is of course subjective as the RPN is in a lot of cases your view.
This is a subject that you must discuss in the team and depends on the levels of RPN that you are getting.
If the numbers are all low, less than say 60 there is little to do. If the numbers are largley over 150 then you have work todo.
Commonsense and your knowledge of your process and product are the best way to go.

rak
6th July 2002, 06:45 PM
Howard and AL,

Thanks!

I agree with both of you.

D.Scott
8th July 2002, 09:07 AM
This is a re-hash as well but take it for what it is worth.

When looking at a FMEA, don't forget to look first at the high severity items. Sometimes they can be more important to a customer than something with a higher RPN.

Dave