My actual question is about the APQP timing plan:
I am working in auto components manufacturing industry (TVS group India), I need to know is it necessary to follow all the steps and sequence of AIAG APQP manual exactly the same fashion??
In one of our recent TS 16949 surveillance audit we had a problem for not following the sequence of APQP manual in the exact same manner in our timing plan.
Also we did not have floor plan for all the parts. We do batch production and not line production. Pls tell me is it required to have a floor plan for my kind of industry also.
Regards,
Hari (SHS)
My actual question is about the APQP timing plan:
I am working in auto components manufacturing industry (TVS group India), I need to know is it necessary to follow all the steps and sequence of AIAG APQP manual exactly the same fashion??
In one of our recent TS 16949 surveillance audit we had a problem for not following the sequence of APQP manual in the exact same manner in our timing plan.
Also we did not have floor plan for all the parts. We do batch production and not line production. Pls tell me is it required to have a floor plan for my kind of industry also.
Regards,
Hari (SHS)