D
dbzman
What does the AIAG manual say about the frequency of MSA. Does it require annual analysis or is this determined by customer requirements/contract?
Thanks!
Thanks!
Mr.1Putt said:Advice needed.
Mr.1Putt said:
I've been given a CI project in trying to lowering the cost of calibration used by the company. We are spending close to $100000 on calibration cost.
Can I use a stability study to suggest that calibration to be less frequent? I was told that this can be a loophole in the system.
The only problem I see with if it works is under Visteon's Customer Specific it requires that MSA studies be done yearly as part of annual layout verification.
Even if I get around doing it less via positive stability study it doesn't look like I can get around doing calibration/msa study for gages related to Visteon, correct?
Even 1 per year is going to cost...
Thanks
dbzman said:What does the AIAG manual say about the frequency of MSA. Does it require annual analysis or is this determined by customer requirements/contract? Thanks!