> Sir,
>
> i would like to know if we can use 5 pieces per lot during inspection instead
> of using AQL? what would be the possible advantages and the disadvantages of
> using the "5 piece-inspection"?
>
> is it really necessary that we follow the AQL in the inspection process? or
> can we define the sampling size depending on our company's decision?
>
> thank you.
> libie
>
> i would like to know if we can use 5 pieces per lot during inspection instead
> of using AQL? what would be the possible advantages and the disadvantages of
> using the "5 piece-inspection"?
>
> is it really necessary that we follow the AQL in the inspection process? or
> can we define the sampling size depending on our company's decision?
>
> thank you.
> libie