Hey ya'll (gee, can you tell I'm from Bama?  ) I just got a copy of an ISO cert newly issued to one my suppliers of raw material (steel) and noted that they claimed (and apparently got) an exclusion from "Validation of Processes for Production and Service Provision". Hmmm.... I gotta' say this is a first for me - I've never seen/heard of anyone even attempting to justify an exclusion from that clause. Have you? And if so, what was the basis for the argument?
|

16th March 2005, 04:56 PM
|
 |
qualitas ad nauseam
Registration Date: Sep 2003
Location: Saginaw, Michigan
Age: 50
|
|
Posts: 653
Thanks Given to Others: 3
Thanked 34 Times in 15 Posts
Karma Power: 79
|
|
I haven't personally run across it, but see example #8 at the web site below
http://web.archive.org/web/200503081...plication.html
I hope it helps.
__________________
Rob - The sum of anecdotes is not data. -Roger Brinner
Last edited by howste; 13th May 2009 at 01:54 AM.
Reason: Replaced dead link with web archive of original link
|

16th March 2005, 05:02 PM
|
 |
Inactive Registered Visitor
Registration Date: Aug 2001
Location: USA
|
|
Posts: 417
Thanks Given to Others: 0
Thanked 1 Time in 1 Post
Karma Power: 50
|
|
Hmmm... thanks for the direction - I read the example and I guess I understand what they're saying, but.... I don't know, maybe this is okay but I've not read any interpretation or guidance or HEARD anything that indicates this clause could really be excluded by anyone. interesting...
|

16th March 2005, 06:35 PM
|
 |
AKA: Dave
Registration Date: Sep 2004
Location: Northeast USA
Age: 53
|
|
Posts: 194
Thanks Given to Others: 544
Thanked 13 Times in 12 Posts
Karma Power: 40
|
|
The old "Special Processes" clause?
SteelWoman,
My first post so please excuse...I'm pretty sure this is the 2000 version (7.5.2) of the 1994 clause regarding special processes - my old definition being processes that by their nature can be validated only by destroying the product during the inspection, i.e. welding was the classic example. Hence the list of "arrangements" such as qualified personnel (certified TIG welder), approved equipment (weld unit #7), specific methods (SOP-75-TIG), etc.,etc.
Along the lines of this concept, you would need knowledge of your supplier's processes to know if this exclusion is actually valid in your opinion. Apparently the supplier convinced their registrar...
__________________
"A great deal of intelligence can be invested in ignorance when the need for illusion is deep" Saul Bellow
Last edited by fuzzy; 16th March 2005 at 06:39 PM.
Reason: Add the ISO clause #
|

16th March 2005, 06:51 PM
|
 |
Post responsibly
Registration Date: Oct 2001
Location: Long Beach, CA - USofA
|
|
Posts: 4,951
Thanks Given to Others: 688
Thanked 1,912 Times in 1,083 Posts
Karma Power: 467
|
|
Quote:
|
Originally Posted by SteelWoman
Hmmm... thanks for the direction - I read the example and I guess I understand what they're saying, but.... I don't know, maybe this is okay but I've not read any interpretation or guidance or HEARD anything that indicates this clause could really be excluded by anyone. interesting...
|
In principle, any clause (sub-clause or requirement) within section 7 of ISO 9001 can be considered for exclusion if it does not affect the organization's ability, or responsibility, to provide product that meets customer and applicable regulatory requirements.
So, if my product realization processes are always able to be monitored by testing or inspecting the (Intermediate and finished) products, then it is perfectly OK to claim an exclusion to 7.5.2.
__________________
Fighting organizational dysfunction, one post at a time.
|

18th March 2005, 02:36 PM
|
|
Getting Involved (6 to 9 Posts)
Registration Date: Mar 2005
Location: SC
|
|
Posts: 8
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 20 Karma: 10 
|
|
I actually don't audit anyone who does not exclude that clause - most companies can verify the resulting output of the process. The clause says where you cannot validate the item you must validate the process, so if you can validate the item you must do that and not the process.
|

18th March 2005, 04:00 PM
|
 |
Super Moderator
Registration Date: May 2003
Location: Clinton Township, MI USA
Age: 41
|
|
Posts: 1,600
Thanks Given to Others: 389
Thanked 134 Times in 80 Posts
Karma Power: 128
|
|
Quote:
|
Originally Posted by Sidney Vianna
So, if my product realization processes are always able to be monitored by testing or inspecting the (Intermediate and finished) products, then it is perfectly OK to claim an exclusion to 7.5.2.
|
We claim exclusion to this. We just machine and assemble - no special processes.
__________________
First thing each morning, I try on my bathing suit. Then, nothing worse can happen the rest of the day.
|

21st April 2009, 06:03 AM
|
|
Shy Poster (1 to 5 Posts)
Registration Date: Apr 2009
Location: Singapore
|
|
Posts: 4
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 3 Karma: 10 
|
|
Re: Exclusion from Validation of Processes for Production and Service Provision?
If we employ a series of verification inspections and validation tests before we install/deliver the final product(s) to customer, can we exclude the requirement validation of processes for production and service provision knowing that we have already identified and corrected mostly the major deficiencies early on? while we are still developing the product? I would appreciate if you can offer some advice. Thanks a lot!
Regards,
Serggie Tabanao
Last edited by Marc; 21st April 2009 at 04:42 PM.
Reason: Information which belongs in the poster's Profile per the TOS removed from post.
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|