The Elsmar Cove Forum and Site Map The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page

Go Back   The Elsmar Cove Forum > Manufacturing, Service, and Business Systems Processes > Lean - Lean in Manufacturing and Services


The Elsmar Cove Forum SideBar!
Monitor the Forum
Monitor New Forum Posts
New Threads Feeds
RSS FeedRSS Feed
Sponsor Link










$ Contributor Forum Access
Courtesy Quick Links

Links that Elsmar Cove visitors will find useful in your quest for knowledge:


Howard's International Quality Services

Atul's Symphony Technologies

Dave Scott's Scott Quality Solutions

Praxiom Research Group


NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest Portal

IEST - Institute of Environmental Sciences and Technology

ASQ - American Society for Quality


All the Important Standards and Related Web Sites in the World
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  #1  
Old 31st May 2006, 06:06 PM
StatsGeek StatsGeek is offline
Shy Poster (1 to 5 Posts)

Registration Date: May 2006
Location: USA, MA
 
Posts: 5
Thanks Given to Others: 16
Thanked 0 Times in 0 Posts
Karma Power: 15
Karma: 10
StatsGeek has less than 100 Karma points so far.
Question Layout and flow improvements - Reduced walking time? Cost savings?

Does anyone have any estimates for cost reductions due to layout / flow improvements that result in reduced walking distances (i.e. feet per second)? I have made some layout changes and can calculate the amount of walking distance saved, but don't know how to translate it to time (cost savings).
Reply With Quote

Sponsored Links
  #2  
Old 1st June 2006, 01:14 PM
Michael Walmsley Michael Walmsley is offline
E-Mails Invalid or Rejected

Registration Date: Dec 2005
Location: US
 
Posts: 158
Thanks Given to Others: 1
Thanked 19 Times in 6 Posts
Karma Power: 0
Karma: 810
Michael Walmsley is appreciated, and has over 700 Karma points.Michael Walmsley is appreciated, and has over 700 Karma points.Michael Walmsley is appreciated, and has over 700 Karma points.Michael Walmsley is appreciated, and has over 700 Karma points.Michael Walmsley is appreciated, and has over 700 Karma points.Michael Walmsley is appreciated, and has over 700 Karma points.Michael Walmsley is appreciated, and has over 700 Karma points.
Default

The question you need answer is,if there is less movement bench to bench , would more product be able to be produced and how much?
Reply With Quote
Sponsored Links

  #3  
Old 1st June 2006, 01:38 PM
StatsGeek StatsGeek is offline
Shy Poster (1 to 5 Posts)

Registration Date: May 2006
Location: USA, MA
 
Posts: 5
Thanks Given to Others: 16
Thanked 0 Times in 0 Posts
Karma Power: 15
Karma: 10
StatsGeek has less than 100 Karma points so far.
Default How much more product?

This is exactly my question. I cannot just use the increased throughput to calculate since there are a variety of reasons our throughput has gone up (other improvement efforts, increased demand / overtime, etc.).

I am trying to figure out how much of this increased throughput is due to the improved flow by estimating the labor time saved.

Does anyone have any suggestions for an estimate on labor time saved due to less walking distance?

Thanks.
Reply With Quote
  #4  
Old 1st June 2006, 02:51 PM
wmarhel wmarhel is offline
Courtesy Access

Registration Date: Oct 2004
Location: DuBois, PA
Age: 39
 
Posts: 612
Thanks Given to Others: 109
Thanked 234 Times in 149 Posts
Karma Power: 94
Karma: 3086
wmarhel is appreciated, and has over 1700 Karma points.
wmarhel is appreciated, and has over 1700 Karma points.
Default

Take your labor rate for the person/s who would typically be doing the material handling and/or labor. Regardless of whether you use the direct rate or the fully burdened rate (includes benefits in addition to the actual pay rate, and this is my preference) is up to you. If 100 minutes a day are spent walking to get materials (convert distances into time spent covering that distance) and this need is eliminated, then the calculation is simply:

100min x labor rate = ???

Keep in mind that there are additional savings and/or improvements besides direct labor content. This is especially true given the fact that labor content is usually less than 10% of the total cost of a product (this wouldn't be true of course if you are in a very manual operation. It is important to include all the benefits of the Lean conversion. Some additional examples could be:

1) Eliminate the use of dedicated material handler/s. This could also eliminate the necessity for a forklift (which could be sold off or the rental could be ended)

2) Reduction in WIP (work-in-progress)

3) Reduction in lead time to the customer (this benefit could be indirect such as improved customer satisfaction, and direct in that it may not be necessary to keep as much inventory as finished goods)

4) Reduction in the amount scrapped

Wayne
Reply With Quote
  #5  
Old 1st June 2006, 03:03 PM
2.5bostons 2.5bostons is offline
Involved - Posts

Registration Date: May 2006
Location: new hampshire, USA
 
Posts: 50
Thanks Given to Others: 0
Thanked 1 Time in 1 Post
Karma Power: 19
Karma: 179
2.5bostons is appreciated, and has over 100 Karma points.2.5bostons is appreciated, and has over 100 Karma points.
Send a message via MSN to 2.5bostons
Default spaghetti diagram?

OK... my question how did you arrive at reducing your walking requirements?

What was the driving force?
Was this a result of a Kaizen?
Standard Work Balance? 5S? What was the intent that can help us figure out the proper metric

Did you do a spaghetti diagram of the process prior to adjustments, measuring distances and identifying repeat movement?

Do you have an after diagram showing the improved layout?

I think the previous post's suggestion calcuation is on point
Reply With Quote
  #6  
Old 1st June 2006, 03:04 PM
ScottK's Avatar
ScottK ScottK is offline
Not out of the crisis

Registration Date: Apr 2006
Location: Butler, NJ
 
Posts: 1,786
Thanks Given to Others: 122
Thanked 281 Times in 223 Posts
Karma Power: 109
Karma: 2998
ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.ScottK is appreciated, and has over 1700 Karma points.
Default

I would only see it as a cost reduction if the new layout allowed the process to be done with fewer resources. Same output, less people or equipment.
Otherwise it's a gain in efficiency. Same people or equipment, greater output.

at any rate, I'm reaching way back here, haven't done "traditional IE" stuff in years, but I believe I used to use between 3.5 and 4 ft/sec as a walking rate.

so, if your saving, say, 400' of walking per shift then you're utilizing 100 seconds of a different, hopefully more productive, manner.

Remember - you can't save time. You can only spend it more wisely.
__________________
Time for a new sig line.
My LinkedIn Profile
Reply With Quote
  #7  
Old 1st June 2006, 04:20 PM
StatsGeek StatsGeek is offline
Shy Poster (1 to 5 Posts)

Registration Date: May 2006
Location: USA, MA
 
Posts: 5
Thanks Given to Others: 16
Thanked 0 Times in 0 Posts
Karma Power: 15
Karma: 10
StatsGeek has less than 100 Karma points so far.
Question Thanks... 3.5 to 4 feet per second??

Anybody else have any thoughts on walking rate? Anybody agree or disagree with the 3.5 to 4 feet per sec. rate suggested by Discordian?

Thank you for all of your responses.

Wayne:
You make some good points about areas to look at for cost savings due to lean projects. I am working with our finance person on cost savings due to WIP reduction. I don't really think the other areas are applicable at this point.

I was thinking in terms of the min. x labor rate calculation. The thing I'm having trouble with is getting at the 100min. without time studying the entire process (don't have detailed "before" time studies).

2.5bostons:
The walking distance reduction is mostly due to line layout improvements (pulling benches closer together to improve material flow) and a few process improvements that we have implemented (using more accessible equipment, etc.). I do have a spaghetti diagram of the previous layout and I am working on creating a spaghetti diagram of the new process and calculating distances for each.

Discordian:
I am looking at this as an efficiency improvement (more units out, same number of operators), but since we would have had to hire more people to meet our current demand rate if this weren't done, I am also counting it as a cost savings (also our mfg. cost per part has gone down).
Reply With Quote
  #8  
Old 1st June 2006, 04:34 PM
morgand morgand is offline
Involved - Posts

Registration Date: Oct 2003
Location: MO
Age: 36
 
Posts: 133
Thanks Given to Others: 0
Thanked 1 Time in 1 Post
Karma Power: 28
Karma: 92
morgand has less than 100 Karma points so far.
Default

there are 5280 feet per mile. My health text said that the average person walks a mile in approximatly 17 minutes (1999). 17 Minutes is 1020 seconds.

5280 / 1020 is about 5 feet per second at a normal walk- not a leisure walk It might be a little less if they meander.
Reply With Quote
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Forum > Manufacturing, Service, and Business Systems Processes > Lean - Lean in Manufacturing and Services

Bookmarks


Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Daylight Savings Time Change - 2008 Marc Forum News and General Information 4 28th October 2008 01:05 PM
Cost Savings based on 2005 Production - Metric Conversion Problem ezorangee Misc. Quality Assurance and Business Systems Related Topics 4 4th September 2006 11:27 AM
Cost Savings Ideas - Plastics Injection Molding Automotive Supplier sidvic Misc. Quality Assurance and Business Systems Related Topics 6 20th May 2006 02:11 PM
Daylight Savings (Summer) Time? Bruce Epstein Coffee Break and Water Cooler Discussions 6 10th April 2002 09:01 AM
Sources of Cost Savings - Waste takes on many shapes and forms Marc Misc. Quality Assurance and Business Systems Related Topics 0 4th July 2000 02:17 PM



The time now is 03:18 PM. All times are GMT -4.
The time zone can be changed in your UserCP --> Options.



   

All Y'All Come Back Now, Y' Hear?

Made With A Mac! FreeBSD OS Powered by Apache!
Using php4 Forums provided and maintained by Marc Smith Database by MySQL

FAIR USE and CORRECTNESS NOTICE: This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe herein constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/ If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. In addition, I do not guarantee the correctness of the content. The risk of using content from the Elsmar Cove web site and forums remains with the user/visitor.

Responsibility Statement: Each person is responsible for anything they post in the Elsmar Cove forum. Neither I, Marc Timothy Smith, nor any of the forum Moderators, are responsible for the content of posts people make. Liability for post content resides with the poster as does interpretation and/or acceptance and/or use of advice by the reader.

Complaints: If you have a complaint with a post in a forum discussion thread, including Content in general, fighting, flaming, copyright infringement, defamation and/or 'slander', please use the 'Report This Post Report This Post Button button which appears at the top of every post in every thread.

Site courtesy of:
Marc Timothy Smith - Cayman Business Systems, 8466 Lesourdsville-West Chester Road, West Chester, Ohio 45069-1929 - USA
(513) 341-6272

To contact me, click the Google Voice link below, enter Your Name and Your Phone Number and Google will ring your phone and connect you for free!

The Elsmar Cove Web Site is *CopyFree*
no new posts