Standardized Work in High Speed Process - 350 Parts per Minute
I am an engineer for a manufacturing process that is in it's infancy of lean implementation. We are currently working on work standardization (among other things). In one particular process we have 24 machines set up in 4 banks of machines (6 presses per bank) and each press produces parts at 350 parts/min. So our cycle time is under 2 seconds. This is great but for any given part produced the standardized work could be split up into the single step of 1) watch the press.
This is obviously not the operators primary duty.
Most examples of standardized work center around all the steps from the beginning of one part to the beginning of the next and that doesn't really work for us. We have standardized a larger unit for the kanbans supplying from each bank of machines but the work done in order to make each unit is very rarely consistent. The primary responsibilities of the operators are to keep the brass rolls supplied, gage components for SPC, remove and replace bad tooling, and cleaning (5S).
I'm just wondering if anyone has any experience standardizing a process like this. I'd appreciate any input.
|

25th July 2006, 08:06 AM
|
|
Courtesy Access
Registration Date: Oct 2004
Location: DuBois, PA
Age: 39
|
|
Posts: 612
Thanks Given to Others: 109
Thanked 234 Times in 149 Posts
Karma Power: 94 Karma: 3086 

|
|
Re: Standardized Work in High Speed Process - 350 Parts per Minute
Quote:
|
Originally Posted by duecesevenOS
Most examples of standardized work center around all the steps from the beginning of one part to the beginning of the next and that doesn't really work for us.
|
Don't get wrapped up with what other people are doing. If they don't have the same process as you, of course their "standardized work" would be different.
Quote:
|
Originally Posted by duecesevenOS
We have standardized a larger unit for the kanbans supplying from each bank of machines but the work done in order to make each unit is very rarely consistent. The primary responsibilities of the operators are to keep the brass rolls supplied, gage components for SPC, remove and replace bad tooling, and cleaning (5S).
|
You've answered some of your own questions as far as tasks that must be performed. You could also take a look at standardizing the set-up of the machines/equipment if that hasn't been done already. Include the method to supply material to the machine.
Other components of the work instructions could include the sequence in which the machines are started for specific jobs. Maybe it's as simple as machine 1 - 2 - 3 -4, but for another product it could be 2 - 3 - 1 - 4.
How about basic maintenance activities that can be performed by the operator such as ensuring the oil reservoirs are at an acceptable level.
If you want a few good references, check out:
The New Standardization and Standard Work for the Shopfloor
Wayne
|

25th July 2006, 03:45 PM
|
 |
E-Mails Invalid or Rejected
Registration Date: Aug 2005
Location: Georgia, USA
|
|
Posts: 125
Thanks Given to Others: 0
Thanked 5 Times in 5 Posts
Karma Power: 0
|
|
Re: Standardized Work in High Speed Process - 350 Parts per Minute
I suspect that each machine runs more than one part.
If this is the case, then you need to include your change overtime into your takt-time. (Number of change-overs/day X change over time).
It may also help to separate your cyclic time from your non-cyclic. (those items that can be done in a cyclical maner, set up machine, run part, measure part, clean from last set-up, set-up visuals for next run, etc, from those that are not done in a cyclical, checking oil levels, pressure levels, adding oils, etc.
In this way you can establish a sequence of steps that must always be followed (standardized work), as well as those things that should be done periodically. This will help you to calculate the total amount of manpower required based on the number of machines in each cell.
Hope this helps
|

10th August 2006, 04:04 PM
|
|
Inactive Registered Visitor
Registration Date: Aug 2006
Location: US/Troy
|
|
Posts: 3
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 14 Karma: 10 
|
|
Re: Standardized Work in High Speed Process - 350 Parts per Minute
I would suggest you set-up those operators on a Kamishibia route. Where they are doing quality checks and load parts on the various presses on a route, vs tied to one piece. Then you can develop the Standard work around these activities.
|

10th August 2006, 04:47 PM
|
|
Registered Visitor
Registration Date: Jul 2006
Location: Missouri
|
|
Posts: 76
Thanks Given to Others: 6
Thanked 11 Times in 9 Posts
Karma Power: 17 Karma: 105  
|
|
Re: Standardized Work in High Speed Process - 350 Parts per Minute
Whoa....Kamishibia? Whole new Japanese word I've never heard of (I think I'll be fluent in a year or two  ). Please explain a little better if possible. I'll look it up though. Thanks for the suggestion.
|

10th August 2006, 04:55 PM
|
|
Registered Visitor
Registration Date: Jul 2006
Location: Missouri
|
|
Posts: 76
Thanks Given to Others: 6
Thanked 11 Times in 9 Posts
Karma Power: 17 Karma: 105  
|
|
Re: Standardized Work in High Speed Process - 350 Parts per Minute
Looks like it's "kamishibai"... If anyone else is looking this up.
Kamishibia is some sort of story....Little confused for a sec there.
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|