What form or format does the quality plan and/or R&M take?
Posted by mibusha at the APQP and PPAP Forum .
Can any one help?
We design and build welding assemblies, hemmer assemblies and fastening
systems. As a TE supplier we are registering to ISO 9001 TE with a
pre-assessment in January,99.
We have been doing Control Plans and FMEAs (actually catching up on them with
a combination of workshops and classes).
I know we have to have a quality plan and we have to design in R&M. Basically I
am using pages 2-2 through 2-5 in the R&M Guidelines (SAE).
My question is: What form or format does the quality plan and/or R&M take? Do
all five stages appear on a Gantt chart? Must I document, for example, LCC
calculations? Or should I write the procedure (our quality plan and/or R&M)in text
form and note each document as it is mentioned in the text? We do most of the
TE requirements but have not done a good job of documenting them.
As you can see I could use some advice on this. Any help would be appreciated.
Thanks,
Michael
|

22nd December 1998, 11:36 PM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,859
Thanks Given to Others: 1,895
Thanked 1,568 Times in 1,020 Posts
Karma Power: 605
|
|
My experience with Quality Plans ranges from product specific plans to general design & development plans. In the ISO and QS world a 'quality plan' can be a series of systems, if you will. That is to say I don't always see a specific written 'quality plan' per se.
In QS it is your APQP system and related events. Yup - Design and Process FMEAs, control plans, flow diagrams, design reviews, verification, validation - all these together form your 'quality plan' in adduition to other things you do (eg: Quality Function Deployment, customer surveys, how nonconforming product is handled [yes - production features may be a part] etc.).
As long as you can show equivalances in your systems to the 'phases', you should be in gear.
I can't speak to the R&M issue.
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|