The Elsmar Cove Forum and Site Map The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page

Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > FMEA and Control Plans


The Elsmar Cove Forum SideBar!
Monitor the Forum
Monitor New Forum Posts
New Threads Feeds
RSS FeedRSS Feed
Sponsor Link










$ Contributor Forum Access
Courtesy Quick Links

Links that Elsmar Cove visitors will find useful in your quest for knowledge:


Howard's International Quality Services

Atul's Symphony Technologies

Dave Scott's Scott Quality Solutions

Praxiom Research Group


NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest Portal

IEST - Institute of Environmental Sciences and Technology

ASQ - American Society for Quality


All the Important Standards and Related Web Sites in the World
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  #1  
Old 22nd May 2000, 10:36 AM
Willie
Unregistered Guest

 
Posts: n/a
I Say... Control Plan Content Requirements - Level of Detail

a Control Plan should describe all actions necessary including receiving, in-process,out going and periodic requirements to ensure that all process outputs will be in a state of control.
According to myself all controls necessary to ensure the successfull execution of a Process Function or Operation should be included in Control Plans.

A Colleague tends to differ from me...according to him you only need to identify key product characteristics and their related key process issues in a Control Plan and forget about all other issues such as incoming inspection of material, storage, packaging or movement of product. This implicate that a process with no final product characteristics will for example not need any control actions in the Control Plan.
According to him the incoming inspection system will for example take care of incoming inspection requirements and the 10 other systems will take care of the other aspects.....it is therefore not necessary to incude these in the Control Plan.

I do not agree with his approach.

Question ...will his approach be acceptable and be regarded as compliant to the requirements of QS 9000 or not ????.
Reply With Quote

Sponsored Links
  #2  
Old 22nd May 2000, 11:09 AM
Laura M's Avatar
Laura M Laura M is offline
Courtesy Access

Registration Date: Aug 1999
Location: Rochester, NY US
 
Posts: 759
Thanks Given to Others: 3
Thanked 17 Times in 15 Posts
Karma Power: 70
Karma: 656
Laura M is appreciated, and has over 500 Karma points.Laura M is appreciated, and has over 500 Karma points.Laura M is appreciated, and has over 500 Karma points.Laura M is appreciated, and has over 500 Karma points.Laura M is appreciated, and has over 500 Karma points.Laura M is appreciated, and has over 500 Karma points.
Send a message via AIM to Laura M Send a message via Skype™ to Laura M
Dock to Dock PCP's were recommended by our registrar (when I worked for a large company), but I don't think its that cut and dry. Most receiving Inspection controls just referred to the appropriate receiving procedures. When you start looking at failure modes (PFMEA) that can happen in transit from dock to assembly line, etc, in some cases you may prevent defects from getting through your process.
We definately included more than KPC's, however, I do think the APQP manual is vague in this regard. Others?
Reply With Quote
Sponsored Links

  #3  
Old 22nd May 2000, 10:56 PM
Marc's Avatar
Marc Marc is offline
Your Elsmar Cove Host

Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
 
Posts: 15,860
Thanks Given to Others: 1,896
Thanked 1,570 Times in 1,021 Posts
Blog Entries: 4
Karma Power: 605
Karma: 11579
Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.
Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.
Send a message via AIM to Marc Send a message via Skype™ to Marc
Yin Yang

Typically a control plan contains customer defined Key Product Characteristics as a minimum, plus any characteristics you decide are important or critical to your process(es) or the product.

The question becomes how far do you go. Your customer may specify 4 Key (or Critical or Special - different companies call them different things) Characteristics. Typically these are defined on the print. Ford uses the infamous 'inverted delta', for example, to identify 'critical' characteristics.

Now it's your turn. You look at areas such as receiving, etc. through delivery. What do you think is critical? You should have input from an FMEA to help you determine your critical characteristics. As is always the case, you're looking at risk factors with your FMEA.

'Legally', your colleague is right saying: "...you only need to identify key product characteristics and their related key process issues in a Control Plan..." However, related key process characteristics may include aspects of everything from receiving to delivery.

"...This implicate that a process with no final product characteristics will for example not need any control actions in the Control Plan..." True - but try to convince an auditor that there are no key characteristics at all. I have seen plenty of products with no customer defined Key Characteristics at all (less so now than 5 years ago because of QS). I have not (in some years) seen a product with no control plan entries.

What receiving does is, in fact, a result of a determination of your identified key characteristics. You may not be thinking of it in the sense of a control plan, but you have receiving requirements for materials and such (including items which go into the product as well as items used to process the product) which have the same basic elements. Sample size, reaction plan, etc. For all intents and purposes receiving does have a control plan. Even in the case of 'ship to stock'.

Your colleague is focusing only on his part of the pie, maybe?

A good question to ask here is: Do you have a Receiving FMEA?

"...and the 10 other systems will take care of the other aspects..." What are the 10 other systems?
Reply With Quote
Thanks to Marc for your informative Post and/or Attachment!
  #4  
Old 31st May 2000, 01:19 AM
Marc's Avatar
Marc Marc is offline
Your Elsmar Cove Host

Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
 
Posts: 15,860
Thanks Given to Others: 1,896
Thanked 1,570 Times in 1,021 Posts
Blog Entries: 4
Karma Power: 605
Karma: 11579
Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.
Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.
Send a message via AIM to Marc Send a message via Skype™ to Marc
Covering Ass

Please replace the wording "Key Product Characteristics" in my posting of 22/5 with "Customer defined Key Product Characteristics"

I will appreciate more comments.
Thanks to Marc and Laura

Willie
Reply With Quote
  #5  
Old 3rd February 2009, 12:34 PM
qualityboi's Avatar
qualityboi qualityboi is offline
Involved in Discussions

Registration Date: Apr 2005
Location: Pacific Northwest
Age: 42
 
Posts: 289
Thanks Given to Others: 69
Thanked 64 Times in 28 Posts
Karma Power: 43
Karma: 953
qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.qualityboi is appreciated, and has over 900 Karma points.
Send a message via Yahoo to qualityboi
Please Help! Re: Control Plan Content Requirements - Level of Detail

The appendix on page 79 of the APQP blue book has a reference checklist that indicates control plans and the need to address incoming through packaging. Are there any harder requirements in the blue books / ISOTS 16949 that cite having a the control plan address incoming materials through packaging directly.

I already realize the logic in having them, but the point is that an auditee is challenging me to cite the specific requirement.

I am new to auditing FMEAs and Control plans, yes I have already had training...
__________________
Jimbo
I will try anything once, sometimes twice, because I am a slow learner.
Reply With Quote
  #6  
Old 17th February 2009, 10:39 PM
Raffy's Avatar
Raffy Raffy is offline
Courtesy Access

Registration Date: Mar 2001
Location: Manila, Philippines
Age: 38
 
Posts: 639
Thanks Given to Others: 225
Thanked 63 Times in 49 Posts
Karma Power: 73
Karma: 1270
Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.Raffy is appreciated, and has over 1100 Karma points.
Please Help! Re: Control Plan Content Requirements - Level of Detail

Hi everyone,
Is the control plan attached in the 2nd edition APQP Manual was changed? What are the changes? Please advice. A revised control plan attachment is highly appreciated.
Thank you very much in advance for the usual prompt attention you will give in this request.
P.S.
I already requested to purchase the said Reference Manual, but i haven't heard any approvals yet... I am currently updating our control plans in preparation for our TS16949 Surveillance Audit probably by June 2009. - Thanks in advance...
Best regards,
Raffy
Reply With Quote
  #7  
Old 17th February 2009, 11:05 PM
bobdoering's Avatar
bobdoering bobdoering is offline
Stop X-bar/R Madness

Registration Date: May 2002
Location: LaGrange, OH
 
Posts: 2,092
Thanks Given to Others: 680
Thanked 563 Times in 469 Posts
Blog Entries: 13
Karma Power: 150
Karma: 3915
bobdoering is appreciated, and has over 1700 Karma points.
bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.bobdoering is appreciated, and has over 1700 Karma points.
Send a message via Yahoo to bobdoering
Default Re: Control Plan Content Requirements - Level of Detail

Quote:
Originally Posted by Willie View Post

a Control Plan should describe all actions necessary including receiving, in-process,out going and periodic requirements to ensure that all process outputs will be in a state of control.
According to myself all controls necessary to ensure the successfull execution of a Process Function or Operation should be included in Control Plans.

A Colleague tends to differ from me...according to him you only need to identify key product characteristics and their related key process issues in a Control Plan and forget about all other issues such as incoming inspection of material, storage, packaging or movement of product. This implicate that a process with no final product characteristics will for example not need any control actions in the Control Plan.
According to him the incoming inspection system will for example take care of incoming inspection requirements and the 10 other systems will take care of the other aspects.....it is therefore not necessary to incude these in the Control Plan.

I do not agree with his approach.

Question ...will his approach be acceptable and be regarded as compliant to the requirements of QS 9000 or not ????.
I agree with you. The control plan should be....well, the control plan. Every characteristic you check, how you check it, with what gage, how often and what do you do if you do not meet the specification should be in this plan for everything you expect to check. Why have a separate system for incoming receiving inspection? Now, if the incoming part is a sublevel BOM with its own part number, then, yes, it should have its own control plan AS the incoming inspection plan. The assembly control plan just brings in the part, maybe with a label verification.

So many people keep trying to reinvent a pretty darn round wheel...
Reply With Quote
  #8  
Old 18th February 2009, 03:06 AM
Varadarajan Varadarajan is offline
Involved in Discussions

Registration Date: Sep 2008
Location: INDIA
Age: 51
 
Posts: 26
Thanks Given to Others: 68
Thanked 8 Times in 6 Posts
Karma Power: 5
Karma: 47
Varadarajan has less than 100 Karma points so far.
Send a message via MSN to Varadarajan
Default Re: Control Plan Content Requirements - Level of Detail

Quote:
Originally Posted by bobdoering View Post

I agree with you. The control plan should be....well, the control plan. Every characteristic you check, how you check it, with what gage, how often and what do you do if you do not meet the specification should be in this plan for everything you expect to check. Why have a separate system for incoming receiving inspection? Now, if the incoming part is a sublevel BOM with its own part number, then, yes, it should have its own control plan AS the incoming inspection plan. The assembly control plan just brings in the part, maybe with a label verification.

So many people keep trying to reinvent a pretty darn round wheel...



I too agree.

My experience in a precision components manufacturing (TS) company for Bosch customer (For Hydraulic gear pump covers)

We had control plans with all the process from Receiving inspection of castings,CNC,VMC etc..vibro deburing,Surface treatment, to Final Packing .
The Receiving inspection has important features of casting/Metallurgical properties.

The final Packing also has specific customer requirements as how many components in a Box, and how many rows it should be placed and in anti-corrosive sheets or bags etc(The parts are shipped by sea)

So all the important features or dimensions affecting the final product must be controlled.
The control plan tells us the control methods for all the non-conformances.
Reply With Quote
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > FMEA and Control Plans

Bookmarks

Tags
control plan, ts 16949, aiag apqp manual


Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Minimum label content requirements for each level of packaging (inner, outer, etc) Chris_H ISO 13485 - Medical Devices - Quality Management Systems 5 24th October 2008 04:31 AM
References instead of Detail - Control Method and Reaction Plan vforge FMEA and Control Plans 5 2nd August 2005 12:54 PM
ISO 14001:2004 - 4.3.2 Legal & Other Requirements - Level of detail expected kalehner ISO 14001 and Environmental Related Standards 18 31st March 2005 11:07 AM
Three Questions About Control Plan Content and Requirements Dawn FMEA and Control Plans 11 12th December 2003 11:12 PM
Control Plan content and fields - Format and Reaction Plan - 4.9.1 & 4.9.2 Marc QS-9000 - American Automotive Manufacturers Standard 5 3rd April 2000 08:19 PM



The time now is 03:51 PM. All times are GMT -4.
The time zone can be changed in your UserCP --> Options.



   

All Y'All Come Back Now, Y' Hear?

Made With A Mac! FreeBSD OS Powered by Apache!
Using php4 Forums provided and maintained by Marc Smith Database by MySQL

FAIR USE and CORRECTNESS NOTICE: This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe herein constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/ If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. In addition, I do not guarantee the correctness of the content. The risk of using content from the Elsmar Cove web site and forums remains with the user/visitor.

Responsibility Statement: Each person is responsible for anything they post in the Elsmar Cove forum. Neither I, Marc Timothy Smith, nor any of the forum Moderators, are responsible for the content of posts people make. Liability for post content resides with the poster as does interpretation and/or acceptance and/or use of advice by the reader.

Complaints: If you have a complaint with a post in a forum discussion thread, including Content in general, fighting, flaming, copyright infringement, defamation and/or 'slander', please use the 'Report This Post Report This Post Button button which appears at the top of every post in every thread.

Site courtesy of:
Marc Timothy Smith - Cayman Business Systems, 8466 Lesourdsville-West Chester Road, West Chester, Ohio 45069-1929 - USA