19th July 2000, 11:08 PM
|
|
|
Process Control Plans
I'm working on control plans for our qs registration. I have a couple of questions -
1. Do Process Control Plans need to list all controls?
2. Does every step in the Process Flowchart need to show up on the Control Plan?
3. In relation to the PFMEA, if something with a high severity has a low RPN number because the occurence is low or the detection is high, does it need to be in the Control Plan?
Thanks for any help.
DJ
|

21st July 2000, 06:19 PM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,860
Thanks Given to Others: 1,896
Thanked 1,570 Times in 1,021 Posts
Karma Power: 605
|
|
1. Do Process Control Plans need to list all controls?
Yes.
2. Does every step in the Process Flowchart need to show up on the Control Plan?
What specific step do you think might not be needed? A 'MOVE' step?
3. In relation to the PFMEA, if something with a high severity has a low RPN number because the occurence is low or the detection is high, does it need to be in the Control.
Is it a critical characteristic?
|

21st July 2000, 10:04 PM
|
|
|
|
1. Thanks, it's a good thing we put them in already.
2. Yes, sort of - Transfer from Tank A to Tank B type stuff.
3. I think I'm confused on the meaning of the word 'critical'. Using the model in the APQP book, does it affect fit/function or does it have any safety/legal considerations - I can comfortably say no. Are there process controls that we have in place to address the high RPN's - yes.
Thanks for your help. This is the first time I've worked with Control Plans and sometimes I feel like I'm unneccesarily wrapping myself around an axle. I think you have an excellent forum here and find it a great resource.
|

22nd July 2000, 04:53 PM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,860
Thanks Given to Others: 1,896
Thanked 1,570 Times in 1,021 Posts
Karma Power: 605
|
|
2. Yes, sort of - Transfer from Tank A to Tank B type stuff.
Pipe or intermediate containers?
Typically the requirement is for 'critical characteristics' to be on the control plan. Critical characteristics are determined by your customer (if any) and by you. You might want to do a forum search for CRITICAL CHARACTERISTIC for some threads on these. Unfortunately there is no black and white here as to what you consider critical characteristics. Your PFMEA (and sometimes the DFMEA) should lead you to what characteristics are critical. And some are just 'common sense' -- Paint colour would be one in the paint industry as an obvious example.
Bottom line is if you are seriously confused about what may or may not be critical characteristics you may want to find a consultant in your industry and get him/her to come in for a day to discuss your thoughts. Or maybe there's someone here with industry experience who can help you out...
Any takers??
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|