The Elsmar Cove Forum and Site Map The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page

Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > Supplier Quality Assurance and other Supplier Issues


The Elsmar Cove Forum SideBar!
Thread Tags
Tag Cloud
Monitor the Forum
Monitor New Forum Posts
New Threads Feeds
RSS FeedRSS Feed
Sponsor Link











$ Contributor Forum Access
Courtesy Quick Links

Links that Elsmar Cove visitors will find useful in your quest for knowledge:


Howard's International Quality Services

Atul's Symphony Technologies

Dave Scott's Scott Quality Solutions

Praxiom Research Group


NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest Portal

IEST - Institute of Environmental Sciences and Technology

ASQ - American Society for Quality


All the Important Standards and Related Web Sites in the World
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  #1  
Old 24th May 2007, 02:16 AM
Arunnegi Arunnegi is offline
Inactive Registered Visitor

Registration Date: May 2007
Location: India
 
Posts: 3
Thanks Given to Others: 1
Thanked 1 Time in 1 Post
Karma Power: 13
Karma: 15
Arunnegi has less than 100 Karma points so far.
Please Help! Economic Order Quantity - Implementing Kanban

Hi every body
I am doing a project of implementing Kanban in a company. For this I need to find out the Reorder point and Economic Order Quantity for the item/parts of my company (about18000 types).

According to me:-

EOQ=(2*D*S/H)^1/2
where,
D=Annual Demand
S=Order cost
H=Annual Holding cost
I have problem in finding the Holding cost. I assumed it to be 25% of the parts cost.so my formula becomes:-

EOQ=[2*D*S/(C*25/100)]^1/2
but this is giving very absurd figure,
for ex-if C=Rs 500,S=Rs 2000 and Annual Demand=3000
then EOQ=48000 which means I m ordering quantity for the next 16 years.

Also, If I take Holding cost of EOQ/2 parts (Since on an average I hold EOQ/2 quantity of the item/parts in a year)
so H=(EOQ/2)*C*25/100
now after some calculations
EOQ=(16*D*S/C)^1/3
this gives EOQ =92 for the above data.
where as its lead time is 132 days and its Reorder point is 1187
as per my knowledge EOQ should not come below the Reorder point.

kindly help me out of this..

regards
Arun
Reply With Quote

Sponsored Links
  #2  
Old 24th May 2007, 08:02 AM
wmarhel wmarhel is offline
Courtesy Access

Registration Date: Oct 2004
Location: DuBois, PA
Age: 40
 
Posts: 618
Thanks Given to Others: 109
Thanked 255 Times in 158 Posts
Karma Power: 99
Karma: 3191
wmarhel is appreciated, and has over 1700 Karma points.
wmarhel is appreciated, and has over 1700 Karma points.wmarhel is appreciated, and has over 1700 Karma points.
Default Re: Economic order quantity - Implementing Kanban

First off, do the calculation for kanban (Reference my previous post here):

The formula for calculating the number of kanban cards in a system for a particular product is:

(Daily Demand x (Run Frequency + Lead Time + Safety Time)) / Container Capacity

Where:

Daily Demand = Customer Consumption expressed as # of units

Run Frequency = Frequency which you decide to set-up and produce that item. This is expressed as a unit of time. For a five day work week, running the product every day would equal (1), every third day would equal (3), etc.

Lead Time = Manufacturing lead time (processing time + Set-up time + queue time) + lead time for kanban retrieval expressed as a unit of time.

Safety Time = Allowance for variations in demand and supply, also expressed as a unit of time. Keep as low as possible.

Container Capacity = Number of units per container (# of units in a container is always the same number).

********************

Notice, that nowhere in the kanban formula is EOQ a factor. What EOQ does is try find the to optimum quantity that should be ordered which would minimuze the total variable costs (purchasing, shipping, carrying, etc.) APICS (The Association for Operations Management) covers EOQ in some of the certification modules.

Whereas EOQ is solely a cost model, kanban is time driven. The formula essentially gives you the reorder point as well. In this case, the quantity is determine by your container capacity, it is just a matter of how often which would be handled by the kanban board or heijunka box.

On a side note, be sure your carry costs are accurate. The typical range thrown out is usually in the 20-30% area, but when you really look at opportunity costs, it is probably more in the >30% range.

Your re-order point (Reorder Point = Lead Time Demand + Safety Stock) is also time based. It is the trigger based on inventory level (in order to maintain a defined level of service to the customer). These points are usually set as triggers within your MRP/ERP system.

The EOQ calculation is a good check and it can be used to help in the basis for your ordering system (which is a different topic), but the results are different in perspective.

Wayne
Reply With Quote
Thank You to wmarhel for your informative Post and/or Attachment!
Sponsored Links

  #3  
Old 24th May 2007, 08:19 AM
Arunnegi Arunnegi is offline
Inactive Registered Visitor

Registration Date: May 2007
Location: India
 
Posts: 3
Thanks Given to Others: 1
Thanked 1 Time in 1 Post
Karma Power: 13
Karma: 15
Arunnegi has less than 100 Karma points so far.
Please Help! Re: Economic order quantity - Implementing Kanban

Dear Wayne
I totally agree with you in every sense. but what I am doing is that I want to keep the reorder point as u have explained (I suppose I did the same calculations). But I want to follow the order quantity as EOQ as far as I can, since it is the optimum quantity( may be the EOQ can be less than RP sometimes and I may have to manipulate the it in that case).
So I still want to find the EOQ, and hence It will be helpful if I get the exact formula. Can u please refer to my earlier post again for that and let me know the right formula.

Arun
Reply With Quote
  #4  
Old 24th May 2007, 08:25 AM
BradM's Avatar
BradM BradM is offline
Super Moderator

Registration Date: Sep 2006
Location: Arlington,Texas
 
Posts: 3,925
Thanks Given to Others: 878
Thanked 1,056 Times in 750 Posts
Karma Power: 317
Karma: 11193
BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.
BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.
Default Re: Economic order quantity - Implementing Kanban

Wayne really did an excellent job on this one.

You may be getting the correct answer with the EOQ. Notice, your holding costs is profoundly less than your ordering costs, so fundamentally you would order that much. Remember, EOQ is just an optimal balance between holding and ordering costs; nothing more comes into play.

I would challenge your holding costs. I can look it up in some books, but holding inventory is extremely expensive.

Too, the EOQ model is easy to calculate, and given the basic assumptions hold (which hardly never occurs) works pretty good. There are some more robust models that may work.
__________________
Brad
Chuck Norris has counted to infinity.Twice.
Reply With Quote
  #5  
Old 24th May 2007, 10:55 AM
wmarhel wmarhel is offline
Courtesy Access

Registration Date: Oct 2004
Location: DuBois, PA
Age: 40
 
Posts: 618
Thanks Given to Others: 109
Thanked 255 Times in 158 Posts
Karma Power: 99
Karma: 3191
wmarhel is appreciated, and has over 1700 Karma points.
wmarhel is appreciated, and has over 1700 Karma points.wmarhel is appreciated, and has over 1700 Karma points.
Default Re: Economic order quantity - Implementing Kanban

Quote:
Originally Posted by Arunnegi View Post


what I am doing is that I want to keep the reorder point as u have explained (I suppose I did the same calculations). But I want to follow the order quantity as EOQ as far as I can, since it is the optimum quantity( may be the

So I still want to find the EOQ, and hence It will be helpful if I get the exact formula. Can u please refer to my earlier post again for that and let me know the right formula.

Arun
I'm going to recommend you get the book, "Introduction to Materials Management" by J.R. Tony R. Arnold and Stephen N. Chapman.

This is one of the primary references used throughout APICS' CPIM (Certified in Production and Inventory Management) body of knowledge. It is also a key reference for their CSCP (Certified Supply Chain Specialist) exam as well. For a textbook, it is a pretty read and an excellent reference.

It would be nice if the EOQ and Reorder Point (RP) could be one and the same.

I just did your calculations and something isn't right. I can't get to your 48,000.

The formula is:

Square root of (Annual usage * 2 * Order Cost) / Annual Carrying Cost

Carrying cost is represented as the annual cost per average "on hand inventory unit/s".

So (correct me if I'm wrong with these numbers).....

Annual Demand 3000
Order Cost 2000
Holding Cost 500

Would yield an EOQ of: 155 (rounding up to the nearest whole unit). Not even close to your number. See the attached spreadsheet.

It is also important to remember that just because you only want an EOQ of 90, the supplier may only sell in bundles of 200 (it just isn't in large enough demand to do otherwise). In this instance, your stuck with an order quantity of 200 units.

Wayne
Attached Files: 1. Scan for viruses before using, 2. Please report any 'bad' files by Reporting the post it is in, 3. Use at your Own Risk.
File Type: xls EOQ.xls (16.0 KB, 224 views)
Reply With Quote
  #6  
Old 24th May 2007, 11:23 AM
BradM's Avatar
BradM BradM is offline
Super Moderator

Registration Date: Sep 2006
Location: Arlington,Texas
 
Posts: 3,925
Thanks Given to Others: 878
Thanked 1,056 Times in 750 Posts
Karma Power: 317
Karma: 11193
BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.
BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.BradM is appreciated, and has over 1700 Karma points.
Default Re: Economic order quantity - Implementing Kanban

Quote:
EOQ=(2*D*S/H)^1/2
where,
D=Annual Demand
S=Order cost
H=Annual Holding cost
I have problem in finding the Holding cost. I assumed it to be 25% of the parts cost.so my formula becomes:-

EOQ=[2*D*S/(C*25/100)]^1/2
but this is giving very absurd figure,
for ex-if C=Rs 500,S=Rs 2000 and Annual Demand=3000
then EOQ=48000 which means I m ordering quantity for the next 16 years.
Wayne, I saw the holding costs as $125 (25% of the parts cost-(500*.25), hence the reason I commented I think that value strikes me as extremely low, especially compared to a $2000 order cost.

What do you think?
__________________
Brad
Chuck Norris has counted to infinity.Twice.
Reply With Quote
  #7  
Old 24th May 2007, 11:56 AM
wmarhel wmarhel is offline
Courtesy Access

Registration Date: Oct 2004
Location: DuBois, PA
Age: 40
 
Posts: 618
Thanks Given to Others: 109
Thanked 255 Times in 158 Posts
Karma Power: 99
Karma: 3191
wmarhel is appreciated, and has over 1700 Karma points.
wmarhel is appreciated, and has over 1700 Karma points.wmarhel is appreciated, and has over 1700 Karma points.
Default Re: Economic order quantity - Implementing Kanban

Quote:
Originally Posted by BradM View Post

Wayne, I saw the holding costs as $125 (25% of the parts cost-(500*.25), hence the reason I commented I think that value strikes me as extremely low, especially compared to a $2000 order cost.

What do you think?
Your right, that would change the quantity to 310. It is also why I did the spreadsheet. The giveaway is that the EOQ quantity is larger than the annual volume. If that is truly the case, then I would have to wonder about the costs that are being used.

Wayne
Reply With Quote
  #8  
Old 25th May 2007, 02:47 AM
Arunnegi Arunnegi is offline
Inactive Registered Visitor

Registration Date: May 2007
Location: India
 
Posts: 3
Thanks Given to Others: 1
Thanked 1 Time in 1 Post
Karma Power: 13
Karma: 15
Arunnegi has less than 100 Karma points so far.
Please Help! Re: Economic order quantity - Implementing Kanban

Thanks Wayne and Brad
There was some problem in my EOQ calculations and Wayne was right in making his point.
Can you help me out in clearing a concept.
I am implementing one bin Kanban in a manufacturing firm (mostly assembling). where I can take one bin with a partition(or two bins adjacent to each other) near the assembly line. Suppose I take two bins blue and Red for example. Now I am taking Red bin quantity as Reorder point and blue bin quantity equal to EOQ- RP.
so when the blue bin gets empty its card moves to the board and I get the trigger that my reorder point has arrived(since only Red bin quantity is left). At this point I order the parts and by the time they arrive the Red bin will be almost empty. So this way I am holding minimum inventory.
Now the question is of Blue bin quantity( I know I may be wrong in taking this).I totally agree with your point that EOQ has nothing to do with Kanban and it is based on Cost and not time. But I want to order the quantity as close as possible to the EOQ.So I have taken it as EOQ-RP.Sometimes the EOQ is less than RP and sometimes their difference is not significant. In that case I manipulate the quantity of Blue bin.
I think I am right in taking the Red bin quantity.
If I am wrong then please tell me how I can take the Blue bin and Red bin quantities.
Thanks
Arun
Attached Files: 1. Scan for viruses before using, 2. Please report any 'bad' files by Reporting the post it is in, 3. Use at your Own Risk.
File Type: pdf Kanban Basics.pdf (419.6 KB, 231 views)
Reply With Quote
Thanks to Arunnegi for your informative Post and/or Attachment!
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > Supplier Quality Assurance and other Supplier Issues

Bookmarks


Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
EOQ (Economic Order Quantity) - Use for managing Customer Orders - asking help Sharpin Zou Lean - Lean in Manufacturing and Services 5 4th June 2010 07:34 AM
During tough economic times, does 'ISO' really help AndyN Coffee Break and Water Cooler Discussions 27 24th March 2009 07:09 AM
Kanban Calculation - Correct Kanban Sizes bricka Lean - Lean in Manufacturing and Services 4 26th September 2008 03:17 PM
EOQ (Economic Order Quantities) - Solution For Parts Manufacturing Nightmare? jmpugh Lean - Lean in Manufacturing and Services 6 22nd January 2008 06:59 PM
Acceptable Error Rates for Order Picking and Order Entry sankargt Quality Tools, Improvement and Analysis 8 28th September 2006 12:00 PM



The time now is 05:41 AM. All times are GMT -4.
The time zone can be changed in your UserCP --> Options.



   

All Y'All Come Back Now, Y' Hear?

Made With A Mac! FreeBSD OS Powered by Apache!
Using php4 Forums provided and maintained by Marc Smith Database by MySQL

FAIR USE and CORRECTNESS NOTICE: This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe herein constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/ If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. In addition, I do not guarantee the correctness of the content. The risk of using content from the Elsmar Cove web site and forums remains with the user/visitor.

Responsibility Statement: Each person is responsible for anything they post in the Elsmar Cove forum. Neither I, Marc Timothy Smith, nor any of the forum Moderators, are responsible for the content of posts people make. Liability for post content resides with the poster as does interpretation and/or acceptance and/or use of advice by the reader.

Complaints: If you have a complaint with a post in a forum discussion thread, including Content in general, fighting, flaming, copyright infringement, defamation and/or 'slander', please use the 'Report This Post Report This Post Button button which appears at the top of every post in every thread.

Site courtesy of:
Marc Timothy Smith - Cayman Business Systems, 8466 Lesourdsville-West Chester Road, West Chester, Ohio 45069-1929 - USA
(513) 341-6272

If you are having problems Registering, Activating your Registration, or other problems, you can phone me in the US. I'm not here 24/7/365, but if I'm here I'll try to help.
The Elsmar Cove Web Site is *CopyFree*
no new posts