The Elsmar Cove Forum and Site Map The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page

Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > FMEA and Control Plans


The Elsmar Cove Forum SideBar!
Monitor the Forum
Monitor New Forum Posts
New Threads Feeds
RSS FeedRSS Feed
Sponsor Link










$ Contributor Forum Access
Courtesy Quick Links

Links that Elsmar Cove visitors will find useful in your quest for knowledge:


Howard's International Quality Services

Atul's Symphony Technologies

Dave Scott's Scott Quality Solutions

Praxiom Research Group


NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest Portal

IEST - Institute of Environmental Sciences and Technology

ASQ - American Society for Quality


All the Important Standards and Related Web Sites in the World
Reply
 
Thread Tools Search this Thread Rating: Thread Rating: 1 votes, 5.00 average. Display Modes
  #1  
Old 16th January 2001, 06:21 PM
kim.humphrey@at.siemens.c
Unregistered Guest

 
Posts: n/a
FMEA

On page 43, the standard states that when the severity of the RPN is high, special attention should be given to it. What does everyone consider high? We have been using 100.
Reply With Quote

Sponsored Links
  #2  
Old 16th January 2001, 06:41 PM
Al Dyer
Unregistered Guest

 
Posts: n/a
Lightbulb

I have found that different suppliers have various "limits" for RPN's but I think the bigger picture would be to have some type of prioritized reduction plan for your highest RPN's.

In a previous life we even had a helpful SQA that gave us RPN numbers of our competitors (no names involved) to benchmark against.

I would like to hear from other forum members if they have any specific supplier limits they could share.

ASD...

------------------
Al Dyer
Mngt. Rep.
ullysses3@excite.com
Reply With Quote
Sponsored Links

  #3  
Old 17th January 2001, 10:17 AM
Sam's Avatar
Sam Sam is offline

Registration Date: Sep 1999
Location: Oklahoma
Age: 67
 
Posts: 1,437
Thanks Given to Others: 1
Thanked 29 Times in 17 Posts
Karma Power: 90
Karma: 1020
Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.Sam is appreciated, and has over 900 Karma points.
"What does everyone consider high"
IMO 1000 or higher. Special attention when severity is 7 or higher.

From the FMEA manual;
"The risk oriority number is the product of severity (S), Occurrence (O), and detection (D). RPN = (S) x(OD) x (D)
This value should be used to rank order the concerns in the process (e.g., in Pareto fashion)
The RPN will be between "1" and "1,000". For higher RPN,s (higher than 1000) the team must undertake efforts to reduce this calculated risk through corrective action(s). In general practice, regardless of the resultant RPN( S x O x D ), special attention should be given when severity (page 35) is high (7,8,9,10)"
Note: expressions in parenthesis is my input.

[This message has been edited by Sam (edited 17 January 2001).]
Reply With Quote
  #4  
Old 18th January 2001, 01:41 AM
Kevin Mader's Avatar
Kevin Mader Kevin Mader is offline
One of THE Original Covers!

Registration Date: Nov 1998
Location: Wallingford, CT USA
Age: 43
 
Posts: 1,158
Thanks Given to Others: 22
Thanked 63 Times in 43 Posts
Karma Power: 94
Karma: 1335
Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.
Send a message via AIM to Kevin Mader
I would discourage an arbitrarily established value. Failing to deal with a value below '100' might prove to be determental.

On the other hand, unwisely dispensing resources to countermeasure a low rating could prove equally bad.

Keep in mind that the FMEA is a LIVING DOCUMENT. This means it must be revisited from time to time. As such, you might find that an RPN for an item that was low because of a false expectation proves to be high. The reverse is also true. Still, as the process or system changes, the RPN could toggle back and forth.

So when do you react? Well, what is a manageable risk? Keep in mind that the organization for the most part is the AUTHORITY on the process or design. You make the decision as to what is a high or low risk (please pay attention to regulatory requirement, ie Essential Requirements which govern your actions). Being the authority on the product/process, the experts, and having knowledge of your manageable resources, you pick your own battles.

Another not so scientific method, but perhaps better than arbitrarily established RPNs, is to use the 80/20 principle. Use Pareto analysis to establish your priorities and address the "vital few" as your resources permit. Use Corrective/Preventive Actions. As you periodically do your review the FMEA, update your RPNS,reprioritize, and repeat the process.

Just another opinion.

Regards,

Kevin
Reply With Quote
  #5  
Old 19th January 2001, 05:53 PM
J.R. Strickland
Unregistered Guest

 
Posts: n/a
At a minimum, we require the following...

1. Any RPN >= 100 must have an action plan to reduce.

2. If no RPN's are over 100, the top 3 RPN's must be considered. Why considered and not an action plan?...because if my top RPN is 20, I will probably get more value out of my engineers elsewhere.

3. Any severity of 9 or 10 must be evaluated. Again, the resultant RPN could be low if occurrence and detectability are 1, but because a 9 or 10 can affect safe vehicle operation or impact a govt. regulation, they deserve special attention.

Reply With Quote
  #6  
Old 15th February 2001, 12:49 PM
dan dan the qualityman
Unregistered Guest

 
Posts: n/a
Bomb!

You have all posed some interesting points of view with respect to the action or lack of action relating to a particular level of RPN. As I see it, the FMEA provides a micro view of your product or system in a prioritized fashion similiar to the Pareto chart which we are all familiar with. The major difference is that the FMEA provides actions and responsibilities and a feedback on the effect of these actions via the re-calculated RPN. Each element on the FMEA should be looked at as an oppurtunity for improvement, obviously with the higher RPN's providing the greatest bang for a buck. Rather than only focusing on RPN's reaching a level you should look at the entire system. Perhaps reducing a number of smaller RPN's may be more timely or economical than placing all of your resources on a single element. Additionally you should not discount the effect of lowering one RPN on other elements in the system. You may see some surprising relationships.
Reply With Quote
  #7  
Old 15th February 2001, 04:30 PM
AJLenarz AJLenarz is offline
Involved in Discussions

Registration Date: Feb 2001
Location: Canton, Ohio
Age: 38
 
Posts: 47
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 36
Karma: 10
AJLenarz has less than 100 Karma points so far.
I’m agreeing with Al. In the spirit of continuous improvement, there needs to be some kind of prioritized reduction plan (a.k.a… the pareto chart).

I have facilitated a number of FMEA meetings. I have noticed if there is a arbitrary cut off value, all of the RPN’s magically and conveniently fall below that value. Now, it make take a bit of time and group justification to accomplish this, but by the end of the day they have convinced themselves of it.

If the RPN’s are on a pareto chart, I have found the group to achieve more realistic RPN’s and make the FMEA process more productive.

Anybody else experience this?


[This message has been edited by AJLenarz (edited 15 February 2001).]

[This message has been edited by AJLenarz (edited 15 February 2001).]
Reply With Quote
  #8  
Old 15th February 2001, 06:33 PM
Al Dyer
Unregistered Guest

 
Posts: n/a
BIG Smile

AJ,

Also agree and have been through it in depth.

Once a limit is set, it seems to be the mind set that human nature will direct you to set your "goals" below the acceptable limit.

Although goals need to be set, once continuous improvement is in place those goals have to be reset downward to continue the improvement process.

I think that internal goals, such as "PPM" must be set lower than any customer expectation.

I believe and have read/heard the mantra "Zero Defects".

Work this entire process into the actual cost of making a good product and we can all see that doing it right in the first place is a good premis, but that finding the faults in the process will lead to real, quantifiable results.

MHO

ASD...
Reply With Quote
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > FMEA and Control Plans

Bookmarks

Tags
fmea, prioritizing, sxo


Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
FMEA Form - Clarification on correct way of filling up (key/fmea date, rev) qalsang FMEA and Control Plans 1 1st September 2009 02:16 AM
FMEA 4th Edition Blank P and D FMEA sheets in Excel .xls spreadsheets qualityboi FMEA and Control Plans 13 12th August 2009 06:06 AM
Need Help with Process FMEA Basics - Feasibility Analysis Outputs are Inputs to FMEA? ilarioduo FMEA and Control Plans 24 28th June 2006 11:02 AM
FMEA 3rd edition - FMEA is required only for high risk operations? Andrews FMEA and Control Plans 7 24th March 2006 02:20 PM
FMEA Information Centre Internet Web Site and FMEA Use Survey Howard Atkins FMEA and Control Plans 6 15th January 2005 06:00 PM



The time now is 03:23 PM. All times are GMT -4.
The time zone can be changed in your UserCP --> Options.



   

All Y'All Come Back Now, Y' Hear?

Made With A Mac! FreeBSD OS Powered by Apache!
Using php4 Forums provided and maintained by Marc Smith Database by MySQL

FAIR USE and CORRECTNESS NOTICE: This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe herein constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/ If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. In addition, I do not guarantee the correctness of the content. The risk of using content from the Elsmar Cove web site and forums remains with the user/visitor.

Responsibility Statement: Each person is responsible for anything they post in the Elsmar Cove forum. Neither I, Marc Timothy Smith, nor any of the forum Moderators, are responsible for the content of posts people make. Liability for post content resides with the poster as does interpretation and/or acceptance and/or use of advice by the reader.

Complaints: If you have a complaint with a post in a forum discussion thread, including Content in general, fighting, flaming, copyright infringement, defamation and/or 'slander', please use the 'Report This Post Report This Post Button button which appears at the top of every post in every thread.

Site courtesy of:
Marc Timothy Smith - Cayman Business Systems, 8466 Lesourdsville-West Chester Road, West Chester, Ohio 45069-1929 - USA
(513) 341-6272

To contact me, click the Google Voice link below, enter Your Name and Your Phone Number and Google will ring your phone and connect you for free!

The Elsmar Cove Web Site is *CopyFree*
no new posts