Paragraph 4.14.3 b) - When is a Preventive Action required?
Can someone help me with this section of the standard. I am confused as to many things.
Example:
Paragraph 4.14.3 b) states "determination of the steps needed to deal with any problems requiring preventive action"
My definition of "preventive" was to take action before a problem occurred. I.E.: Maintainence on equipment, calibration of gages, inspection of raw material before use are some of my examples of preventive actions. Taking action to "deal with any problems" is corrective action in my book.
What am I missing here - any help????
Thanks,
CarolX
|

20th July 2000, 03:17 PM
|
 |
Forum Moderator
Registration Date: Mar 2000
Location: MID-WEST USA
|
|
Posts: 486
Thanks Given to Others: 0
Thanked 4 Times in 3 Posts
Karma Power: 51 Karma: 114  
|
|
Here's a place to start. Don't be worried about confusion with this one!!
http://Elsmar.com/ubb/Forum31/HTML/000023.html
If you are familliar with D-FMEA or P-FMEA conducted Prior to a problem occuring and/or 8D 5Y after a reported defect occurance... it will help give you a better idea of the prevent - correct dilema..
Regards
Jim
[This message has been edited by Jim Biz (edited 20 July 2000).]
|

20th July 2000, 04:46 PM
|
 |
Super Moderator
Registration Date: Jun 2000
Location: North of Chicago,Illinois, USA
Age: 49
|
|
Posts: 2,087
Thanks Given to Others: 419
Thanked 314 Times in 234 Posts
Karma Power: 176
|
|
|
WOUCH - I can see I am not the only one to ever have problems with this one. Thanks for the lead - truly appreciated.
I will continue to hash through this one - should be fun (NOT)!
Regards,
CarolX
|

10th April 2001, 07:09 PM
|
|
|
Preventive Action or Not
The may be straight forward, but we have had some discussion here so I wanted a outside opinion for clarification.
Example: Parts are rejected from the mfg floor for a nonconformance, some problem with them. Its not a serious trend right now, the rejection of this part. The question would be, Can a Preventive Action be written to have this part that remains in stock, checked and if necessary rejected, so no more are issued to the floor to prevent further rejects which slows production??
Or is this a case that a CAR should be written ??
Thank you for your input
Bryan
|

10th April 2001, 08:08 PM
|
 |
Forum Moderator
Registration Date: Mar 2000
Location: MID-WEST USA
|
|
Posts: 486
Thanks Given to Others: 0
Thanked 4 Times in 3 Posts
Karma Power: 51 Karma: 114  
|
|
Just IMHO:
I'd call it corrective: it already happened wether or not it got shipped out or not it was not prevented before it occured.... if/when there are other similar products that may show the same condition in the future then I'd call those actions preventative.
Guess I'm operating on the assumption that the error in reality-found-you or occured prior to a preventative application in place ... that's corrective - any action taken prior to an actual error occuring is preventative
Regards
Jim
|

10th April 2001, 08:26 PM
|
|
|
|
Jim,
Agree that this instance is a corrective action.
Shouldn't the initial corrective action also identify like proceeses/products that could be affected and therefore corrected?
If the same problem occurs again in the like process that has been corrected, wouldn't that then become another corrective action and open up the effectiveness of the original corrective action.
I think we are on the same wave length:
Corrective Action - Occurred
Preventive Action - Could Occur (FMEA?)
Continuous Improvement - All's well, let's improve it
ASD...
|

11th April 2001, 09:58 AM
|
 |
Super Moderator
Registration Date: Feb 2001
Location: Wellington, OH USA
Age: 69
|
|
Posts: 1,604
Thanks Given to Others: 80
Thanked 289 Times in 172 Posts
Karma Power: 149
|
|
|
I sure don't want to get hung up on semantics here and basiclly I agree with Al but I don't think his definitions go far enough to seperate Prevention and Continuous Improvement. To be a Prevention, it must have the same "all's well" characteristic as the C/I. To me the big difference is that the true Prevention has no measureable or goal (other than 0 which has been the state all along - otherwise you would be doing a C/A). There is never an occurance if the Prevention is successful. On the other hand, every C/I has a goal and a measureable (or else it would be called a "Continuous Status-Quo").
Just my opinion but it seems to make life easier here in tracking and the auditors have never raised an objection.
Dave
|

11th April 2001, 07:35 PM
|
|
|
Quote:
Originally posted by D.Scott:
I sure don't want to get hung up on semantics here and basiclly I agree with Al but I don't think his definitions go far enough to seperate Prevention and Continuous Improvement. To be a Prevention, it must have the same "all's well" characteristic as the C/I. To me the big difference is that the true Prevention has no measureable or goal (other than 0 which has been the state all along - otherwise you would be doing a C/A). There is never an occurance if the Prevention is successful. On the other hand, every C/I has a goal and a measureable (or else it would be called a "Continuous Status-Quo").
Just my opinion but it seems to make life easier here in tracking and the auditors have never raised an objection.
Dave
|
Dave,
I agree, I did not go far enough into the thought process behind my comment. Here goes,
A hypothetical situation #1:
I use FMEA review and prioritize the RPN's for preventive action projects.
Do I have a measurable? Yes, the reduced RPN (if successful)
Do I gave a goal? Yes, the lowest RPN possible.
Can I have an RPN of "0"? Common sense says no, no process is perfect.
Hypothetical #2:
I am running a daily chart on out internal PPM. The goal (limit) is 25.
1: My daily reading for the last month show I am consistently running in a range of 5-10 PPM. I say, people we can do better. Let's start a "continuous improvement" project.
2: Same as month 1 (5-10 PPM). At the start of month 2 we start to see the daily PPM's creeping up towards 13-18. I say, people, let's start a "preventive action" project. My reasoning is that we are within our goals but we want to prevent the PPM from going any higher.
3: Same as month 1 (5-10 PPM. I look at yesterdays data and see that the PPM is at 50. I say, people, shut down the process and begin a "corrective action" immediately!
I think any auditor worth their salt will see that there is a fine line between preventive action and continuous improvement. If a company documents that they are acting upon their defined measurables and improving their processes and systems there should be little discussion between the fine line between the 2 activities.
ASD...
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|