Quote:
In Reply to Parent Post by kemble
There are product and process characteristic column on the Control Plan,can I put them at the same row(No./Product/Process)?Which CP table is right on the attatched picture file?
Could someone please give me some explanation about the characteristic block on th Control Plan?
Thanks a lot!
|
If the two items in your example require different controls, they should be on separate lines, as in the second example. For instance, you may need an inspection control wherein a force test is required, and you may also need some sort of test or verification of the material. Presumably the material test would come before the force test--the controls on the PCP should be listed in order of occurrence.