The Elsmar Cove Forum and Site Map The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page

Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > Supplier Quality Assurance and other Supplier Issues


The Elsmar Cove Forum SideBar!
Monitor the Forum
Monitor New Forum Posts
New Threads Feeds
RSS FeedRSS Feed
Sponsor Link










$ Contributor Forum Access
Courtesy Quick Links

Links that Elsmar Cove visitors will find useful in your quest for knowledge:


Howard's International Quality Services

Atul's Symphony Technologies

Dave Scott's Scott Quality Solutions

Praxiom Research Group


NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest Portal

IEST - Institute of Environmental Sciences and Technology

ASQ - American Society for Quality


All the Important Standards and Related Web Sites in the World
Reply
 
Thread Tools Search this Thread Rating: Thread Rating: 1 votes, 4.00 average. Display Modes
  #1  
Old 8th February 1999, 05:29 PM
Daniel Emond
Unregistered Guest

 
Posts: n/a
Default Subcontractors development

Would anybody tell me what kind of subjects we may develop first with a supplier that is not very concerned by the OEM ?

We have identified our critical subcontractors. But we produce items for customers who make business with OEM. It has already been hard for us to follow all QS9000 requirements (like PPAP for example). So, we anticipate the answers of our suppliers if we ask them to built stuff like "control plan" or "FMEA" ?

Any comments ?

Reply With Quote

Sponsored Links
  #2  
Old 8th February 1999, 11:49 PM
Howard Atkins's Avatar
Howard Atkins Howard Atkins is offline
Forum Administrator

Registration Date: Jul 1997
Location: Revivim, Israel
 
Posts: 2,412
Thanks Given to Others: 100
Thanked 448 Times in 253 Posts
Blog Entries: 8
Karma Power: 195
Karma: 4817
Howard Atkins is appreciated, and has over 1700 Karma points.
Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.Howard Atkins is appreciated, and has over 1700 Karma points.
Send a message via Skype™ to Howard Atkins
Default

This is one of the big problems. My customers, Tier 1 or OEM do not conform to this clause in my respect and any attempts by me to receive help advice, training is generally rebuffed .
We are now in a situation wherby we are required to show our customers the warrant of our purchased parts.
I try to explain them the requirements and expect that they will give me a control plan , not neccesarily as I submit but as a collection of their work instructions, which is what the control plan really is. The enlightened suppliers realise that the requests by me are in the long run to their benefit.
It is a lot of work and if we do not do it we will get a non conformacy.
Ask for the simple stuff first .
Howard
Reply With Quote
Sponsored Links

  #3  
Old 9th February 1999, 09:25 AM
Daniel Emond
Unregistered Guest

 
Posts: n/a
Default

Thanks for your comments Howard. We have requested us almost the same. Our purshasing manager have recently completed the annual subcontractor's evaluation. We sent in the same mailing some directives to explain to the critical subcontractors our needs related to the subcontractors development.

Basically, we ask for their control plans. We explained us the difference between a "control plan" and "an inspection and test plan" that we used to talk with ISO standards. Almost of our critical subcontractors are ISO 9002 registered or maybe more.

So, we simply explained us, as a first request, the added elements compared to ITP as: "reaction plan", "special characteristics, ...
Reply With Quote
  #4  
Old 1st March 1999, 12:14 PM
Steven Sulkin
Unregistered Guest

 
Posts: n/a
Default Definition of "Development"

In an effort to define our scope, I need to understand ISO/QS's definition of "Development."

Anyone seen the definition, or at least a distinction between Design and Development from ISO or QS?

Background information: my employer does not have design responsibility insofar as setting dimensional and chemical specs. We are, however, responsible for developing the processing steps that will result in the desired performance results. Does our responsibility classify as development rather than design?

Thanks in advance,
Steve.
Reply With Quote
  #5  
Old 3rd March 1999, 06:24 PM
Batman
Unregistered Guest

 
Posts: n/a
Default

Steve,
I had the same discussion (nicely put) with my Engineers in 96 as we were developing the APQP Level II and III's. They oh so wanted to include the DESIGN part of APQP. I explained that we do not (have never) owned a drawing, and do not have the authority to change it, but their arguement was that we "design" the process that makes the product. I agreed that we do in fact put together the process - Man, Materials, Machinery, etc. - to make the parts, but that is NOT what is meant by DESIGN. THAT is DEVELOPMENT. When I am asked about this, my simple answer is always "Who's name is on the Request for Quote?" Having a Request for Quote is actually the answer.
Reply With Quote
  #6  
Old 4th March 1999, 01:26 AM
Christian Lupo
Unregistered Guest

 
Posts: n/a
Default

Steve-

geez Steve i really don't think there is a difference. Design responsible is defined as if a supplier (your company) has the authority to establish a new, or change an existing product specification for any product shipped to a customer. Customer approval of a design responsible suppliers product does not waive the supplier's design responsible status. Ask your customer's SQE for clarification.

At our company we develop a certain design, but our customer wants design responsibility. We still have to document everything required in section 4.4 eventhough we are not design responsible.

What your customer is doing is analogus to hiring a subcontractor to develop a product. The customer "owns" the design your are the subcontractor hired to do it.
Reply With Quote
  #7  
Old 24th January 2000, 03:13 PM
Al
Unregistered Guest

 
Posts: n/a
QS-9000 Subcontractor Development

A recent external auditor defined "development" and the wording of 4.6.2.1 so literally that even a subcontractor's QS-9000 registration wouldn't mean that we could stop with their development (ie: continuous improvement). We currently tier our suppliers regarding development activities, do surveys and annual performance apprasials/awards. How much is enough? Certainly you can't force a large supply base into compliance when some of the big ones don't care about automotive or our business.
Reply With Quote
  #8  
Old 25th January 2000, 05:19 AM
Marc's Avatar
Marc Marc is online now
Your Elsmar Cove Host

Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
 
Posts: 15,857
Thanks Given to Others: 1,895
Thanked 1,567 Times in 1,019 Posts
Blog Entries: 4
Karma Power: 605
Karma: 11564
Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.
Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.Marc is appreciated, and has over 1700 Karma points.
Send a message via AIM to Marc Send a message via Skype™ to Marc
Yin Yang

I've seen a range of supplier development from a survey every year to the extremem of haviong someone at a supplier's facility every day. In my opinion, what you are doing is sufficient.
Reply With Quote
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > Supplier Quality Assurance and other Supplier Issues

Bookmarks


Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Supplier Development Requirements - TS 16949 andrewg ISO/TS 16949 - International Automotive Quality Systems Standard 46 30th November 2006 12:40 PM
Supplier Development - Cited for 'no evidence of subcontractor development' barbt Supplier Quality Assurance and other Supplier Issues 7 11th February 2005 08:51 AM
TS 16949 Clause 7.4.1.2 - Supplier Development and ISO 9000 Registration Requirement Kerry Supplier Quality Assurance and other Supplier Issues 18 22nd October 2004 01:47 PM
Are You Meeting Subcontractor (Supplier) Development Requirements? Andrews Supplier Quality Assurance and other Supplier Issues 10 9th June 2003 07:27 PM
QS-9000 Clause 4.6.2.1 and Interpretation C9 - Subcontractor Development Andrews QS-9000 - American Automotive Manufacturers Standard 41 9th June 2003 07:08 PM



The time now is 11:48 PM. All times are GMT -4.
The time zone can be changed in your UserCP --> Options.



   

All Y'All Come Back Now, Y' Hear?

Made With A Mac! FreeBSD OS Powered by Apache!
Using php4 Forums provided and maintained by Marc Smith Database by MySQL

FAIR USE and CORRECTNESS NOTICE: This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe herein constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/ If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. In addition, I do not guarantee the correctness of the content. The risk of using content from the Elsmar Cove web site and forums remains with the user/visitor.

Responsibility Statement: Each person is responsible for anything they post in the Elsmar Cove forum. Neither I, Marc Timothy Smith, nor any of the forum Moderators, are responsible for the content of posts people make. Liability for post content resides with the poster as does interpretation and/or acceptance and/or use of advice by the reader.

Complaints: If you have a complaint with a post in a forum discussion thread, including Content in general, fighting, flaming, copyright infringement, defamation and/or 'slander', please use the 'Report This Post Report This Post Button button which appears at the top of every post in every thread.

Site courtesy of:
Marc Timothy Smith - Cayman Business Systems, 8466 Lesourdsville-West Chester Road, West Chester, Ohio 45069-1929 - USA
(513) 341-6272

To contact me, click the Google Voice link below, enter Your Name and Your Phone Number and Google will ring your phone and connect you for free!

The Elsmar Cove Web Site is *CopyFree*
no new posts