|
|
 |

10th July 2002, 12:15 AM
|
|
Involved - Posts
Registration Date: Oct 2001
Location: Chennai - India
Age: 32
|
|
Posts: 293
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 39 Karma: 43 
|
|
8.2.2 Internal audit
8.2.2 Internal audit says "The management responsible for the area being audited shall ensure that actions are taken without UNDUE DELAY to eliminate detected non-conformities".What does UNDUE DELAY mean.If some corrective actions takes 2 months to implement does it mean it is a non-conforming situation.
What will happen if some of the internal audit NCR's are still open during the routine surveillance audit by the cerifying body?
|

10th July 2002, 08:05 AM
|
 |
Send Martini's !!!!!!!
Registration Date: Feb 2002
Location: Wine Country, NY
Age: 38
|
|
Posts: 201
Thanks Given to Others: 1
Thanked 23 Times in 19 Posts
Karma Power: 42
|
|
Dare I use this in the Quality Field: Here goes. Just use some simple common sense. There is no definition for undue delay. Don't read too much into this. If an audit finding is essential enough to require a C/A, that will in turn add cost effective value, just have it scheduled with the respective dept and get it done when it is feasible. Agree that it needs to happen before you officially document it. Dont be a policeman just writing tickets. The ongoing open items that you speak of that can drag on for months and months and then are fabricated to close out usually were issued without discussion and werent important enough to start with. If it is a 2 month projet, that's O.K. The most important part IMHO is to use common sense when you document the actions, so that you dont create a giant listing of them to look "good" at audit time and then feel the pressure just to close them out on paper for the scumbag 3rd party auditors. Get the buy in that this is an improvement tool and you're not just out there to find stuff wrong. Good luck !!!
__________________
Operator Error cannot be the Root Cause. Oh, unless you're a Pilot.
|

10th July 2002, 08:21 AM
|
 |
Super Moderator
Registration Date: Feb 2001
Location: Wellington, OH USA
Age: 69
|
|
Posts: 1,604
Thanks Given to Others: 80
Thanked 289 Times in 172 Posts
Karma Power: 149
|
|
IMHO there is nothing wrong with corrective actions being open as long as they are being actively worked on. I have seen some companies trap themselves into a corner by stating in a procedure that the C/A must be closed within 60 or 90 days only to find it is impossible to complete the permanent corrective action in that time.
To my thinking, UNDUE DELAY would be doing nothing about the issue for any period over a week or so. If you do the investigation and root cause determination, implement an interim corrective action but have to order a piece of equipment that will take 6 months to arrive, you can't determine any "undue" delay. If on the other hand, you waited 2 months before starting the C/A, that probably is "undue" delay.
Whenever a subjective requirement is made, there will be different interpretations of what it means. AIAG "clarified" the term "timely" by stating this meant "days, not weeks". The difficulty comes when judging when the clock starts ticking.
My opinion is that if you are doing what you reasonably can to close your C/As, not dragging your heels, and keeping your customer (internal or external) up-to-date - you will have no problem with your registrar.
Dave
__________________
"Time you enjoyed wasting is not wasted time"
|

10th July 2002, 09:11 AM
|
 |
Super Moderator
Registration Date: Jan 2001
Location: NC, USA
|
|
Posts: 3,140
Thanks Given to Others: 318
Thanked 770 Times in 525 Posts
Karma Power: 255
|
|
Greetings
I gotta go with the flow here, there is nothing that says that corrective actions cannot take months to finish. My advice to you is to be very thorough in you CA system when you schedule corrective actions.
Point one: do not confuse corrective actions with root cause analysis or managing problems, nonconformances. I have found that a lot of people don't fully understand the whole process. I think that ISO would do the world a service if they talked about problem/issue management instead of corrective and preventive actions.
Point two: If a corrective action is truly needed, make sure you are specific in scheduling and assigning activities. Don't say "Joe will fix it" Each step should be assigned and scheduled. 1) purchasing agent will issue a PO for the Whatchamaycallit. Lead time is 3 weeks. Delivery due on 7/31/02. 2) Whatchamaycallit will be set up by maintenance. Task time is 1 week. Action due date is 8/7/02. 3) Newly installed Whatchamaycallit will be trialed, and operators trained. Equipment and process capabilities will be assessed. Training will take approximately 3 weeks and will be done at the same time the equipment is trialed. Capability assessments will take aproximately 3 more weeks. Action due date is 9/30/02.
If you set up each action and follow up on it soon after the due date, you will be able to adjust schedules for any unforeseen problems. (like the barge that ran aground last nite  )
Not only have you provided evidence of corrective and/or preventive actions, but you can also use these as part of the quality planning process when applicable. I have been involved in corrective actions that took 2 years to complete. Of course there were many interim actions that were taken to minimize risk until new lines could be purchased, fabricated and installed. Just make sure you can show you have a schedule, you are on top of it, and making progress!
Good luck!
__________________
"It's fun to have fun, but you have to know how", Dr. Seuss
Man may have invented fire, it took a woman to learn how to play with it.
|

10th July 2002, 09:36 AM
|
|
Courtesy Access
Registration Date: Sep 2001
Location: Southern Indiana
Age: 47
|
|
Posts: 941
Thanks Given to Others: 3
Thanked 29 Times in 25 Posts
Karma Power: 65
|
|
Common sense applies. Action - as a part of CA containment must be done without undue delays. So IMO containment is the immediate (undue) action as a part of the CA process. When I find an N/C during an audit containment is done immediately as well as when a N/C is detected by other methods.
|

10th July 2002, 11:40 AM
|
 |
VINI, VIDI, DORMIVI
Registration Date: Feb 2002
Location: Walled Lake, Michigan
|
|
Posts: 1,153
Thanks Given to Others: 20
Thanked 79 Times in 51 Posts
Karma Power: 84
|
|
No Undue Delay to me would be putting in place whatever it took to protect the customer from receiving bad product (containment). The closure of the CAR would come when you can prove out the preventive action (no directed time frame).
All of us agreeing on basically the same thing!!!!! Is it a Friday the 13th or something?? What's up with that?
__________________
"What this country needs is more unemployed politicians." Edward Langley
|

10th July 2002, 11:51 AM
|
|
Inactive Registered Visitor
Registration Date: May 2002
Location: Toronto
|
|
Posts: 46
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 31 Karma: 10 
|
|
I agree with 'SteelMaiden' (Wonderful name!). Corrective action should, where appropriate, be accompanied by an action time line. The progress can be then tracked against the timeline. Un-due delay then would be, not adhering to the time line wiithout a valid reason.
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|