The Elsmar Cove Forum and Site Map The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page

Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > Preventive Action and Continuous Improvement


The Elsmar Cove Forum SideBar!
Monitor the Forum
Monitor New Forum Posts
New Threads Feeds
RSS FeedRSS Feed
Sponsor Link










$ Contributor Forum Access
Courtesy Quick Links

Links that Elsmar Cove visitors will find useful in your quest for knowledge:


Howard's International Quality Services

Atul's Symphony Technologies

Dave Scott's Scott Quality Solutions

Praxiom Research Group


NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest Portal

IEST - Institute of Environmental Sciences and Technology

ASQ - American Society for Quality


All the Important Standards and Related Web Sites in the World
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  #1  
Old 23rd July 2002, 04:54 AM
tomjess tomjess is offline
Involved - Posts

Registration Date: Mar 2002
Location: New Zealand
Age: 50
 
Posts: 50
Thanks Given to Others: 0
Thanked 2 Times in 2 Posts
Karma Power: 33
Karma: 17
tomjess has less than 100 Karma points so far.
Default Quality Management Teams

What are Quality Management Teams and how do they work?

I have to introduce it to my company. I am wondering how it works and what needs to be done.

Any ideas and pointers will be great

Thanks in advance
Reply With Quote

Sponsored Links
  #2  
Old 23rd July 2002, 06:32 AM
sneekparty sneekparty is offline
Inactive Registered Visitor

Registration Date: Jun 2002
Location: The Netherlands
Age: 29
 
Posts: 32
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 31
Karma: 10
sneekparty has less than 100 Karma points so far.
Default We call them Quality Improvement Teams

Hi Tomjess,

I am the first who reacts to your post, but I think I will not be the last..This is a subject where everybody has an opinion...so you came to the right place...

But now something about my experiences with QT (Quality Teams)..Well when we first started with QT we looked at where should we be focusing on in the first place...because you can't do the whole process at once...So we first focused our energy on just one department...(and not R&D, this is something where a lot of improvements can be made, but very difficult to start with)..
We then looked which persons should be capable to form the QT..
We started up a team...with disciplines from R&D until the packaging department...After determining the team..we began our first meeting..in which I and a member of the Board of Directors (important for commitment)...spoke about the goals we had for this team...after spoken generally we split up and gave them an assignment come up with at least one problem on the departement we want to discuss...

At the second meeting we discussed the problems and how we could solve those problems...after a while we came familiar with the process and we expanded it to more departments and once we even invited suppliers and customers to help us improve our processes...

Well hope this helps you...and I hope to hear from the others what they think about this subject...

Grtz,
Martin
__________________
"Plan, do, check and act all in one day?"
Reply With Quote
Sponsored Links

  #3  
Old 23rd July 2002, 09:17 PM
tomjess tomjess is offline
Involved - Posts

Registration Date: Mar 2002
Location: New Zealand
Age: 50
 
Posts: 50
Thanks Given to Others: 0
Thanked 2 Times in 2 Posts
Karma Power: 33
Karma: 17
tomjess has less than 100 Karma points so far.
Default Sorry, Quality Improvement Teams

I should have written Quality Improvement Teams.

Sorry.
Reply With Quote
  #4  
Old 23rd July 2002, 11:37 PM
Al Dyer
Unregistered Guest

 
Posts: n/a
Default

1: Define the problem
2: define the facilitator
3: Facilitator convenes a team
4: Facilitator ensures that there is a rep from all departments
5: Facilitator decides who the champion of the team will be
6: Facilitator ensures that all tools are available.
7: Facilitator ensures that meetings run smoothly
8: Facilitator ensures that all actions decided by the team are proper and acted upon

Notes:

-Make the group leader a person that has the ability to speak and to somewhat control a group.

-Make the loudest, most objectional person in charge of the team and give them the authority

-Some people don't say much in groups, but can have alot of positive input, give them an avenue to submit ideas and thoughts other than in an open meeting format

-Realize that as a facilitator that you might have to "shut" someone down. Do what you have to do to ensure the group dynamics.

-Make sure that facilitators have read a book or been trained in group dynamics.

-Know when to cut your losses if a group is not performing to the expected results. Everybody makes a mistake.

I have more, but I think you get the gist of my message!
Reply With Quote
  #5  
Old 24th July 2002, 09:11 AM
gpainter gpainter is offline
Courtesy Access

Registration Date: Sep 2001
Location: Southern Indiana
Age: 47
 
Posts: 941
Thanks Given to Others: 3
Thanked 29 Times in 25 Posts
Karma Power: 65
Karma: 696
gpainter is appreciated, and has over 500 Karma points.gpainter is appreciated, and has over 500 Karma points.gpainter is appreciated, and has over 500 Karma points.gpainter is appreciated, and has over 500 Karma points.gpainter is appreciated, and has over 500 Karma points.gpainter is appreciated, and has over 500 Karma points.
Default

Do away with the "Q" word and make it Improvement Teams. This way it helps everyone and is not just another Quality thing that is the QA Departments deal.
Reply With Quote
  #6  
Old 27th July 2002, 09:58 PM
Kevin Mader's Avatar
Kevin Mader Kevin Mader is offline
One of THE Original Covers!

Registration Date: Nov 1998
Location: Wallingford, CT USA
Age: 43
 
Posts: 1,158
Thanks Given to Others: 22
Thanked 63 Times in 43 Posts
Karma Power: 94
Karma: 1335
Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.Kevin Mader is appreciated, and has over 1300 Karma points.
Send a message via AIM to Kevin Mader
Default

I like to use the term "value makers" when addressing folks in the organization. Basically, I think that Value is at the center of the System.

Regards,

Kevin
__________________
"Without theory there is nothing to modify or learn." W. Edwards Deming
Reply With Quote
  #7  
Old 28th July 2002, 12:39 AM
NITIN's Avatar
NITIN NITIN is offline
Involved - Posts

Registration Date: Apr 2002
Location: UAE
Age: 34
 
Posts: 33
Thanks Given to Others: 0
Thanked 1 Time in 1 Post
Karma Power: 31
Karma: 15
NITIN has less than 100 Karma points so far.
Default

You could start process audits based on department relations defined by your QMS.Doing audits is a great way of learning and improving.
__________________
We must be the world we want to create.
Reply With Quote
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Forum > Common Quality Assurance Processes and Tools > Preventive Action and Continuous Improvement

Bookmarks


Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Report template for quality process audits of the software product teams gopilr Internal Auditing 1 22nd April 2008 08:22 AM
Do your internal auditors work in teams or individually? GStough Internal Auditing 29 8th February 2007 08:44 AM
Self Directed Work Teams - Anyone using SDWT in their company? gpainter Manufacturing and Related Processes 19 20th August 2005 03:47 PM
Plant Quality 'War Room' - Advanced Program Teams Jgryn Misc. Quality Assurance and Business Systems Related Topics 1 25th August 2004 02:53 PM
Teams and Lean Manufacturing Schroeder Lean - Lean in Manufacturing and Services 20 25th October 2001 03:09 PM



The time now is 06:23 AM. All times are GMT -4.
The time zone can be changed in your UserCP --> Options.



   

All Y'All Come Back Now, Y' Hear?

Made With A Mac! FreeBSD OS Powered by Apache!
Using php4 Forums provided and maintained by Marc Smith Database by MySQL

FAIR USE and CORRECTNESS NOTICE: This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of environmental, political, human rights, economic, democracy, scientific, and social justice issues, etc. We believe herein constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/ If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. In addition, I do not guarantee the correctness of the content. The risk of using content from the Elsmar Cove web site and forums remains with the user/visitor.

Responsibility Statement: Each person is responsible for anything they post in the Elsmar Cove forum. Neither I, Marc Timothy Smith, nor any of the forum Moderators, are responsible for the content of posts people make. Liability for post content resides with the poster as does interpretation and/or acceptance and/or use of advice by the reader.

Complaints: If you have a complaint with a post in a forum discussion thread, including Content in general, fighting, flaming, copyright infringement, defamation and/or 'slander', please use the 'Report This Post Report This Post Button button which appears at the top of every post in every thread.

Site courtesy of:
Marc Timothy Smith - Cayman Business Systems, 8466 Lesourdsville-West Chester Road, West Chester, Ohio 45069-1929 - USA
(513) 341-6272

To contact me, click the Google Voice link below, enter Your Name and Your Phone Number and Google will ring your phone and connect you for free!

The Elsmar Cove Web Site is *CopyFree*
no new posts