Hi Guys
Should we have a formal documented procedure (talking QS9000 here) for the control of the design of gauges (i.e. special gauges we make in-house) ?
Or if we operated a proper MSA programme on gauges would that negate the need for such a procedure ?
Please advise your thoughts as I am currently in two minds (maybe more).
|

9th August 2002, 10:37 PM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,857
Thanks Given to Others: 1,895
Thanked 1,566 Times in 1,018 Posts
Karma Power: 605
|
|
I would look at what's happening now. I'm not sure how you can 'control' a fixture design process outside of the standard design process template. Hiring / job criteria may also play a part. That is to say, is a requirement of the position to have experience in gage design? There is the benefit of standardization any time you document a process, including a design process.
As far as an R&R, I'm not sure how that would apply. Amongst other aspects, an improperly designed fixture may give you a good R&R but by design is not even really measuring what you think you're measuring. Especially when you look at GD&T issues in some designs and other aspects such as material flexability (e.g.: When is restraint necessary? Which surface do you restrain and why? Etc., etc.).
I see them as different issues entirely. The first thing I assume is that a gage / fixture is poorly designed and take a look for myself as to whether I think the gage / fixture designer knew what s/he was doing.
Are you currently having problems? Or are you thinking something else.
__________________
A Search is a terrible thing to waste!
One Test is Worth 1000 Expert Opinions - The plural of anecdote is not data.
We can't solve problems by using the same kind of thinking we used when we created them. - Unknown
|

17th August 2002, 05:44 PM
|
 |
Courtesy Access
Registration Date: Dec 2001
Location: England
|
|
Posts: 1,643
Thanks Given to Others: 10
Thanked 63 Times in 44 Posts
Karma Power: 80
|
|
Sorry for the delay in replying - been on my hols again.
This question really stems from internal audit findings. I could re-word it to suit ISO9001:2000 in that the gauge design 'process' is not adequately defined. i.e. when I ask who designs gauges the answer is practically 'anyone we can get hold of' (i.e. internal 'product' engineering staff or external sub-contractors), when I ask where are master drawings kept the answer is 'dunno, some are here but Im not sure if they are masters', when I ask who has approval authority for gauge design I get a complete blank expression, etc, etc.
Now I think this is a valid audit finding, but also a recent complaint has also highlighted deficiency in the gauge design process (I try to align my audit findings with real current business issues).
Now is my audit finding valid, or are gauges a special case if we perform R&R studies and the like ?
I am kinda thinking this process (procedure) needs defining as it appears anyone can create a new gauge, anyway they like - but I also recognise that R&R, or more specific MSA studies are in effect an excellent design validation tool - hence does the process/procedure need defining if the output is effectively controlled via R&R or MSA.
Yours - still in two minds - MG
|

19th August 2002, 10:47 AM
|
 |
Registration Date: Sep 1999
Location: Oklahoma
Age: 67
|
|
Posts: 1,437
Thanks Given to Others: 1
Thanked 29 Times in 17 Posts
Karma Power: 90
|
|
MG,
IMO, Gage design and gage control would be two distinctly different processes. Gage control is not a problem. It is well defined in the standard/specification.
Gage design is not. Should there be a procedure? IMO yes. It has been my experience in the past that most engineering/design departments maintain a set of design documents. Included in these documents is everything from material/component selection to design equations and test requirements.
I don't see how any design department could function without a set of design procedures. I know, someone is going to say, you will stifle my creativity. Not true, creativity without control is chaos.
As for valid audit finding, I would think it would only be valid if you could reference a paragraph number, otherwise it would be an "opportunity for improvement"
__________________
Sam Goody
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|