Setting AQL (Acceptable Quality Level) on C=Zero inspections
Here's a general question:
We use a C=Zero sampling system for our incoming inspection, using "associated AQLs". What is the best way to determine which AQL to select for a particular part being inspected under this type of system? I have a Quality Engineer that wants to develop a set of "standard AQL levels" for each type of product being inspected.
For example: Rubber seals would always have an AQL of 1.0, nuts and bolts, 10.0, and so on.
Does anybody within the sound of my voice have any input into how this should be handled? We're trying hard not to be arbitrary.
Thanks.
Norman V.
|

16th October 2002, 03:03 PM
|
 |
Dogs rule
Registration Date: Jul 2002
Location: Madison, WI
Age: 56
|
|
Posts: 980
Thanks Given to Others: 15
Thanked 23 Times in 16 Posts
Karma Power: 69
|
|
Sorry, I've got a major disconnect going right now but I'm responding anyway (they say the first thing that goes.......).
I don't see how an AQL has anything to do with a C=0 "sampling plan". By definition, doesn't AQL imply defective/nonconforming parts are OK?
Bill
__________________
There is no psychiatrist in the world like a puppy licking your face. - Ben Williams
|

16th October 2002, 03:12 PM
|
 |
Be Audit You Can Be!
Registration Date: Jul 2001
Location: Philadelphia, PA
|
|
Posts: 30
Thanks Given to Others: 3
Thanked 0 Times in 0 Posts
Karma Power: 36 Karma: 130  
|
|
Ok, let's clarify
In the traditional sense of AQL, (MIL-105-E), you are correct, AQL determines (among other things) how many rejects you can accept in a lot. In a C=Zero system, the "associated AQL" merely is used in a table to help you determine how many samples to pull based on lot size.
The AQL levels are "associated", because the Operating Characterisitic (OC) Curves would look about the same in terms of a percent defective for each AQL level, even though the acceptance number is Zero.
My main questions was, what is the best way to decide how to set the AQL level during the Quality Planning process, aside from just picking an AQL arbitrarily?
Thanks,
Norman V.
|

16th October 2002, 03:45 PM
|
|
An Early 'Cover'
Registration Date: Mar 2002
Location: East Coast US
|
|
Posts: 1,773
Thanks Given to Others: 24
Thanked 51 Times in 39 Posts
Karma Power: 103
|
|
Since it is incoming inspection, I'd sit down with your internal customer(s) who will use each part and discuss it with them. Discuss what impact a defect will have on them - i.e. if there is 1% defective how would that affect you and downstream operations, etc. Also, what has been the incoming quality level in the past, and was it "acceptable" to them in the past. Also consider time of inspection, etc. Some will rant and rave and say no defect is ever "acceptable", but in the real world, IMO, zero defects is a pipe dream. JHO. Hope this helps.
__________________
Mike S. ("Gun Nut")
And they ask me why I drink....
|

16th October 2002, 05:35 PM
|
|
Been around a while
Registration Date: Jan 2002
Location: Southeastern USA
|
|
Posts: 1,995
Thanks Given to Others: 281
Thanked 266 Times in 211 Posts
Karma Power: 171
|
|
Hi
Dr Ken Stephens (Applied Acceptance Sampling, available through ASQ) gives the following steps:
1. Determine and list each quality characteristic
2. Determine the product unit.
3. Develop and specify the test method.
4. Determine the criteria for conformity.
5. Determine and list the calssification of nonconforming units or nonconformities and/or groups of nonconformities.
6. Establish an Index Quality Level (AOQL, etc).
7. Determine if sampling/acceptability should be based on lot inspection, on-line (continuous, etc.
I have excerpted here, and he goes on to more specifics. We used this textg for one of my classes at SPSU, and I can say that if you want to find out about acceptance sampling, this is the text.
The class was mind boggling.
Hope this helps.
|

17th October 2002, 12:52 PM
|
 |
Be Audit You Can Be!
Registration Date: Jul 2001
Location: Philadelphia, PA
|
|
Posts: 30
Thanks Given to Others: 3
Thanked 0 Times in 0 Posts
Karma Power: 36 Karma: 130  
|
|
Mind Boggling?
Craig,
When you say "mind-boggling", do you mean that in a good way or a bad way?
Anyhow, I saw that book in the ASQ catalog, and it does look good. The CD ROM that accompanies it seem interesting as well.
Maybe I'll put it on my Christmas list.
Thanks,
Norman V.
|

17th October 2002, 01:03 PM
|
|
Been around a while
Registration Date: Jan 2002
Location: Southeastern USA
|
|
Posts: 1,995
Thanks Given to Others: 281
Thanked 266 Times in 211 Posts
Karma Power: 171
|
|
Norman:
Mind boggling in both a good and bad way, really.
Before this class, I assumed that Dr. Deming ment that inspection was bad. Not so. What he said, and ment, was that DEPENDANCE on inspection for quality is bad. We still inspect, but our process is such that we don't make bad stuff.
In a bad way, we actually designed acceptance sampling plans - those are some of the major files on the CD. Not for those with less-than-complete statistical backgrounds, IMHO. The class was the most difficult in the SPSU Master's program. We used the draft for Dr. Stephen's book, and he taught the class (online). He is retired now, but his list of publications is impressive, and this particular book is highly recommended.
|

17th October 2002, 01:25 PM
|
|
Courtesy Access
Registration Date: Apr 2002
Location: Lombard, IL
|
|
Posts: 508
Thanks Given to Others: 10
Thanked 41 Times in 24 Posts
Karma Power: 58
|
|
But the question still has not been answered, unless it is in The BOOK? I believe the act of deciding is a step (#6), but are there any generally accepted parameters in making that decision, OR do we have to read the book?
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|