Engineering change validation - Companies that have no design responsibility
Is this applicable to companies that have no design responsibility? Only validation we do is PPAP
|

28th January 2005, 07:08 AM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,852
Thanks Given to Others: 1,892
Thanked 1,563 Times in 1,016 Posts
Karma Power: 604
|
|
If you are not design responsible you are not responsible for design validation. However, in some cases you *might* be part of that process as a 'guest' of the party responsible for the design.
|

28th January 2005, 08:04 AM
|
 |
Dogs rule
Registration Date: Jul 2002
Location: Madison, WI
Age: 56
|
|
Posts: 980
Thanks Given to Others: 15
Thanked 23 Times in 16 Posts
Karma Power: 69
|
|
Quote:
|
Originally Posted by Marc
If you are not design responsible you are not responsible for design validation.
|
I fully agree. However - regarding an engineering change, there have been instances where we have asked for an engineering change and our customer required us to "do" the the part validation. That meant we had to "buy time" on our customer's robots or go to another source to perform the testing. I don't know how common a practice that is, but it has happened.
Just FWIW
__________________
There is no psychiatrist in the world like a puppy licking your face. - Ben Williams
|

29th January 2005, 04:48 AM
|
|
Involved - Posts
Registration Date: Dec 2003
Location: CHENNAI
Age: 29
|
|
Posts: 40
Thanks Given to Others: 1
Thanked 0 Times in 0 Posts
Karma Power: 25 Karma: 10 
|
|
Design Validation
Dear all
As i know the Design validation should be done with in two working weeks.From the date of change of design.
For a company of design responsiablity they have to do the full design validation as per their DESIGN verification plan.
For whom the design is not the company responsiablity they should do the process revied and conduct PPAP to conclude the Design validation.
REGARDS
R.L.SATTHISH KUMAR
ANY VIEWS PL REPLY
|

29th January 2005, 08:29 AM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,852
Thanks Given to Others: 1,892
Thanked 1,563 Times in 1,016 Posts
Karma Power: 604
|
|
Quote:
|
Originally Posted by remsqa
As i know the Design validation should be done with in two working weeks.From the date of change of design.
|
I don't know of any specific time requirement.
Quote:
|
For a company of design responsiablity they have to do the full design validation as per their DESIGN verification plan.
|
Yes.
Quote:
|
For whom the design is not the company responsiablity they should do the process revied and conduct PPAP to conclude the Design validation.
|
Yes.
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|