Regarding AS9100 paragraph 8.2.4.2, how are others in the industry implementing this section?
Can an organization simply write a procedure detailing a simple FAI for those customers who do not require compliance to AS9102 and still be compliant to AS9100?
For example, if I were to write into our manufacturing process to do a FAI at the end of the manufactuing process and include the key characteristics, would this be enough to satisfy the requirement?
|

17th June 2003, 05:42 PM
|
 |
Moderator
Registration Date: Feb 2001
Location: Grand Rapids, Michigan
Age: 48
|
|
Posts: 483
Thanks Given to Others: 36
Thanked 73 Times in 64 Posts
Karma Power: 64
|
|
We were certified last November and our documented FAI process does not comply with AS9102 but it does comply with the paragraph you quoted from AS9100a.
My understanding is that AS9102 is only for use as a guide at this point unless it is flowed down contractually.
Any other experiences?
|

17th June 2003, 06:01 PM
|
 |
Post responsibly
Registration Date: Oct 2001
Location: Long Beach, CA - USofA
|
|
Posts: 4,951
Thanks Given to Others: 688
Thanked 1,912 Times in 1,083 Posts
Karma Power: 467
|
|
Right on the mark
BadgerMan, you are 100 % correct. Unless contractually mandated by your customer, compliance with AS9102 is optional.
I would just like to share that FAI and AS9102 have been subject of many discussions at the AAQG, EAQG APAQG and IAQG meetings. A revised, clearer AS9102 is expected to be released shortly to solve some of the difficulties aerospace suppliers have been encountering.
__________________
Fighting organizational dysfunction, one post at a time.
|
|
Thanks to Sidney Vianna for your informative Post and/or Attachment!
|
|

20th August 2003, 03:42 PM
|
|
Inactive Registered Visitor
Registration Date: Aug 2003
Location: USA, CA
|
|
Posts: 2
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 26 Karma: 10 
|
|
Sidney,
Been hearing about a new release of AS9102 for a while now, any news?
Thx
|

20th August 2003, 04:01 PM
|
 |
Post responsibly
Registration Date: Oct 2001
Location: Long Beach, CA - USofA
|
|
Posts: 4,951
Thanks Given to Others: 688
Thanked 1,912 Times in 1,083 Posts
Karma Power: 467
|
|
Yes. The rev.a of 9102 has been ballotted and approved as far as I know.
I believe that the delay has to do with the two other Sectors involved, ie, Europe and Asia, since they want to have the Standard adopted worldwide.
Next September 8-11 during the next AAQG meeting in Montreal, I believe that they should have an update of when the Rev. A of 9102 and Rev. B of AS9100 should be released.
Hope this helps.
__________________
Fighting organizational dysfunction, one post at a time.
|

20th August 2003, 04:14 PM
|
|
Inactive Registered Visitor
Registration Date: Aug 2003
Location: USA, CA
|
|
Posts: 2
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 26 Karma: 10 
|
|
Yes this information is very helpful, thank you!
|

6th January 2005, 10:18 AM
|
|
Inactive Registered Visitor
Registration Date: Jan 2005
Location: uk
|
|
Posts: 3
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 20 Karma: 10 
|
|
as9102a
i have been tasked to implement this standard for a variety of customers, i feel it could be quite some task getting our inspectors on board. How have others found the implementation process, there does seem an excess of information required it feels like we are re-qualifying rather than doing FAI.
|

7th January 2005, 03:27 PM
|
 |
Moderator
Registration Date: Feb 2001
Location: Grand Rapids, Michigan
Age: 48
|
|
Posts: 483
Thanks Given to Others: 36
Thanked 73 Times in 64 Posts
Karma Power: 64
|
|
Quote:
|
Originally Posted by Tom a
it feels like we are re-qualifying rather than doing FAI.
|
Are customers requesting a full FAI IAW AS9102a for products already in production? So far, our customers have only requested 9102 compliant FAI's for mature products when there are changes. Otherwise, the original FAI was satisfactory.
__________________
Quando Omni Flunkus Moritati
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|