When to submit a new PPAP? Colored resin pre-blended to blending it in-house
There is much confusion within our company concerning when certain changes require a new PPAP submission for a current production part. For example, we are switching from receiving our colored resin pre-blended to blending it in-house--using the exact same base resin and colorant our outside compounder was using.
Our APQP manager says we have to re-PPAP and re-do all testing called out by the specs on the assembly drawing, for each component for which we want to blend resin. (i.e. complete level 3 PPAP...) Our engineering manager disagrees, saying that this change should be transparent to our customer.
Under what circumstances, and in what situations, is it required that a subcontractor submit a new PPAP package for a current production part?
Thanks,
Melissa Weiandt
Associate Buyer
Plastics Div.
|

11th January 2000, 09:11 AM
|
|
|
|
If you are dealing with an automotive customer you DEFINATLY have to re-ppap, unless you get a waiver from your customer. Always ask your customer if you are not sure if you should re-ppap or not. Just make sure you document waht the customer tells you.
|

11th January 2000, 09:22 AM
|
 |
One of THE Original Covers!
Registration Date: Nov 1998
Location: Wallingford, CT USA
Age: 43
|
|
Posts: 1,158
Thanks Given to Others: 22
Thanked 63 Times in 43 Posts
Karma Power: 94
|
|
|
Melissa,
As you already know, PPAP attemps to solidify the process of manufacturing and the control planning you set in place to ensure that all requirements are understood and that the process has the potential to produce these requirements. When the approved process changes, the impact must be determined, and the customer notified as appropriate.
What controls were in place for the original resin/colorant blending? Are they called out in the PPAP documentation? Have they changed? My guess is that your APQP person is probably correct. A change from blending at a source to an internal process (perhaps you are new to this process as well) is fairly significant and will likely have different controls (reference section II of the PPAP manual, 3, 7 and 9 on page 2). With these different controls, items such as the Flow Diagram, Control Plan, and FMEA will all be updated to reflect the change.
I hope this helps.
Regards,
Kevin
|

13th January 2000, 12:03 AM
|
 |
Your Elsmar Cove Host
Registration Date: Jan 1996
Location: West Chester, Ohio - USA
Age: 59
|
|
Posts: 15,857
Thanks Given to Others: 1,895
Thanked 1,566 Times in 1,018 Posts
Karma Power: 605
|
|
Melissa, I also suggest you do a search here for PPAP as this is a topic which has been discussed a number of times. It might give you some other ideas. I just did a Search for PPAP (all forums) and about 80 threads came up.
Quote:
|
...and re-do all testing...
|
The extent of specific retest(s) depends upon the specifics of the change. I would discuss you change(s) with the customer QA rep and ask what they feel is appropriate. In the past when i did this stuff I would make up a plan (proposal) and get the customer to approve it prior to proceeding with the plan. I would say "This is the proposed change" and "This is what we believe the change will affect." The plan says: "This is what we plan to do to ensure the changes do not change the product features we believe will be affected.
An example: If you machine steel parts which can rust -> a packaging change could prompt PPAP but validation would probably be limited to corrosion studies (if you previously validated this aspect).
|

18th April 2006, 01:57 PM
|
|
Well
Registration Date: Sep 2005
Location: Brazil
|
|
Posts: 65
Thanks Given to Others: 2
Thanked 1 Time in 1 Post
Karma Power: 18 Karma: 15 
|
|
if duly it will be waked up with its customer is not necessary re-submit.
|

17th May 2006, 09:18 PM
|
|
Involved in Discussions
Registration Date: Dec 2004
Location: CT.
|
|
Posts: 13
Thanks Given to Others: 3
Thanked 0 Times in 0 Posts
Karma Power: 21 Karma: 10 
|
|
Quote:
|
Originally Posted by chivas industries llc
Our engineering manager disagrees, saying that this change should be transparent to our customer.
|
Tell him that even change of your supplier is transperant to the customer, yet it still requires PPAP.
|

22nd May 2006, 11:19 AM
|
 |
I make things happen
Registration Date: Nov 2004
Location: Toledo, Ohio
Age: 40
|
|
Posts: 53
Thanks Given to Others: 0
Thanked 4 Times in 2 Posts
Karma Power: 27
|
|
Just ask the supplier SQA if it is required, this will leave no doubt. Better yet, maybe ask that individual if they would be willing to come in and have a meeting decsribing what changes require what actions thus alleviating yourselves from this issue in the future.
Murph
__________________
Ran into a chum with a bottle of rum and we wound up drinking all night!
|

8th June 2006, 08:45 AM
|
|
Inactive Registered Visitor
Registration Date: Jun 2006
Location: Swden
|
|
Posts: 9
Thanks Given to Others: 0
Thanked 0 Times in 0 Posts
Karma Power: 15 Karma: 20 
|
|
Re: When to submit a new PPAP? Colored resin pre-blended to blending it in-house
My understanding is that any process change should signal a new PPAP.
Only time you do not need to re-new the PPAP is when STA/SQA has said something else.
|
Lower Navigation Bar
|
|
|
|
Visitors Currently Viewing this Thread: 1 (0 Registered Visitors and 1 Unregistered Guests)
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate Thread Content |
Linear Mode
|
|
Posting Settings
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|