The Elsmar Cove Wiki More Free Files The Elsmar Cove Forums Discussion Thread Index Post Attachments Listing Failure Modes Services and Solutions to Problems Elsmar cove Forums Main Page Elsmar Cove Home Page
Welcome To The Old Cayman Cove Forums!
This thread is carried over and continued in the Current Elsmar Cove Forums


  The Old Elsmar Cove Forums
  General ISO Topics
  1st Articles / initial Sample Submissions.

Post New Topic  Post A Reply
profile | register | preferences | faq | search

UBBFriend: Email This Page to Someone! next newest topic | next oldest topic
Author Topic:   1st Articles / initial Sample Submissions.
gperry
Lurker (<10 Posts)

Posts: 1
From:Mt. Pleasant, SC, USA
Registered: Jan 2000

posted 27 January 2000 11:51 AM     Click Here to See the Profile for gperry   Click Here to Email gperry     Edit/Delete Message   Reply w/Quote
My background is QS-9000 but I now work for a company that is strictly ISO-9000 (custom plastic vacuum thermoforming). I am use to submitting PPAP's and the requirements for what, when and how to submit one. ISO-9000 does not have a section that addresses inital sample submissions; however, some of my customers require them. I have not been able to find nformation concerning 1st articles and how to address them in my procedures. If I use the AIAG requirements for all products some of my customers are overwhelmed by the process. Some of my orders are just not big enough for a 1st article submission. Any advice?

IP: Logged

Kevin Mader
Forum Wizard

Posts: 575
From:Seymour, CT USA
Registered: Nov 98

posted 27 January 2000 12:26 PM     Click Here to See the Profile for Kevin Mader   Click Here to Email Kevin Mader     Edit/Delete Message   Reply w/Quote
What are your Customers expecting?

You may find that everyone has different expectations, so you may have to create many different submission plans. As you accumulate the information, you will probably pick out some of the typical items. With these, you may want to consider adding them to your ISO Quality Program. ISO is a far more vague guideline than you are use to, so the QP you have inherited may not be as specific as you would like/expect.

Regards,

Kevin

IP: Logged

Marc Smith
Cheech Wizard

Posts: 4119
From:West Chester, OH, USA
Registered:

posted 27 January 2000 12:42 PM     Click Here to See the Profile for Marc Smith   Click Here to Email Marc Smith     Edit/Delete Message   Reply w/Quote
And the bottom line is ISO does not address 1st article. Thus, as Don pointed out--> you rely on customer requirements. With several clients we have made up a spreadsheet. Reading down was a list of process elements - design review, etc., to machine runoff (high volume) or whatever right on to final inspection and test. In my first ISO implementation years ago I did this with the ISO requirements, BWM, FORD, etc. We ended up with a list of ISO and customer requirements.

You could do this with the APQP skeleton in mind. Customer A may just want a full layout to print. Customer B may just want a functional test. Customer C may want both of those and maybe capability studies from a runoff.

What the customer asks for should be considered during contract review. If the customer wants 15 widgets and wants runoff data from a 300 piece run (sounds insane, but you never know), you would want to negotiate exact terms and conditions and quote appropriately.

IP: Logged

All times are Eastern Standard Time (USA)

next newest topic | next oldest topic

Administrative Options: Close Topic | Archive/Move | Delete Topic
Post New Topic  Post A Reply
Hop to:

Contact Us | The Elsmar Cove Home Page