  TPM - Total Productive Maintenance
  Implementation

Post New Topic  Post A Reply
profile | register | preferences | faq | search

UBBFriend: Email This Page to Someone! next newest topic | next oldest topic
Author Topic:   Implementation
Nailen
unregistered
posted 06 March 2001 09:46 AM           Edit/Delete Message   Reply w/Quote
How hard is it to implement TPM the second time around.

IP: Logged

WALLACE
Forum Contributor

Posts: 46
From:Ontario, Canada.
Registered: Nov 2000

posted 06 March 2001 01:17 PM     Click Here to See the Profile for WALLACE   Click Here to Email WALLACE     Edit/Delete Message   Reply w/Quote
It all depends what happened the first time around and the kind of business you are in.
The failure to implement TPM has many causes, have you identified any of them?
I come from the Auto sector and,I would be pleased to share information and case studies with you.
Wallace.

IP: Logged

nailen
unregistered
posted 07 March 2001 07:20 AM           Edit/Delete Message   Reply w/Quote
Wallace,

The type of business is a major paper manufacturing and converting company. When we went down the road to implementation we did not use the "Top Down approach". It was driven from the shop floor. The problem we had was Middle and senior management were not participative in the process and this is where it fell down. Now we are in the same postion we were in 3yrs ago, if not worse.

Cheers,

Nailen

[This message has been edited by nailen (edited 07 March 2001).]

IP: Logged

WALLACE
Forum Contributor

Posts: 46
From:Ontario, Canada.
Registered: Nov 2000

posted 08 March 2001 02:37 AM     Click Here to See the Profile for WALLACE   Click Here to Email WALLACE     Edit/Delete Message   Reply w/Quote
Nailen,
I have seen the repercusions of well intentioned shop floor guys taking the reigns when it comes to managing TPM, My experience tells me that top management lack of commitment to TPM issues sends a clear voice to the guys in production that they don't give a @#$% about production maintenance and the fact that down time cost to quality outputs regarding TPM does indeed have a negetive effect on the validity of initial project costs.
I would suspect that if you have a formal registered quality system in place, this would be the most logical first step to take in reviewing top management commitment to issues that effect both system and product quality, I have found that using a flow chart approach to forming procedures for TPM issues is an excellent way to have all departments allowed to express input to formalizing a TPM commitment.
Wallace.

IP: Logged

All times are Eastern Standard Time (USA)

next newest topic | next oldest topic

Administrative Options: Close Topic | Archive/Move | Delete Topic
Post New Topic  Post A Reply
Hop to:

Contact Us | The Elsmar Cove Home Page

Your Input Into These Forums Is Appreciated! Thanks!


UBB 5.45c

Main Site Search
Y'All Come Back Now, Ya Hear?
Powered by FreeBSD!Made With A Mac!Powered by Apache!