Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
UL - Underwriters Laboratories - Health Sciences
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >
Forum Username

Elsmar Cove Forum Visitor Notice(s)

Wooden Line

Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?


Elsmar XML RSS Feed
Elsmar Cove Forum RSS Feed

Monitor the Elsmar Forum
Sponsor Links




Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
cpk (related to process capability), process capability
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 4th July 2017, 07:14 AM
ejmoska

 
 
Total Posts: 2
Question Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?

Hello,

just a small question to which i can't seem to find an answer:

For Cpk calculation, we have:
Target 0%
UCL 2%
LCL -2%
USL 4%
LSL -4%

when calculating Cpk, should we be using LSL/USL or LCL/UCL?

also, if we have out of spec values somewhere within results, should they be left there to display "true" Cpk or moved to another metric, like FPY?

What if the out-of-spec data, jumps to i.e -99%, -30% or 20% this greatly affects mean value, and Cpk no longer shows accurate data. So far we are removing such values which greatly affect mean, but is this really the correct way to go?

Last edited by ejmoska; 5th July 2017 at 01:17 AM.

Sponsored Links
  Post Number #2  
Old 5th July 2017, 12:02 AM
AMIT BALLAL's Avatar
AMIT BALLAL

 
 
Total Posts: 123
Look! Re: Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?

For calculating Cpk, LSL/USL should be used.

Did you use control chart to check presence of any special cause prior to calculating process capability? Is your process in control, but out of specification?

Can you share the SPC report, so that the question can be answered properly?


Thanks,
Amit

Last edited by AMIT BALLAL; 5th July 2017 at 01:28 AM.
Sponsored Links

  Post Number #3  
Old 5th July 2017, 06:10 AM
Bev D's Avatar
Bev D

 
 
Total Posts: 3,547
Re: Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?

Can you also explain how you are applying the calculation? Are you recalculating every lot, week, month? What is the actual sample size you are using?
Why are you calculating Cpk? Is a Customer requiring it or are you doing it because you think it's the 'right thing' to do?

Cpk is potentially very misleading number if not done properly...
  Post Number #4  
Old 5th July 2017, 09:31 AM
Steve Prevette's Avatar
Steve Prevette

 
 
Total Posts: 2,515
Re: Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?

It should be pointed out that you use BOTH the specification limits and the SPC control limits in the Cpk calculation. This is assuming that the SPC chart shows the process is stable. You are basically comparing the spread of the observed variation against the allowed variation, and accounting for if the observed data are "off-center" from the center of the allowed variation (spec).

If your statement "What if the out-of-spec data, jumps to i.e -99%, -30% or 20%" is true, likely the process is not stable, and Cpk does indeed become meaningless. If such "jumps" are actually part of the stable process, then your Cpk is indeed poor. Keep in mind you don't recalculate the mean / UCL / LCL on a whim.
Thanks to Steve Prevette for your informative Post and/or Attachment!
  Post Number #5  
Old 5th July 2017, 09:56 AM
Bev D's Avatar
Bev D

 
 
Total Posts: 3,547
Re: Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?

one caution: the Control limits can be used for comparing the process variation to the specification limits IF the control chart is an I, MR chart for individual data points. We cannot use the control limits from Xbar charts for averages, we would have to calculate the spread of the individual values separately....

we still should still assess stability using a (appropriate) control chart.
Thanks to Bev D for your informative Post and/or Attachment!
  Post Number #6  
Old 5th July 2017, 10:09 AM
Steve Prevette's Avatar
Steve Prevette

 
 
Total Posts: 2,515
Re: Questions regarding Cpk Calculation - Should we be using LSL/USL or LCL/UCL?

Quote:
In Reply to Parent Post by Bev D View Post

one caution: the Control limits can be used for comparing the process variation to the specification limits IF the control chart is an I, MR chart for individual data points. We cannot use the control limits from Xbar charts for averages, we would have to calculate the spread of the individual values separately....

we still should still assess stability using a (appropriate) control chart.
True. Though one could take X-bar Range charts and convert to what would be the individual standard deviation.
Thanks to Steve Prevette for your informative Post and/or Attachment!
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Calculation of the Mean - Student Question about Cpk calculation jal8712 Capability, Accuracy and Stability - Processes, Machines, etc. 6 23rd June 2012 06:58 AM
Uncertainty Calculation in Excel - Please review my calculation ghosh1975 General Measurement Device and Calibration Topics 2 26th August 2010 01:18 AM
Tier II Automotive Paint Shop - questions questions questions mothergoose IATF 16949 - Automotive Quality Systems Standard 9 6th February 2009 10:49 AM
Failures-in-time (FITs), DPPM and Probability Calculation Questions johnb1 Reliability Analysis - Predictions, Testing and Standards 9 5th June 2008 12:34 PM
Internal Audit Questions - Does anyone have sample questions for Management QHSEer Internal Auditing 16 6th December 2007 07:21 AM