The difference between Feasibility Assessment and Contract Review

Rudy84

Registered
Please, could someone explain to me the difference between feasibility assessment and contract review?
In which phase i should carry out the first and in which the second?

thank you in advance :bigwave:
 

Sidney Vianna

Post Responsibly
Leader
Admin
Re: Feasibility VS Contract Review

Typically, a feasibility assessment happens very early in the process, to ascertain that a product/service can deliver some performance expectations.

Only after a feasibility assessment confirms the possibility of performance being achievable, a contract negotiation would ensue.
 

normzone

Trusted Information Resource
Re: Feasibility VS Contract Review

And contract review is either part of negotiations, or it's own step after the purchase order arrives and you check to see what kinds of land mines the customer slipped in.
 