FAA 8130-21G Airworthiness Approval Tag Form - New Changes?

C

Corsair

Anyone is aware for the changes on the latest 8130-21G Airworthiness Approval Tag Form?

:thanx:
 
F

Frank T.

FAA Order 8130-21G was released 10/26/2009 and can be viewed/downloaded from the FAA website

This order (8130-21G) is effective on 4/14/2010.

The policy changes per paragraph 1-5 are as follows: This revision -

a. Reflects changes and updates appropriate references following publication of Production and Airworthiness Approvals, Part marking, and Miscellaneous Amendments; Final Rule in the Federal Register under docket number FAA-2006-25877.

b. Replaces parts and appliances with the term “article.” (Article – Means a material, part, component, process, or appliance)

c. Removes references to classes of products.

d. Deletes the term “newly overhauled” and associated guidelines from the description of work performed.

e. Revises acceptable methods for enabling traceability of FAA Form 8130-3 by permitting use of Block 3 of the form in combination with other information on the form.

f. Removes language pertaining to distributors that are accredited in accordance with Advisory Circular (AC) 00-56, Voluntary Industry Distributor Accreditation Program.

g. Combines and moves information on computer-generated forms, information systems, and automation to a new paragraph 1-9.

h. In Chapter 3, permits use of either the term “Inspected” or “Tested” in Block 12 rather than requiring that both terms be entered together.

i. Adds a requirement in Chapter 4 that for exported aircraft engines or propellers, the exporter include total time and if applicable, time since overhauled.
 
Last edited by a moderator:
C

Corsair

We are involve in PMA replacement parts,I guess we have to get familiar on this one.

:thanx:
 
A

andygr

Here is information from AIR 200
http://www.faa.gov/aircraft/air_cert/production_approvals/14cfr_amendments/resources_part21/
While the order is out the time line has some elements ( especialy with PMA) not being able to come into effect untill next April
Look at the PDF labled "part 21 publications fact sheet" for the dates

They are on a traveling road show giving a 3-4 hr presentation in various locations. Give your PI a call to see when they might be in a town near you:lol:
http://www.faa.gov/aircraft/air_cert/production_approvals/
 
C

Corsair

Thank you all,if I not mistaken there are also some changes on form 8130-3.

Correct?

:thanx:
 
Q

quality24

Not that I am aware of. Rev F made some changes "Eligibility" not on Tag any longer.
 