Changes to Control Plans or PFMEA's (Process FMEA)

Monitor the Elsmar Forum
Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

AIAG - Automotive Industry Action Group

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
control plans, fmea - failure modes and effects analysis, process fmea
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 18th June 2010, 01:42 PM
5litre

 
 
Total Posts: 5
Please Help! Changes to Control Plans or PFMEA's (Process FMEA)

Is it necesaary for Document Control to keep a record of updates to Control Plans or PFMEA's, or just necessary to up the revision level (date) and issue the new one?

The standard states that you must control documents, but this would be data within the document.

I have not been keeping a Change Record for each part number that gets revised, is this an N/C?

Sponsored Links
  Post Number #2  
Old 18th June 2010, 01:49 PM
Stijloor's Avatar
Stijloor

 
 
Total Posts: 15,334
Re: Changes to CP or PFMEA's

Quote:
In Reply to Parent Post by 5litre View Post

Is it necesaary for Document Control to keep a record of updates to Control Plans or PFMEA's, or just necessary to up the revision level (date) and issue the new one?

The standard states that you must control documents, but this would be data within the document.

I have not been keeping a Change Record for each part number that gets revised, is this an N/C?
This may help:

The AIAG PPAP Manual, Section 6, Page 21 states:

Quote:
<snip> The organization shall ensure that the appropriate PPAP records from a superseded part PPAP file are included, or referenced in the new part PPAP file.
Stijloor.
  Post Number #3  
Old 18th June 2010, 02:04 PM
5litre

 
 
Total Posts: 5
Re: Changes to CP or PFMEA's

My question would be for rev. changes to a specific part number, not really for a superseded number. We do keep a Document Change Log for changes to documents we use that get revised from time to time.

Thanks
  Post Number #4  
Old 18th June 2010, 02:06 PM
bpritts

 
 
Total Posts: 247
Re: Changes to CP or PFMEA's

I have included control plans in the scope of document control in all of my clients' systems. I suppose you could argue that the changes to the content represent changes to data rather than a document, but data changes must be controlled, too.

Remember the goals of document control and decide for yourself. Documents and/or data which are relied on for product design, manufacturing, inspection or service must be controlled, to ensure that changes are made in an authorized manner, and current information available to all who need it.

Possibly you could use the signatures and dates on the form as evidence of approval, but as noted above you'll also need to ensure that records of implementation and change must be kept, too.

Best regards............Brad
  Post Number #5  
Old 19th June 2010, 10:39 AM
ARTEMIS

 
 
Total Posts: 26
Re: Changes to Control Plans or PFMEA's (Process FMEA)

I agree,

If you make any changes to an document that affect the way you perform a tasks in the course of your business that change needs to be controlled.
  Post Number #6  
Old 19th June 2010, 10:56 AM
jerry_Malaysia's Avatar
jerry_Malaysia

 
 
Total Posts: 96
Re: Changes to Control Plans or PFMEA's (Process FMEA)

In the place that I work, we control the changes of control plan and FMEA according to document control procedure. We have recorded what are the reason for each change, and attach supporting documents example validation, testing and trial result etc. This is because we need to keep track on why we made the changes and how we made the changes. We may use FMEA as benchmark for similar product development in future, therefore, we would like to have as much information as possible.
  Post Number #7  
Old 19th June 2010, 03:44 PM
jkuil's Avatar
jkuil

 
 
Total Posts: 247
Re: Changes to Control Plans or PFMEA's (Process FMEA)

Critical is the document change control of any specification
  • specification of the product
  • specification of how it is being manufactured
  • specification of the controls and inspections that ensure product quality
A change record should specify the changes and how they are controlled: the validation of the change and the impact on the risk assessment. It may be necessary to update FMEA's and control plans due to the change. Your change control form should assess and record this need.
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
How to develop a Control Plan from a PFMEA (Process FMEA) Kales Veggie FMEA and Control Plans 43 16th April 2018 04:55 AM
PFMEA (Process FMEA) Forms - Dyadem FMEA Software Products LUV-d-4UM FMEA and Control Plans 5 19th November 2010 03:11 PM
Software which links Process FMEA (PFMEA), Control Plan and Flow Chart Jose Luis de la Cruz - 2005 Quality Assurance and Compliance Software Tools / Solutions 9 25th June 2010 12:07 PM
The real Link between a PFMEA (Process FMEA) and the Control Plan jshipley FMEA and Control Plans 19 5th March 2008 08:29 AM
Connections between PFMEA (Process FMEA) and the Control Plan. michu FMEA and Control Plans 20 26th March 2007 12:28 PM