Would someone please clarify for me. I am being told by a customer that On the Job Training, Ample Supply at Station" and Supervisor Verification are not acceptable for Current Design/Controls Prevention. This is for a tack weld step.
Tack Weld, Setup Machine, Setup Incorrect, Nonconforming Part, Inadequate Training, OJT, Measurement
This is the example for OJT that they don't like
Please forgive me if I missed something or could have place this elsewhere. I'm in a big hurry for any feedback.
Cordially,
David Schneider
QE for Outside Contracts
Tack Weld, Setup Machine, Setup Incorrect, Nonconforming Part, Inadequate Training, OJT, Measurement
This is the example for OJT that they don't like
Please forgive me if I missed something or could have place this elsewhere. I'm in a big hurry for any feedback.
Cordially,
David Schneider
QE for Outside Contracts