SOP or Work Instruction for PFMEA?

Monitor the Elsmar Forum
Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

AIAG - Automotive Industry Action Group

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
pfmea (process fmea), sop (standard operating procedure), work instructions (wi)
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 22nd April 2015, 01:45 PM
gjkoenig

 
 
Total Posts: 8
Question SOP or Work Instruction for PFMEA?

Hello,

We were recently audited by a new customer and were cited for not having a procedure for PFMEAs. We are a TS16949 company and generate PFMEAs during the Contract Review and include them in our PPAPs per AIAG. There is no separate procedure (SOP/WI) on PFMEA but the PFMEA Form is referenced in some of our existing SOPs. How is the PFMEA Process normally invoked/controlled in an organization? Do we need to create a separate SOP or Work Instruction in order to spell out the details from inception to monitoring or is it enough to just reference our PFMEA Form in the existing SOPs? I really do not want to create another "Procedure" if we are already covered somewhere else.

The SQE auditor also mentioned that because of having no procedure, we do not have clearly identified RPN numbers for each process that would trigger an action (corrective action). As a newbie to PFMEA, I was under the impression that it is not advisable to use threshold numbers but rather evaluate the process risks individually.

I would appreciate any comments.

gjkoenig

Sponsored Links
  Post Number #2  
Old 22nd April 2015, 01:49 PM
Stijloor's Avatar
Stijloor

 
 
Total Posts: 15,334
Re: SOP or Work Instruction for PFMEA?

Quote:
In Reply to Parent Post by gjkoenig View Post

Hello,

We were recently audited by a new customer and were cited for not having a procedure for PFMEAs. We are a TS16949 company and generate PFMEAs during the Contract Review and include them in our PPAPs per AIAG. There is no separate procedure (SOP/WI) on PFMEA but the PFMEA Form is referenced in some of our existing SOPs. How is the PFMEA Process normally invoked/controlled in an organization? Do we need to create a separate SOP or Work Instruction in order to spell out the details from inception to monitoring or is it enough to just reference our PFMEA Form in the existing SOPs? I really do not want to create another "Procedure" if we are already covered somewhere else.

The SQE auditor also mentioned that because of having no procedure, we do not have clearly identified RPN numbers for each process that would trigger an action (corrective action). As a newbie to PFMEA, I was under the impression that it is not advisable to use threshold numbers but rather evaluate the process risks individually.

I would appreciate any comments.

gjkoenig
This auditor is totally off-base! There is no requirement for an FMEA procedure. In addition, RPN's should not be used to trigger (or prioritize) the need for action.
Thank You to Stijloor for your informative Post and/or Attachment!
  Post Number #3  
Old 22nd April 2015, 03:14 PM
Golfman25

 
 
Total Posts: 1,463
Re: SOP or Work Instruction for PFMEA?

The auditor is out of his mind. Like you, we handle it in contract review - where we basically indicate what documents we create. I suppose our "procedure" is that blue FMEA book. Cause that is what we refer to when we do them. IMO, the whole RPN thing has become a joke perpetuated by simpletons.

However, since it is a customer audit, I guess you are in trouble. Unless you can talk some sense to the guy, you'll have to come up with a "fix." Good luck.
Thank You to Golfman25 for your informative Post and/or Attachment!
  Post Number #4  
Old 23rd April 2015, 07:33 AM
gjkoenig

 
 
Total Posts: 8
Re: SOP or Work Instruction for PFMEA?

Thanks for the response. I don't know if it matters, but the customer audit was VDA 6.3 Process Audit. The auditor was reviewing a PFMEA included in a PPAP for one of their parts and asked for the PFMEA Plan that controls the RPN numbers. As a newbie, I was tongue-tied as we have no procedure but our PFMEA Form and risk numbers model the AIAG format.

I am becoming a little more comfortable defending our current PFMEA process in that I do not want to create a separate "procedure" but rather take note of where PFMEA is referenced in our other established SOPs.

gjkoenig
  Post Number #5  
Old 23rd April 2015, 11:01 AM
Ron Rompen's Avatar
Ron Rompen

 
 
Total Posts: 571
Re: SOP or Work Instruction for PFMEA?

VDA 6.3 is different than TS 16949, so that may explain some (not all) of his comments. In my past experience, I have always referenced the PFMEA in my APQP procedure/process map as one of the outputs. If you state clearly in your procedure that the AIAG manual is used as the guideline for PFMEA development and maintenance, that should cover it.

As far as using RPN's to trigger actions, there are still many out there who look for a threshold number - this goes against the intent of risk analysis; you need to analyze your HIGHEST risk(s) and take appropriate action, whether they exceed an arbitrary number or not. Again, if you clearly note this in your procedure, you should be covered.
  Post Number #6  
Old 26th July 2017, 02:12 PM
flagman

 
 
Total Posts: 1
Quid Pro Quo Re: SOP or Work Instruction for PFMEA?

IMHO, a procedure, aka documented information , should be used to define the responsibilities (who completes the PFMEA), Authorities (who authorizes/approves the PFMEA), to define use of symbols (e.g. do you use customer symbols for critical characteristics, or your own, do your symbols "equate" to the customer's symbols via a translation table), to clarify you do not take action on the highest RPN - but rather on the highest ___, frequency of review, and so forth.

As there are other considerations for inclusion in a Procedure, you may want to write a Procedure for APQP and cover all the requirements in one document... You "might" include the sequence of work (Contract Review > PFD > FMEA > MSA > Ctrl Pln > ...), how Change Management flows back into the FMEA, and the flow of subcontractor assessment and PPAP into your own flow.


-wizuurd
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Standard work, standardized work instruction & work instruction: What are differences morteza IATF 16949 - Automotive Quality Systems Standard 7 29th June 2017 09:26 AM
Process Flow Chart is a Work Procedure or a Work Guide, or a Work Instruction jm1231 Document Control Systems, Procedures, Forms and Templates 28 9th March 2012 12:52 AM
AS9100C Work Instruction Clarification - How detailed should a Work Instruction be? tqual AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 10 12th February 2012 07:48 AM
Humorous work instruction - Relief Station Work Instruction Crusader Funny Stuff - Jokes and Humour 6 28th October 2008 04:53 PM
Work Instruction - TS 16949 - Is work instruction for packing and delivery mandatory sathis IATF 16949 - Automotive Quality Systems Standard 6 31st August 2005 01:24 AM



The time now is 10:17 AM. All times are GMT -4.
Your time zone can be changed in your UserCP --> Options.



Misc. Internal Links


NOTE: This forum uses "Cookies"