What is supposed to happen when a CA cannot be closed out or the root cause...
UL - Underwriters Laboratories - Health Sciences
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
What is supposed to happen when a CA cannot be closed out or the root cause...
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > > >
Forum Username

Elsmar Cove Forum Visitor Notice(s)

Wooden Line

What is supposed to happen when a CA cannot be closed out or the root cause...


Elsmar XML RSS Feed
Elsmar Cove Forum RSS Feed

Monitor the Elsmar Forum
Sponsor Links




Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
corrective action (ca), customer complaints and customer found nonconformance
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 10th August 2017, 06:01 PM
kbishop94

 
 
Total Posts: 1
Lightbulb What is supposed to happen when a CA cannot be closed out or the root cause...

determined?
Example:

Customer Complaint: Contamination is found in the product we provide to them. (chemical, liquid petroleum based, processed and shipped out of our facility in 55g drums)

Investigation phase: It was determined and agreed upon by all parties (this was a lengthy RCA process involving multiple parties including (1) our organization (2) supplier of drums (3) customer and (4) supplier of raw the material.
During this investigation it is determined by all (and agreed upon) that the most likely source of contamination was coming from the drums. Chemical analysis of the contamination was also performed and backed up the theory that the source was indeed the drums.

Corrective Actions: Corrective actions were put in place to (1) check the drums, (2) clean the drums out (if necessary) and (3) filter the product before being transferred to the drums (as a precaution.)

Implementation: Revisions to SOPs and Work INstructions are made and implemented and process is audited to verify the effectiveness of the changes made. All is good.
Then, the contamination is back. Furthermore, it is revealed that it was probably there all along but it was just smaller particles that they prior observed. So what actions do we ,\should we, take from here? Re-open that CAR, or issue a new one? What if its revealed that the contamination has always been there and the customer just did not have the necessary equipment in place to find it? Could the CAR be redacted in this case?

Thanks for all suggestions and opinions here folks!!

Sponsored Links
  Post Number #2  
Old 10th August 2017, 08:52 PM
Big Jim

 
 
Total Posts: 2,764
Re: What is supposed to happen when a CA cannot be closed out or the root cause...

I would open a new one and reference the old one.

Sometimes even with due diligence problems are not resolved on the first go around. You now have another opportunity to resolve it. That doesn't mean that you didn't learn from the effort so far. At minimum you have learned that what was already done either wasn't right or wasn't sufficient.

When a problem repeats, there is ALWAYS something about it that can help with the resolution. The circumstances were different. The conditions were different. Someone else observed it. Etc.

When you have a repeat it may be necessary to bring more resources to the resolution. Keep an open mind and brainstorm with the best individuals in the collective organizations.

In this case, having been through something like this, I suspect that the drum supplier is still having trouble with his coating process. That said, keep an open mind and see what turns up this time around.

The smaller particles could also be due to your own filtering process. You might see if the particles are smaller than your filter mesh and check the filters to see if they caught anything.

Run with what you have learned that is different and keep an open mind about other possibilities.
Thanks to Big Jim for your informative Post and/or Attachment!
Sponsored Links

Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
The days before International Standards - Has ISO done what it was supposed to? statdoug ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7 5th February 2013 07:51 PM
Is the first piece inspection method supposed to be in the Control Plan? Pudge Inspection, Prints (Drawings), Testing, Sampling and Related Topics 18 10th October 2012 01:07 AM
GM's RED X - Supposed to be a simple tool to find Root Cause erica 2005 Problem Solving, Root Cause Fault and Failure Analysis 23 10th March 2012 07:56 AM
AS9102 FAI - What is a distributor of ball bearings supposed to do? The Almighty Bearing AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 2 3rd February 2012 02:33 PM
Who are supposed to be the auditees/auditors in a small organization? cmfugen ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9 1st April 2008 02:43 PM