ROSEMUND J.
There are few requirements under 4.17.1, where:
1. the internal audit should cover all shift
2. Audit schedule updated annually, and
3. When internal/external nonconformance or customer complaints occur, the planned audit
frequency should be increased.
Please see below situation:
1) I believe this is only applicable to manufacturing related elements, such as 4.9,
4.12...etc. In my factory, I have QA specialist/operators doing shiftly audit focusing on product and process conformances. I also have interbal quality system auditor (trained and certified by consultants) focusing on systemic issue. Is this meet the intent?
2. What does it mean "updated annualy? My consultant told me, there should be a planned audit schedule and the schedule can only be changed annually. I have to follow the schedule consistantly without fail except there is special event. This is not feasible as a lot of activities, customer visit/audit, corperate audit..etc happening. We have to change the schedule to maximize our resources. Could anyone give me some suggestion, comment?
3. I do not know how to meet this. I believe every company has internal/external
non-conformance, if everytime we need to increase the frequency, I will be in trouble. Please advice.
Thanks.
1. the internal audit should cover all shift
2. Audit schedule updated annually, and
3. When internal/external nonconformance or customer complaints occur, the planned audit
frequency should be increased.
Please see below situation:
1) I believe this is only applicable to manufacturing related elements, such as 4.9,
4.12...etc. In my factory, I have QA specialist/operators doing shiftly audit focusing on product and process conformances. I also have interbal quality system auditor (trained and certified by consultants) focusing on systemic issue. Is this meet the intent?
2. What does it mean "updated annualy? My consultant told me, there should be a planned audit schedule and the schedule can only be changed annually. I have to follow the schedule consistantly without fail except there is special event. This is not feasible as a lot of activities, customer visit/audit, corperate audit..etc happening. We have to change the schedule to maximize our resources. Could anyone give me some suggestion, comment?
3. I do not know how to meet this. I believe every company has internal/external
non-conformance, if everytime we need to increase the frequency, I will be in trouble. Please advice.
Thanks.