I am implementing the CQI-23 Special process molding and a doubt came up:

In some requirements appears N/A for type of control , but in the monitoring requirement colun appears the requirement

For instance.
In the Process Table A question A6.7(plastification- melttemperature) the type of control is N/A , but in the monitoring frequency appears start-up as minimum requirement.

How can I understand this??

I don't need a control but i have to check the status of melt temperature??


Thanks for any help!!!
 

Jeff Putman

Starting to get Involved
CQI-23 is certainly not one of the best of the AIAG forms. I handle it like this:
No control is required for A6.7, but if you have a control in place you are required to perform it at start-up. If you have no control N/A would be in both boxes.
 

bobdoering

Stop X-bar/R Madness!!
Trusted Information Resource
Perhaps they are thinking of verifying settings (heaters, etc.), but not necessarily statistical process control, etc. I have not read the whole document, but that may still be their thinking.
 
H

Hilario Anaya

You may have a thermometer or thermocouple for measuring, but not a closed loop control system for controlling it.
 

Poopsy1084

Registered
I was just asked for a CQI-23 today. I was never asked for one before and totally not prepared. Does anybody have a editable version of it I can use? I looked in the post attachments and was unsuccessful.
 