I had a question regarding what is required of scheduling as far as AS9100. I am creating a process matrix with AS9100 clauses to link each process but I am having trouble covering scheduling which is located within the production process.
For example, IATF16949 8.5.1.7 states:
"The organization shall ensure that production is scheduled in order to meet customer orders/demands such as Just-In-Time (JIT) and is supported by an information system that permits access to production at key stages of the process and is order driven."
Is this mentioned in AS9100D in some way that I may have overlooked while reading it?
For example, IATF16949 8.5.1.7 states:
"The organization shall ensure that production is scheduled in order to meet customer orders/demands such as Just-In-Time (JIT) and is supported by an information system that permits access to production at key stages of the process and is order driven."
Is this mentioned in AS9100D in some way that I may have overlooked while reading it?