The Cove Business Standards Discussion Forums More Free Files Forum Discussion Thread Post Attachments Listing Cove Discussion Forums Main Page
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
UL - Underwriters Laboratories - Health Sciences
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >
Forum Username

Elsmar Cove Forum Visitor Notice(s)

Wooden Line

ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)


Elsmar XML RSS Feed
Elsmar Cove Forum RSS Feed

Monitor the Elsmar Forum
Sponsor Links




Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
iso 9001:2015, risk management and analysis
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 8th September 2017, 12:34 PM
QAMTY

 
 
Total Posts: 476
Thank You! ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Hi everybody

In the task of addressing risks, I have the next doubt, could you clarify it?

NOTE 1 Options to address risks can include avoiding risk, taking risk in order to pursue an opportunity, eliminating the risk source, changing the likelihood or consequences, sharing the risk, or retaining risk by informed decision.

In 6.1.2, Note 1, taking risk in order to pursue an opportunity is not the same as retaining risk by informed decision?

Thanks

Sponsored Links
  Post Number #2  
Old 10th September 2017, 04:01 PM
dsanabria

 
 
Total Posts: 1,175
Re: ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Can you rephrase your concern or question?

It looks like you are mixing process risks with venture risks - two different subjects.
Sponsored Links

  Post Number #3  
Old 17th September 2017, 11:55 PM
QAMTY

 
 
Total Posts: 476
Re: ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Thanks Dsanabria

Well, the doubt really it is, what it means "by informed decision?
and the other question is:

In any possible decisions, do all of them will need a mitigation plan?

I mean, mitigation means to lower the risk value? but in the case of avoiding it,
it is like risk wont be taken, is it a mitigation too?
Please explain how to apply mitigation considering note 1?
NOTE 1 Options to address risks can include avoiding risk, taking risk in order to pursue an opportunity, eliminating the risk source, changing the likelihood or consequences, sharing the risk, or retaining risk by informed decision.
Thanks
  Post Number #4  
Old 18th September 2017, 12:17 AM
Marc's Avatar
Marc

 
 
Total Posts: 25,940
Re: ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Quote:
In Reply to Parent Post by QAMTY View Post

<snip> what it means "by informed decision?
and the other question is:

In any possible decisions, do all of them will need a mitigation plan? <snip>
1. Informed decision: Someone who is knowledgable in the discipline(s) has at least thought about, and possibly documented, potential issues. The key word is "informed" (aka qualified to do so).

2. This has been discussed here many times. Recently it was discussed with respect to disaster plans. A company can never have a mitigation plan for every potential disaster.

Also see: Mitigation Plan - Bing Search
and Risk Based Thinking - Chennaiite's Blog
and Records Destroyed - Hurricane Harvey has likely destroyed our Quality Systems Records
Thanks to Marc for your informative Post and/or Attachment!
  Post Number #5  
Old 18th September 2017, 09:50 AM
QAMTY

 
 
Total Posts: 476
Re: ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Thanks Mark for your clarification

As you say "Someone who is knowledgable", but in these cases:
changing the likelihood or consequences, sharing the risk, or retaining risk by informed decision, I think in all of them, always participate knowledgable people, then, why the standard only mention this in "retaining"?
Thanks
  Post Number #6  
Old 18th September 2017, 10:38 AM
QAMTY

 
 
Total Posts: 476
Re: ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Marc

According to the link you shared, "Chennaiite's Blog" from into it,I copied a portion of it,

"thereby sharing your Risk of missing the flight with the Driver; The Driver keeps informed of his Employer about the Risk of losing taxi charge and the Employer decides to bear it on a good-will; You start-off from the place after ten minutes when the Driver is back;

From this, it seems that Informed decisions, meant agreements with someone to do something
What do you think?

Thanks
  Post Number #7  
Old 18th September 2017, 11:01 AM
Marc's Avatar
Marc

 
 
Total Posts: 25,940
Re: ISO 9001:2015 - Clarification in 6.1.2 Note 1 (Options to Address Risks)

Well, how about:

1. Informed decision: Someone who is knowledgable in the discipline(s) has at least thought about, and possibly documented, potential issues. The key word is "informed" (aka qualified to do so and is aware of related facts and information).

Someone else here may be able to give you a clearer definition.
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Values - ISO 9001 2015 - Clause 4.1 Note 3 QAMTY ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4 4th May 2017 12:30 AM
Source of practice to Evaluate Risks? (ISO 9001:2015) QAMTY ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1 7th April 2017 07:37 AM
Actions To Address Risks and Opportunities Rich Shippy IATF 16949 - Automotive Quality Systems Standard 1 13th February 2017 03:59 PM
Clarification of ISO 9001:2015 Clause 8.5.6 Control of Changes btu32s ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2 31st October 2016 12:01 PM
Confusion about Risks for Processes in ISO 9001:2015 armani ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 41 30th August 2016 12:03 PM