orion1
Hello,
I have question regarding takt time calculation for long runner product.
I want to calculate the takt time for specific product A that makes 60 % of entire products in terms of production units.
Takt time = Available time (Product A) / Customer Demand (Product A).
Total available time per shift = 480 min - 30 min per break= 450 min.
The question is what available time should be taken for calculation of takt time of product A?
Thank you
Orion