API Q1 5.6.1.2 - Initial Supplier Evaluation

Monitor the Elsmar Forum
Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

AIAG - Automotive Industry Action Group

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
api q1 - oil industry quality management system (qms), supplier evaluation/rating/approval
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 18th June 2014, 09:23 PM
Aussie99

 
 
Total Posts: 35
Please Help! API Q1 5.6.1.2 - Initial Supplier Evaluation

Hi,
API Q1 5.6.1.2 states:

"For purchase of critical products, components or activities, the criteria for the initial evaluation of suppliers by the organisation shall be site specific for each supplier and shall include the following:

(a) Verification that the supplier's quality management system conforms to the quality system requirements specified for suppliers by the organisation"

Can someone give me a couple of examples of what sort of quality system requirements we should be be specifying, or is it the norm to just say they must hold ISO 9001 or API Q1 for example.

A recent audit raised shortcomings in this area for us and I'm trying to find a realistic solution. Our auditor says it's not enough to just witness a certificate to show compliance with a quality management system spec............we actually have to verify their system. Does this mean an on site audit, or would a questionnaire suffice. (confident in the knowledge that the janitor could tick and flick any questionnaire).

We are a small company in a remote location, 3000kms plus from our critical suppliers, (and potential future suppliers). Our critical purchases are very minimal. Suppliers are certainly not going to bend over backwards to assist us when the value of our business to them is so small.

Any thoughts?

Sponsored Links
  Post Number #2  
Old 18th June 2014, 09:50 PM
lokeky1

 
 
Total Posts: 38
Re: Initial Supplier Evaluation

Hi Ausie99

When site audit is not cost effective, I use a combination of questionaire, relevant certificates for quality systems and product, email, website search and phone interview. I also provide history of supply and product quality.

I get as much information as I can about the Company, Quality System and the product until I am convinced and satisfied. Finally I write a report to say the reason I approve the supplier. I will also mentioned that this was a desktop audit.

Another way to justify the type of audits (site or desktop) is using risk assessment.


Hope this helps.

Loke
Thank You to lokeky1 for your informative Post and/or Attachment!
  Post Number #3  
Old 18th June 2014, 11:42 PM
Aussie99

 
 
Total Posts: 35
Re: Initial Supplier Evaluation

Thanks Lokeky,
I like your approach. We do have questionnaires we have sent out in the past, so I will brush them up a bit and utilise some of your other suggestions. Hopefully API will see it as being acceptable.

The suppliers we currently use for critical products are firmly entrenched and been in the system for many years, and as I stated previously, we are talking very minimal items. So it's not a process I'm likely to go through in the near future. Nonetheless, the process and associated documents need to be in place to satisfy the requirements of Q1.

Thanks for you help here.

Aussie
  Post Number #4  
Old 19th June 2014, 09:52 AM
bluepagen

 
 
Total Posts: 81
Re: Initial Supplier Evaluation

Hi Aussie99, we use questionnaires also, but require at a minimum that critical suppliers have a quality manual and a method in place to take actions whe NCR's or Trends are identified, and, an onsite assessment to ensure iit capability to meet purchasing requirements, or first article inspection to ensure confromance to stated requirments, or identifying how the supplied product conforms to stated requirements.

Hope this helps.
Thanks to bluepagen for your informative Post and/or Attachment!
  Post Number #5  
Old 19th June 2014, 08:41 PM
Aussie99

 
 
Total Posts: 35
Re: Initial Supplier Evaluation

Quote:
In Reply to Parent Post by bluepagen View Post

Hi Aussie99, we use questionnaires also, but require at a minimum that critical suppliers have a quality manual and a method in place to take actions whe NCR's or Trends are identified, and, an onsite assessment to ensure iit capability to meet purchasing requirements, or first article inspection to ensure confromance to stated requirments, or identifying how the supplied product conforms to stated requirements.

Hope this helps.
Thanks Bluepagen....................onsite assessments for us are out of the picture due to our location.

First article inspection is the major form of evaluation and re-evaluation for us. Big change in Q1 9th edition relative to suppliers of critical purchases is clause 5.6.1.2 where initial supplier evaluation must include both items (a) AND (b), as opposed to re-evaluation, (clause 5.6.1.3), where the "AND" is replaced by "OR" .
This is where I fell down................
  Post Number #6  
Old 26th June 2014, 01:35 AM
radica

 
 
Total Posts: 12
Re: API Q1 5.6.1.2 - Initial Supplier Evaluation

Please, what is meant by the "initial evaluation"? Does the initial evaluation is performed only at the beginning of cooperation with the supplier or refers to a periodic evaluation for example. once per a year? And if so what is the difference between the periodic evaluation and re-evaluation?
  Post Number #7  
Old 26th June 2014, 01:53 AM
Aussie99

 
 
Total Posts: 35
Re: API Q1 5.6.1.2 - Initial Supplier Evaluation

Quote:
In Reply to Parent Post by radica View Post

Please, what is meant by the "initial evaluation"? Does the initial evaluation is performed only at the beginning of cooperation with the supplier or refers to a periodic evaluation for example. once per a year? And if so what is the difference between the periodic evaluation and re-evaluation?
Hi Radica...........it is exactly as you describe.............initial evaluation is performed prior to the "beginning of cooperation" with a supplier. Periodic evaluations would be referred to as re-evaluations. Note that for "critical purchases" your initial valuation of a supplier contains an extra requirement (item (a) of clause 5.6.1.2) when compared to non-critical purchases, (clause 5.6.1.3).
  Post Number #8  
Old 28th January 2015, 04:09 AM
Suz10

 
 
Total Posts: n/a
Re: API Q1 5.6.1.2 - Initial Supplier Evaluation

Hi All,
I have difficulties on b) item iii - identifying how the supplied product conforms to stated requirements when limited by proprietary, legal and/or contractual agreement. - how do we actually practice this?
Thanks in advance....
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
ISO 10993-1:2009 Sensitization (Initial Evaluation Test) vs. USP Institute Other Medical Device Related Standards 3 3rd November 2010 06:06 PM
Initial Supplier Evaluation Method - 7.4.1 Purchasing Process quality1 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3 5th August 2009 03:59 PM
Chrysler requirement of Initial Risk Evaluation BT1981 IATF 16949 - Automotive Quality Systems Standard 2 17th August 2007 05:34 PM
Why there is no initial evaluation in OHSAS 18001:1999? s_warin Occupational Health & Safety Management Standards 5 1st September 2002 12:05 PM
Subcontractor Evaluation - Require onsite visit after the initial audit? dhillsburg Misc. Quality Assurance and Business Systems Related Topics 5 20th March 2000 08:53 AM