The Cove Business Standards Discussion Forums
Process Validation - Production Line Transferring to a Different Facility
Please read this thread...
Software update
Process Validation - Production Line Transferring to a Different Facility
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > > >
Forum Username

Elsmar Cove Forum Visitor Notice(s)

Wooden Line

Process Validation - Production Line Transferring to a Different Facility

Monitor the Elsmar Forum
Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

AIAG - Automotive Industry Action Group

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
moving to another location or facility, process verification and validation, production line, validation (general)
Reply
 
Thread Tools Search this Thread Rating: Thread Rating: 1 votes, 5.00 average. Display Modes
  Post Number #1  
Old 16th February 2008, 02:46 PM
Keep Smiling's Avatar
Keep Smiling

 
 
Total Posts: 5
Please Help! Process Validation - Production Line Transferring to a Different Facility

Our west coast plant is coating a blade for medical end use. The line is transferring to the midwest, and the customer is asking for our plan to capture process validation. I am in aerospace, so the lingo is all new to me.

If the process is the same, and equipment is similar (but not the same pieces) which qualifications are applicable: IQ - Installation Qualification, OQ - Operation Qualification, & PQ - Process Qualification? Any examples of document formats?

All help is appreciated

Sponsored Links
  Post Number #2  
Old 16th February 2008, 09:53 PM
Ajit Basrur's Avatar
Ajit Basrur

 
 
Total Posts: 6,217
Re: Process Validation - Product Transfer to Different Facility

Quote:
In Reply to Parent Post by Keep Smiling View Post

Our west coast plant is coating a blade for medical end use. The line is transferring to the midwest, and the customer is asking for our plan to capture process validation. I am in aerospace, so the lingo is all new to me.

If the process is the same, and equipment is similar (but not the same pieces) which qualifications are applicable: IQ - Installation Qualification, OQ - Operation Qualification, & PQ - Process Qualification? Any examples of document formats?

All help is appreciated
Welcome to the Cove and yes, as suggested by you, I am smiling too

Let me give you the basic definitions of DQ, IQ, OQ and PQ and then that will be more clearer. The entire requirement becomes necessary because of one point that you have pointed out - similar but not same

The qualification and validation process is done to establish and provide
documentary evidence that:

The premises, the supporting utilities, the equipment and the processes have been designed in accordance with the requirements of GMP. This normally
constitutes Design Qualification or DQ.

The premises, supporting utilities and the equipment have been built and installed in compliance with their design specifications. This constitutes Installation Qualification or IQ.

The premises, supporting utilities and the equipment operate in accordance with their design specifications. This constitutes Operational Qualification or
OQ.

A specific process will consistently produce a product meeting its predetermined specifications and quality attributes. This constitutes Process Validation or PV. The term Performance Qualification or PQ may be used
also.

The next question is when to qualify and validate -

Any aspect of, including significant changes to, the premises, the facilities, the equipment or the processes, which may affect the quality of the product, directly or indirectly, should be qualified and validated.

In your case, since the entire line is being transferred, you would have to start right from the Installation Qualification to confirm if the installation is being done correctly in the first place.

Hope this clarifies.
Thanks to Ajit Basrur for your informative Post and/or Attachment!
  Post Number #3  
Old 17th February 2008, 06:18 PM
Bev D's Avatar
Bev D

 
 
Total Posts: 3,614
Re: Process Validation - Production Line Transferring to a Different Facility

quite simply: you should perfrom IQ, OQ and PQ. Of course you dont'tthink anything will be different or you wouldn't be asking. But we don't do validation because we think we will fail. We do it in case we missed something and might fail.

in the medical industry this typically isn't optional. Your Customer can very well also help you with the validation plans.
  Post Number #4  
Old 18th February 2008, 10:14 AM
Keep Smiling's Avatar
Keep Smiling

 
 
Total Posts: 5
Re: Process Validation - Product Transfer to Different Facility

Thanks for the information & definitions, that gives me a good start. Does the FDA have specific forms to complete for the IQ, OQ, & PQ; or do I need to establish them?
  Post Number #5  
Old 18th February 2008, 10:32 PM
Ajit Basrur's Avatar
Ajit Basrur

 
 
Total Posts: 6,217
BIG Smile Re: Process Validation - Product Transfer to Different Facility

Quote:
In Reply to Parent Post by Keep Smiling View Post

Thanks for the information & definitions, that gives me a good start. Does the FDA have specific forms to complete for the IQ, OQ, & PQ; or do I need to establish them?
No, FDA does not have specific forms and you have establish yourself.

I suggest you should have a procedure on these Qualifications and Validations with a template for IQ, OQ and PQ.

Good Luck
  Post Number #6  
Old 19th February 2008, 03:49 AM
Gert Sorensen's Avatar
Gert Sorensen

 
 
Total Posts: 1,278
Re: Process Validation - Production Line Transferring to a Different Facility

Aside from all the good advise above, here is some food for thought:

Is the process running smoothly now? Is it already validated?

Moving a machine or a production line can be a nightmare! Don't go into this with your eyes shut....

I have seen a machine being moved all of 100 feet - simple operation - and it took us 8 (eight!) months before it produced acceptable products again. We did not have the sufficient knowledge of the machine and of the surroundings.

Assuming the process is running smoothly: If I were you I would start by establishing every conceivable aspect of the surroundings as they are today.
How is the:
  • Humidity?
  • Pressure?
  • Temperature?
  • Lighting?
  • Current
  • Waterflow/pressure/temperature?
  • Other machines nearby? What do they do?
  • Does this change with the seasons?
etc. etc. etc.

When you have established everything you can think of relating to surroundings then move on to the machinery. Establish everything about it, you will need to know it.

Why will you need this? Because that when you set up your line somewhere else and it does not work then you will need to find the fault that is there somewhere, and knowing everything about the environment where it did work is a good first step to fault analysis.

It is also a good basis for your IQ. When you know what you need from the surroundings then you simply test as part of your IQ to make sure that it is allright.
Thank You to Gert Sorensen for your informative Post and/or Attachment!
  Post Number #7  
Old 19th February 2008, 04:34 AM
chris1price

 
 
Total Posts: 258
Re: Process Validation - Production Line Transferring to a Different Facility

The GHTF document on process validation (SG3/N99-10) makes a good starting point for understanding medical device validation. http://www.ghtf.org/sg3/sg3-final.html
Thank You to chris1price for your informative Post and/or Attachment!
  Post Number #8  
Old 19th February 2008, 04:44 AM
Adam S

 
 
Total Posts: 19
Re: Process Validation - Production Line Transferring to a Different Facility

In my organisation, the starting point of any project is the Risk Assessment stage - it is here that the potential need for process validation will be raised.

Historically, we have been quite good at conducting effective validations - where we have been not so good is getting that Risk Assessment process live and "in the muscle" to use a nasty corporate term. Once RA is part of working life and business planning, you're much more likely to control your processes well
Thanks to Adam S for your informative Post and/or Attachment!
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
ISO 9001 clause that covers Production Line Re-Validation Qualitygoalieman Quality Manager and Management Related Issues 10 20th August 2012 03:25 PM
Correlation Production Time Study on a Process on an Assembly Line mechboy Manufacturing and Related Processes 3 29th July 2010 01:03 PM
Robots in a Production Line - Control Plan and Process FMEA puddlejumper Manufacturing and Related Processes 9 16th June 2010 08:28 AM
Line Leader Assessment form - Qualification process for production line leader rafe80 Training - Internal, External, Online and Distance Learning 1 10th March 2010 09:53 AM
Process Productivity - Identifying Strengths and weaknesses of a production facility PAT1L Quality Tools, Improvement and Analysis 3 29th August 2004 12:12 PM



The time now is 10:51 PM. All times are GMT -4.
Your time zone can be changed in your UserCP --> Options.



Misc. Internal Links


NOTE: This forum uses "Cookies"