Capacity Utilization - How to do a capacity utilization project

Monitor the Elsmar Forum
Courtesy Quick Links


Links Elsmar Cove visitors will find useful in the quest for knowledge and support:

Jennifer Kirley's
Conway Business Services


Howard's
International Quality Services


Marcelo Antunes'
SQR Consulting, and
Medical Devices Expert Forum


Bob Doering
Bob Doering's Blogs and,
Correct SPC - Precision Machining


Ajit Basrur
Claritas Consulting, LLC



International Standards Bodies - World Wide Standards Bodies

AIAG - Automotive Industry Action Group

ASQ - American Society for Quality

International Organization for Standardization - ISO Standards and Information

NIST's Engineering Statistics Handbook

IRCA - International Register of Certified Auditors

SAE - Society of Automotive Engineers

Quality Digest

IEST - Institute of Environmental Sciences and Technology


Some Related Topic Tags
capacity analysis, process capacity
Reply
 
Thread Tools Search this Thread Rate Thread Content Display Modes
  Post Number #1  
Old 7th March 2006, 01:02 PM
Andy_80

 
 
Total Posts: n/a
Please Help! Capacity Utilization - How to do a capacity utilization project

I work for an engineering services co and my team caters to GM. we are a tem of 12 people. Let me explain the process we do before asking anything.
We do the PPAP approval for GM NAVO from India. All the suppliers who are suppliy parts to GM get their currnet PPAP approved from us,it is on line. All the team members are divided based on the comodities like power train n exhaust, seats and wiring harness ect.....the amount of work load is not measured.sometimes its too high.
I want to do a capacity utilization project. I'm sure we have to hire more heads to do this work but I need to justify this to my management with numbers and statstics.
can we do this using the sixsigma tool or how do we go abot it.

Sponsored Links
  Post Number #2  
Old 7th March 2006, 03:52 PM
Bill Pflanz

 
 
Total Posts: 710
Quote:
In Reply to Parent Post by Andy_80

All the team members are divided based on the comodities like power train n exhaust, seats and wiring harness ect.....the amount of work load is not measured.sometimes its too high.
I want to do a capacity utilization project. I'm sure we have to hire more heads to do this work but I need to justify this to my management with numbers and statstics.
can we do this using the sixsigma tool or how do we go abot it.
A six sigma tool is not necessary. The real problem you have is that you freely admit "the amount of work load is not measured" even though you say it is "sometimes too high".

Before you start asking for more heads, you may want to start collecting some data on the number of requests received, the time it takes to process them, and various ratios on the time per request per employee. If not all requests take equal time to process than you may have to collect the data by commodities.

As you are collecting the data, you may also want to find out if some team members are over utilized while others have spare capacity. If so, then you could do some work sharing rather than hiring more people.

Bill Pflanz
  Post Number #3  
Old 4th June 2007, 05:24 PM
sspoldir

 
 
Total Posts: n/a
Re: Capacity Utilization - How to do a capacity utilization project

A bit late to the party but...

It sounds like your talking rough cut capacity planning, which is rather straight foward (again rough cut). How many parts/products/widgets can you produce in a given period of time (typically calculated per hour).

Then chart that out on a bar graph against the orders you have or the forecasted orders per week or month. If at any point those numbers go above the hours available then you have a capacity problem and need to "flatten" it out into another time period or find ways to raise the capacity level.
Reply

Lower Navigation Bar
Go Back   The Elsmar Cove Business Systems and Standards Discussion Forums > >

Bookmarks



Visitors Currently Viewing this Thread: 1 (0 Registered Visitors (Members) and 1 Unregistered Guest Visitors)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Forum Search
Display Modes Rate Thread Content
Rate Thread Content:

Forum Posting Settings
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Emoticons are On
[IMG] code is On
HTML code is Off


Similar Discussion Threads
Discussion Thread Title Thread Starter Forum Replies Last Post or Poll Vote
Design Capacity - What does 'Design Capacity' (or 'Rated Capacity') mean? samsung Definitions, Acronyms, Abbreviations and Interpretations 10 13th June 2012 01:36 PM
How to calculate utilization of ATM in this problem? monaali Lean in Manufacturing and Service Industries 4 2nd April 2010 12:09 PM
Utilization of new ERP system - (IFS- Industrial and Financial Systems) Tarrahb1 Quality Assurance and Compliance Software Tools / Solutions 8 16th June 2009 08:20 AM
Calculating Utilization % and On Time Delivery Yeong Lean in Manufacturing and Service Industries 6 11th August 2006 05:07 AM
Warehouse Space Utilization Spreadsheet Marla Diaz Document Control Systems, Procedures, Forms and Templates 5 26th September 2005 03:59 AM



The time now is 03:31 AM. All times are GMT -4.
Your time zone can be changed in your UserCP --> Options.



Misc. Internal Links


NOTE: This forum uses "Cookies"