Standard Pack:
1 standard pack = 1 container = 1 pull signal
1 days production = ( )
1 standard pack = 1 days production / 10
( ) = ( ) / 10
Maximum Inventory Level (Max):
Weekly average = 8 weeks inventory / 8
( ) = ( ) / 8
Days of inventory = weekly average / planned daily production
( ) = ( ) / ( )
Safety stock *s.s.) = additional inventory that must be added due
to current non-synchronized operations.
MAX = (days of inventory) X (daily planned production) + (s.s.)
( ) = ( ) X ( ) + ( )
Minimum inventory level (MIN):
(MIN) = batch size = red zone = replenishment
(MIN) = ( )
Number of Pull Signals in a Loop (nps)*:
(nps) = (MAX) / number of pieces in a standard pack
( )* = ( ) / ( )
Number of Pull Signals in a Red Zone (RZ)*:
(RZ) = (MIN) / pieces in a standard pack
( )* = ( ) / ( )
Number of Pull Signals in a Yellow Zone (YZ)*:
(YZ) = (nps) - (RZ) / 2
( )* = (( ) - ( )) / 2
Number of Pull Signals in a Green Zone (GZ)*:
(GZ) = (nps) - (RZ) - (YZ)
( ) = ( ) - ( ) - ( )
Designated Storage (dss):
(dss) = (nps) X (length) X (width) / number of containers high
( ) = ( ) X ( ) X ( ) / ( )
* Round up to the next highest number
/ Means divided by
X Means multiplied by
| Previous slide | Next slide | Back to first slide | View graphic version |