Hi Gentlemen..
I have a question regrading process sequence.
Most of the time I seen NDT calls after dimension inspection, But hear we may miss our identification tractability of parts.
Because in NDT we put parts in tray without tag.So it gets mixed up with each other.
So my question is, Can't we change sequence of operation like NDT & then dimension inspection.
Excepting your thoughts...