A mathematical measurable for document control

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#1
I had an interesting call today where a person was asked, during a TS 16949 registrar stage 1 audit, for a 'mathematical' measurable for document control. I've never been asked for that.

Your comments?
 
Elsmar Forum Sponsor

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#2
Line items (of what's targeted as important) could be measured singly by number or percentage of escapes. Outdated revisions found in use; number or percent of the time QA has rejected a revision during review due to missing appendices, etc, while no one else in the signature loop noticed; etc.

These lines are more actionable than a statistical score, but an overall score could be calculated by assigning each type of escape a value, multiplying that value by number of escapes, then totaling. (Like in golf, low scores are better or else process the number into percent)
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#3
Is this a standard TS 16949 requirement / auditor expectation? As I say, I've never been asked about a measureble for document control before.

Also - The company in question is only about 35 people with non-complex processes and stable documentation.
 

Sidney Vianna

Post Responsibly
Staff member
Admin
#4
I had an interesting call today where a person was asked, during a TS 16949 registrar stage 1 audit, for a 'mathematical' measurable for document control. I've never been asked for that.

Your comments?
Marc, I am no TS qualified auditor, but it sounds like the TS auditor doing this Stage 1 audit thinks that document control is a process (or the registrant company identified doc control as a process in their Quality Manual). Misidentified as a process, document control would have to be monitored, thus the question. This is just a wild guess.

Or it could be another case of "AUDITORS GONE WILD"
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#5
That's the way I interpreted it Sidney. From the conversation I suggested that there is a general 'communication' issue with the auditor (interpretation issue in this case in my opinion) precisely because of the auditor interpreting document control as a process. There was more to the conversation, which I won't go into here, but that is why I think it's a specific auditor issue. But - I wanted to ask because I thought maybe I'd missed something in TS 16949 interpretations somewhere.
 
C

Chavador

#6
Hello all,

Well let me tell you that in our system have defined “document control” as a process. We face the same problem to define a measurable objective, trying to find an objective that add an extra value to the system we thought that delivery time after approval was very essential so, the target for this process is to register an deliver the new document into 24 hour.

Now the objective has been modified and improved, the percentage of compliance is equal to: Requirement (to register, controlled copy, not controlled copy,) / service or document delivery * 100.

That’s it.


Salvador Gonzalez.
 
C

Chavador

#7
Sorry formula is wrong, I show you the right:

Number of services or Document deliveries / number of requisitions (to register, controlled copy, not controlled copy)*100


Salvador Gonzalez.
 
#8
I had an interesting call today where a person was asked, during a TS 16949 registrar stage 1 audit, for a 'mathematical' measurable for document control. I've never been asked for that.

Your comments?
Marc:
Years ago, in the early days of ISO 9001:2000, I did hear of one auditor asking for the document control procedure to be measured............unfortunately, he was one of my old buddies from way back when..........:rolleyes:

My guess is right up there with Sidney's, except for the possibility of a mis-quote over the need to measure the process of review, distribution and implementation of customer engineering specs (two business weeks, as you know).

Andy
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#9
My guess is right up there with Sidney's, except for the possibility of a mis-quote over the need to measure the process of review, distribution and implementation of customer engineering specs (two business weeks, as you know).
Yup, but key word is "mathematical".

I can understand Jennifer's reply in the context of a big company. But now we're getting into a gray area of whether document control is technically a process as defined by TS 16949.

Number of services or Document deliveries / number of requisitions (to register, controlled copy, not controlled copy)*100
How many controlled documents does your company have?
Do you do a monthly report?

Any further details you provide will be appreciated.
 

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#10
I'm in a big company and we don't do a monthly report.

I suspect it's a case of either auditors gone wild, or misunderstanding. I'm not aware of any such requirement.

However, a standard question is, (paraphrased) "How do you know if your process is going well or not?" It would actually be easy to figure out if there is a positive or negative trend of escapes. To show such a trend over time would be at least as much as such an auditor has the right to ask for.
 
Thread starter Similar threads Forum Replies Date
A Sample Size for Mathematical Model with acceptable Confidence Level Using Minitab Software 7
D Mathematical Model of Taguchi L18 Using Minitab Software 7
I Mathematical Probability Puzzle Brain Teasers and Puzzles 25
Marc NIST Handbook of Mathematical Functions reference text World News 0
P Mathematical probabilities (Sampling Inspection) Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
P Strictly mathematical viewpoint - What Makes 100%? Funny Stuff - Jokes and Humour 0
A Another mathematical riddle Brain Teasers and Puzzles 6
A Mathematical riddle Brain Teasers and Puzzles 4
A Mathematical difference between mean Deviation and Standard Deviation Statistical Analysis Tools, Techniques and SPC 3
N How can a mathematical model for value stream mapping can be developed Other ISO and International Standards and European Regulations 5
C Mathematical law relating profits and revenues, or costs and revenues? Misc. Quality Assurance and Business Systems Related Topics 2
T Mathematical model which represents the Gage R&R of an attribute defined product Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 4
T Can we remove a quality objective if we decide it is not measurable? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 11
S Process Measurable Objectives Imported Legacy Blogs 3
D Measurable objectives for our in-house calibration department General Measurement Device and Calibration Topics 6
G Management Review Non-Conformance - Meeting Measurable Goals and Objectives ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 14
P Do Quality Objectives have to be Measurable? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 57
Q Time Based, Measurable Mid-Year Performance Goals Quality Manager and Management Related Issues 3
C What is the smallest measurable tolerance? Measurement Uncertainty (MU) 4
N Measurable Targets and Objectives - Envelope Printing Company ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
D Setting a measurable target for a new service Statistical Analysis Tools, Techniques and SPC 6
Y Identifying measurable processes: How not to lose the forest behind the trees? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
V Departmental Measurable Objective Needs for AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
L Objectives: Measurable or having a tangible value? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
D Definition Measurable Goal vs. Relevant Goal vs. Realistic Goal - Definitions Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 10
somashekar Departmental Measurable Objectives Across All Company Functions ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 12
L Measurable Departmental objectives for the Management Representative (MR) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
S Samples of Measurable Business Objectives Misc. Quality Assurance and Business Systems Related Topics 10
A Measurable Quality Objectives of the Corporate Communication Department ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 11
W Quantifiable and Measurable Quality Goals? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
E Process Diagrams and Measurables - Do you HAVE to have a measurable? IATF 16949 - Automotive Quality Systems Standard 10
G ISO 9001:2000 Registration, but no process approach and no measurable objectives ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
D Top Management Quality Objectives - Setting objectives and Measurable goals ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
I Company and Departmental Measurable Goals - How many, by whom... ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
A Process Measurable - Ideal process measurable for a quality control department ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
M R&M Measurable. QS-9000 - American Automotive Manufacturers Standard 4
W Measurable Quality Objectives which can relate to Quality Policy - 5.4.1 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 13
E Determining and Defining Measurable Objectives in ISO 9001:2000 Clause 5 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 80
S QOS for Tooling and Equipment - Having difficulty selecting a measurable QS-9000 - American Automotive Manufacturers Standard 2
J Document Control Metrics Document Control Systems, Procedures, Forms and Templates 3
A Document Review and Document Approval --- 2 Signatures needed acc. §820.40? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 3
I Document Control Software Document Control Systems, Procedures, Forms and Templates 2
K 25-year lifetime of medical device - document storage period EU Medical Device Regulations 1
J UDI - Where to document it? EU Medical Device Regulations 8
T Controlling Expandable Forms in Paper-Based Document Control System Document Control Systems, Procedures, Forms and Templates 10
S Changing revision status of a reviewed document Manufacturing and Related Processes 4
shimonv Document Control Procedure Header Content Document Control Systems, Procedures, Forms and Templates 3
A Document release vs its related training. Which should come first? ISO 13485:2016 - Medical Device Quality Management Systems 18
Q Document ownerships Document Control Systems, Procedures, Forms and Templates 14
E Document Change Request forms (or no forms)? ISO 13485:2016 - Medical Device Quality Management Systems 9

Similar threads