Hi Marc:
Long time no "see".

I requested a copy of the changes from AIAG (attached as Word document). Here also is a text version of the 3rd edition changes. My main gripe as an auditor has been addressing not only high RPNs but also those with high severity which the 3rd edition now more clearly recognizes (yes, there is a God):
3rd Edition
Design
FMEA – Introduction
· In the Team Effort section, the technical/physical limits of product maintenance (service) is given consideration.
Design FMEA – Development of a Design FMEA
· Detailed discussion of system, subsystem, and component in item 2 with an associated appendix (Appendix F) that provides descriptions and examples.
· For the severity ranking, the ranking used is the most serious for a given failure mode. If a failure mode has numerous effects, only the most serious matters.
· Two notes added to discussion of severity ranking.· Additional examples of typical causes of failure provided.
· Occurrence table changed to failures per thousand vehicles/items.
· Only two types of design controls are recognized:§ Prevention§ Detection
· For design controls, the form has been changed to provide for separate columns to record controls. One column is to be used to record prevention controls, the other column is for detection controls.
· The one column form for controls is still included in the appendix, however, use of the two column form for controls is the preferred approach.
· The example used has been changed to reflect the two columns for controls.
· To determine the detection ranking, only detection controls are considered.
· For recommended actions, focus first on high severity and then on high RPN.
· Intent of actions is to first reduce the severity ranking then the occurrence ranking then the detection ranking.
Process FMEA – Introduction
Process FMEA – Development of a Process FMEA
· For Key Date, a note has been added for suppliers that recognize a due date at scheduled start of production is too late. The latest the due date could be for a supplier is the customer required PPAP submission date.
· In item 9, Process Function/Requirements, it is recommended to record the associated process/operation number for the step being analyzed.
· Additional examples of typical failure modes have been provided.
· In item 10, Potential Failure Mode, a note has been added that provides guidance on recording potential failure modes.
· For the severity ranking, the ranking that is used is the most serious for a given failure mode. If a failure mode has numerous effects, only the most serious matters.
· Severity table has been changed to recognize effects for both internal and external customers.
· A note has been added to the severity section.
· Additional examples for causes of failure have been provided.
· Occurrence table changed to failures per thousand vehicles/items.
· Appendix (Appendix I) provided with associated Ppk values to assist team in determining the occurrence ranking.
· Only two types of process controls are recognized:§ Prevention§ Detection
· For process controls, the form has been changed to provide for separate columns to record controls. One column is to be used to record prevention controls, the other column is for detection controls.
· The one column form for controls is still included in the appendix, however, use of the two-column form for controls is the preferred approach.
· The example used has been changed to reflect the two columns for controls.
· To determine the detection ranking, only the detection controls are considered.
· Detection table provides additional detail to assist the team in determining the detection ranking.
· For recommended actions, focus first on high severity and then on high RPN.
· Intent of actions is to first reduce the severity ranking then the occurrence ranking then the detection ranking.
Process FMEA – Follow Up
· Methods to use to ensure that concerns have been identified and actions implemented have been included.
Appendices
· Design FMEA Quality Objectives and Process FMEA Quality Objectives have been added as appendix A and B respectively.
· Both one column and two columns forms for controls are included.
· An appendix (Appendix F) has been added that provides information concerning the interfaces and interactions among systems, subsystems, and components.
· An appendix (Appendix I) has been added that includes a Ppk column for the Process FMEA occurrence table. It also includes sample calculations.
Best Regards,
Pete