Hello people,
I am currently proceding with implementing AS9100 from ISO9001.
Can anyone clarify:
"7.2.2 d) risks (e.g., new technology, short delivery time scale) have been evaluated."
We currently use a contract review checksheet for the review of requirements, is this a case of an addition to the contract review, or could this be a bit of a minefield?
If anyone can push me in the right direction, I would be grateful.
Thanks
Chris:)
 
Elsmar Forum Sponsor
D

D.Scott

#2
Hello people,
I am currently proceding with implementing AS9100 from ISO9001.
Can anyone clarify:
"7.2.2 d) risks (e.g., new technology, short delivery time scale) have been evaluated."
We currently use a contract review checksheet for the review of requirements, is this a case of an addition to the contract review, or could this be a bit of a minefield?
If anyone can push me in the right direction, I would be grateful.
Thanks
Chris:)
As in all standards, don't overkill it. Keep it simple. Add the evaluation of risks to your current contract review. The key is that it be addressed and be done before commitment to supply a product.

Note the review is a "Key Requirement". Be sure your current checklist addresses the a,b and c as well. Then you can add the d portion.

Dave
 
A

AS_QualityEngineer

#3
Hello people,
I am currently proceding with implementing AS9100 from ISO9001.
Can anyone clarify:
"7.2.2 d) risks (e.g., new technology, short delivery time scale) have been evaluated."
We currently use a contract review checksheet for the review of requirements, is this a case of an addition to the contract review, or could this be a bit of a minefield?
If anyone can push me in the right direction, I would be grateful.
Thanks
Chris:)
Identify the Risk and prepare Mittigation Plan. Follow the stages:

- Risk Identification – Identify risks through discussion with all major stakeholders.
- Risk Categorization – Group the risks into categories
- Risk Probability and Impact Assessment – For each risk identified, assess the risk event in terms of likelihood of occurrence (Risk Probability) and its effect on project objectives if the risk event occurs (Risk Severity = Impact Score). This information will be used to prioritize the risk using established threshold criteria.
- Risk Prioritization - Risks that meet the threshold criteria will be so noted in the Risk Register. These Risks will be prioritized.
- Risk Response Planning – For each risk in the Risk Register that is above the Risk Threshold:
- Determine the options and actions to reduce the likelihood or consequences of impact to the project’s objectives
- Determine the response based on a cost/benefit analysis (cost vs. expected effectiveness)
- Describe the actions to be taken to mitigate the risk
- Describe the Signs and Symptoms that may be indicators of Risk Event occurrence
- Describe the actions to be taken when the risk event occurs (contingency plan)
- Assign responsibilities for each agreed-upon response
- Assign a “due date” where risk responses are time-sensitive
- Determine impact on project budget and schedule and make appropriate changes or additions to the project plan.
- Incorporate this information into the Risk Register
 
Last edited by a moderator:

DannyK

Trusted Information Resource
#4
The way you would address the risk requirement depends on the complexity of what you will be delivering. If it is a new system that you are responsible for designing is different than if you are delivering a part within your capabilities.

Usually companies look at delivery, technological, and price risks. They have a checklist for new jobs and for repeat jobs.

I would suggest you keep the risk assessment simple.
 

Sidney Vianna

Post Responsibly
Leader
Admin
#5
If anyone can push me in the right direction, I would be grateful.
This might be a very complex issue. No single answer fits all scenarios.

Ask Airbus about the consequences of the harness configuration risks for the A380 program. Ask Boeing about the risks of outsourcing tremendous amount of complex engineering work, which used to be done in house, associated with the fact that the 787 programs brings a boat-load of new technologies.

Both organizations use 9100 certified suppliers. Do you think their suppliers did an effective risk assessment of these two new programs? A single sentence in AS9100 might lead to tremendous amount of work. But if you don't want to disappoint your customers with (up to) 24 month delivery delays, such work needs to be done. And in a serious manner.
 

howste

Thaumaturge
Trusted Information Resource
#6
As Sidney suggests, risk management is being increasingly emphasized in the aerospace world. In the text of the current version of AS9100 risk is only mentioned once. In the latest draft version, it's mentioned 16 times.

By the end of the year when the new version of AS9100 is released, there will be a new Risk Management clause (7.1.2) in the standard. Take a peek at the proposed changes in a draft AS9100 version. The final version should be similar to this.
 

Sidney Vianna

Post Responsibly
Leader
Admin
#7
By the end of the year when the new version of AS9100 is released, there will be a new Risk Management clause (7.1.2) in the standard. Take a peek at the proposed changes in a draft AS9100 version. The final version should be similar to this.
Howste, it was good to see you again, last week. Too bad you missed the second day of the workshop. Note that I posted a copy of the presentation on the 9100 changes in this post. It was an interesting discussion.
 

howste

Thaumaturge
Trusted Information Resource
#8
Howste, it was good to see you again, last week. Too bad you missed the second day of the workshop. Note that I posted a copy of the presentation on the 9100 changes in this post. It was an interesting discussion.
It was great to see you too, Sidney. :agree1: I was hoping they'd go over the changes on Monday, but alas... Fortunately I did get the flash drive with the presentations before I had to go.
 
Thread starter Similar threads Forum Replies Date
W Evidence for Review of Requirements - AS9100 Clause 7.2.2 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
E AS9100 7.2.2 Review of Requirements Related to the Product AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
M AS9100 7.2.2 Review of Requirements - Order & Product Review Records AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
O Management Review Inputs and Outputs - AS9100 Registration Audit Requirements Management Review Meetings and related Processes 16
J KPI's for AS9100 Cl. 8.2/8.5 - Bids/Contract Review/Order Entry AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
W Checklist for AS9100 Clause 7.2.2 Review Of Requirememts Related to Product AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
M AS9100 5.6.2(c) Review Input: Process Performance - Detailed explanation needed AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
M Management Review - AS9100 Clause 5.6.3 Review Output AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
J Corrective Action Review - AS9100 Rev. C Requirement AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
F AS9100 Management Review NCR help - Output of the MR is not Adequate AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
K AS9100:2009 Process Checklist (Contract Review) - Feedback wanted Contract Review Process 4
R Does AS9100 require that QA review all POs before release AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
P AS9100 Contract Review - Can the Sales Manager be the process owner? Contract Review Process 4
G AS9100 - 7.2 Contract Review - How others do Contract Review in a documented fashion Contract Review Process 7
Kevin Walters AS9100 and AS9120 AATT Course and Test AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B AS9100 Calibration Register AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Crusader ASQ AS9100 Lead Auditor Training Career and Occupation Discussions 27
9 AS9100 Friendly ERP Recommendations Misc. Quality Assurance and Business Systems Related Topics 1
dpenbert AS9100 7.5.3 - Manual Document Control AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
D AS9120 to AS9100 due to value added activities AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
P Can I exempt products/services from my AS9100 QMS? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
P AS9100 and CAMO - Continuing Airworthiness Management Organization AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
K AS9100 - Looking for advice on how to become a CB Auditor AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
D AS9100 Rev D - Clause 8.7 Control of Non conforming outputs AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
D AS9100 VS IATF 16949 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
W AS9100 Shelf Life Extension or Exemption AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
J Merging two AS9100 Companies: how to manage interim period AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
L AS9100 Section 8.4.2 - External provider test reports AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
M Can we combine AS9100 and DO-254 certification? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
O Should a Covid vaccine and testing policy be included as part of ISO9001 or AS9100 risk management? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
A AS9100 - 7.1.5.2 In-House Calibration AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 25
H AS9100 D - 8.1.2 Configuration Management for Build-to-Print Service Provider AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
M Transferring AS9100 to new Legal Entity AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
M Lapse in AS9100 Certificate AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
D AS9100 News AS9100 Rev. E? Any news? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
M Software verification and validation AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Z AS9100 Control of Nonconforming Outputs - Rework Dispositions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
briteme4 ASL - AS9100 / Supplier Survey Supplier Quality Assurance and other Supplier Issues 3
Crusader AS9100 7.5.2 NOTE Approval methods identified AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
A Can a organization use a disclaimer "pending AS9100 Certification" in Marketing Information? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
R AS9100D internal audit checklist or ISO 9001 2015 to AS9100 D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
T AS9100 audit due to facility move AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
K AS9100 and ISO9001 together AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
M Do AS9100 Registrar Auditors have nonconformity quotas? General Auditing Discussions 45
L Heading dies as "tooling" and AS9100 Manufacturing and Related Processes 2
L Heading dies as "tooling" and AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
F AS9100 - Validation, FAIR's, ITAR and Sub-Contracting AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
L AS9100 - Product and Service Provision 8.5.1q AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
T Temperature Requirements For In House Calibration - AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 16
T What does AS9100 mean when it says you must establish a process to do X? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 24

Similar threads

Top Bottom