AS9100 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

B

bigbirdy

#1
Hi! Guys,

I am wondering if somebody could explain the intent of 7.5.1 ( Control of production and service provision) clauses f and g ? Also, How do you audit planning .

Thanks a Lot

Big Birdy:)
 
Elsmar Forum Sponsor

Marc

Fully vaccinated are you?
Leader
#3
Re: 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

Another quick "Bump". Can anyone help with this? My thanks in advance!
 
T

TrishDish

#4
Re: 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

My company received an audit finding last week during an annual customer audit of our system. The auditor reviewed 5 completed job traveler packages and noticed that on some of them the physical count recorded at various operations did not match the original planned count (it was more). At the final operation there was an accounting of all the produced pieces, example - 10 pcs ordered by the customer, 12 pcs made, in the end 10 pcs sent to the customer and 2 pcs sent to stock. However, when the "extra" pcs were made early on in the production process the auditor saw no statement of rationale for the overage pcs from the original order and therefore gave us a finding against the requirement in AS9100C, 7.5.1, g). I gathered the auditor wanted to see the original count lined out on every single follow on operation.
Does anyone out there think this requirement might have been misinterpreted by the auditor or have some recommendations on how to resolve our issue? If the original planning called for, say 10, and along the way additional parts were fabricated and recorded on the job traveler, why would it be necessary to go through the entire paperwork traveler and "correct" the original job count?
Help! and thank you in advance
 
J

Jason PCSwitches

#5
Re: 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

My company received an audit finding last week during an annual customer audit of our system. The auditor reviewed 5 completed job traveler packages and noticed that on some of them the physical count recorded at various operations did not match the original planned count (it was more). At the final operation there was an accounting of all the produced pieces, example - 10 pcs ordered by the customer, 12 pcs made, in the end 10 pcs sent to the customer and 2 pcs sent to stock. However, when the "extra" pcs were made early on in the production process the auditor saw no statement of rationale for the overage pcs from the original order and therefore gave us a finding against the requirement in AS9100C, 7.5.1, g). I gathered the auditor wanted to see the original count lined out on every single follow on operation.
Does anyone out there think this requirement might have been misinterpreted by the auditor or have some recommendations on how to resolve our issue? If the original planning called for, say 10, and along the way additional parts were fabricated and recorded on the job traveler, why would it be necessary to go through the entire paperwork traveler and "correct" the original job count?
Help! and thank you in advance
I'm curious as to how you responded in the auditors presence?

You state that everything was recorded on the traveler, which if so is accountability and satisfies "f". As far as building the extra 2 pcs. what was the purpose? You don't need to justify building extra pcs., though it would be wise if this is a standard practice to have something in your procedures that makes a reference to excess production.

Some might say that the w/o was for 10 pcs. and you made more than that so you didn't conform to plan arrangement's. That's desk-jockey thinking in my book. Often times a certain % of an order is overrun to allow for any fallout or safety stock. Again, I would review the process and determine if this was isolated or standard practice.

As long as you have traceability & everything is documented I don't see an issue. Maybe he didn't like your coffee!!
 
#6
Re: 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

I also don't see anything wrong with your approach. I don't see how 7.5.1 f even fits the scenario. It sounds like you have accounted for all product during production. You made two extra parts and you kept a record of it.

You should challenge this finding. If nothing else you will get a better explanation (although I don't see how).

One very good reason for challenging bad findings is that it is very hard to come up with an appropriate root cause and corrective action when you can see no value or benefit to the exercise. You could end up getting dinged for an ineffective response because you can't see how to get an effective one.
 

dsanabria

Quite Involved in Discussions
#7
Re: 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

Hi! Guys,

I am wondering if somebody could explain the intent of 7.5.1 ( Control of production and service provision) clauses f and g ? Also, How do you audit planning .

Thanks a Lot

Big Birdy:)
If you could provide a scenario to identify the actual question that you are facing - then a more precise answer or explanation can be provided.

Auditing Planning is part of the process approach - Planning could mean different items to different company and how they approach it. Most companies are using the process approach (inputs / outputs) and the requirements of the standard.
 
B

bigbirdy

#8
Re: 7.5.1.F and 7.5.1 G Intent - Control of Production and Service Provision

I just want to get some ideas, what questions to ask and what other areas I need to look to satisy this requirement.

Thank you very much for all the help!!
 

Mikishots

Trusted Information Resource
#9
Some things you can check for:

See if quality control stamps or signoffs were noted in the appropriate areas on each of the sampled WO’s.

See if acknowledgement and sign off of part qty’s and non-conforming product were noted on the sampled work orders on the floor.

Are individual parts required to make up the assembly attached in the work order? Are any required batch numbers present? Is there WO traceability for parts on pick lists?

Ensure that any required split work order and non-conformance instructions are available.

Item f) reinforces an earlier requirement covered in Subclause 7.2.1 a) and asks you to control the implementation of release for delivery and post-delivery activities, as well as the release activities for the products/services you are selling.
 
Last edited:
D

dbaca0903

#10
We recently had a customer come to our facility and perform a product audit. Everything went well, but he wrote us up for 7.5.1g. My issue is that he calls out the example in the section. He was hung up on split orders in particular. We maintain product accountability throughout the entire process, but because we didn't have anything about split orders, he wrote up a SCAR. Is it correct to write up a corrective action siting an example?
 
Thread starter Similar threads Forum Replies Date
Q AS9100:2016 D - Intent of 8.4.3 (K) - Implement QMS AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
Sidney Vianna Informational New IAQG Document - AS9100 Clarifications of Intent AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
T AS9100 Process Sequence and Interaction Map Example AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
T Document Approver System AS9100 Doc Control AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Sam.F ISO9001/AS9100 Software Quality Assurance and Compliance Software Tools and Solutions 1
L Collateral Duty Inspectors - Ok for AS9100? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
C Production not following AS9100 std AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
T Process Sequence and Interaction Map AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
B AS9100 applicability to aircraft operation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
S Supplier AS9100 certificate suspended - still ship goods ? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
S Pros and cons to transition to AS9100 for non aerospace company AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
B AS9100 Certification Audit Accounting for Additional Customer QMS Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 15
Q AS9100 Facility Relocation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
J Do we need to raise concessions for every noted deviation under AS9100 Manufacturing and Related Processes 3
S Minimum Retention Time for Records of internal audit results as per AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
PowerJunkie Cancelling AS9100 Certification - How and Who to notify? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
M Exclusions allowed in AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
M Minimum/ mandatory core processes AS9100 Process Maps, Process Mapping and Turtle Diagrams 6
M Lack of qualified AS9100 Auditors AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 18
F AS9100 and FAIR - When to do them AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
P AS9100 and Raw Material Traceability AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
B AS9100:D - Purchase Order required if ordering paint on supplier portal? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
E Calibration Records during AS9100 Audit AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
M AS9100 examples of procedures, quality manual, etc. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
H Does this clause mean i must be in compliance with AS9100 or is 9001 enough? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
O AS9100 8.4.3 Supplier Terms and Conditions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
S AS9100 Supplier Audit Checklist example AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B AS9100 Design Authority questions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Q AS9100:D Counterfeit internal audit questions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Q AS9100 Counterfeit Parts Prevention/Mitigation Work Instruction? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
B SPOC 001/SPOC 002 AS9100 FAIR REQUIREMENTS AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
D Do all products fall under scope of AS9100? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Kevin Walters AS9100 and AS9120 AATT Course and Test AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B AS9100 Calibration Register AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Crusader ASQ AS9100 Lead Auditor Training Career and Occupation Discussions 27
9 AS9100 Friendly ERP Recommendations Misc. Quality Assurance and Business Systems Related Topics 1
dpenbert AS9100 7.5.3 - Manual Document Control AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
D AS9120 to AS9100 due to value added activities AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
P Can I exempt products/services from my AS9100 QMS? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
P AS9100 and CAMO - Continuing Airworthiness Management Organization AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
K AS9100 - Looking for advice on how to become a CB Auditor AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
D AS9100 Rev D - Clause 8.7 Control of Non conforming outputs AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
D AS9100 VS IATF 16949 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
W AS9100 Shelf Life Extension or Exemption AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
J Merging two AS9100 Companies: how to manage interim period AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
L AS9100 Section 8.4.2 - External provider test reports AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
M Can we combine AS9100 and DO-254 certification? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
O Should a Covid vaccine and testing policy be included as part of ISO9001 or AS9100 risk management? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
A AS9100 - 7.1.5.2 In-House Calibration AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 25
H AS9100 D - 8.1.2 Configuration Management for Build-to-Print Service Provider AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1

Similar threads

Top Bottom